Resolved
RESOLVED that arrangements be made for the Board to visit the Sutton Courtney MRF.
Joint Waste Disposal Board decided this item on Friday 16 October 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that arrangements be made for the Board to visit the Sutton Courtney MRF.
2.1That Members note the contents of this report.
3.1Not applicable.
4.1This report contains no decisions for Members, only information items.
5 BACKGROUND INFORMATION
Street Sweepings
5.1In 2012, the Environment Agency (EA) provided a clarification of guidance on the waste management processing of street sweepings and gully arisings. The clarification stressed that such material should not be incorporated into a composting process and could not be recorded as being ‘recycled’.
5.2The immediate impact of the clarification was significant. In terms of performance the clarification meant a reduction in recycling rate of <3.5%. In terms of financial cost for the re3 councils, it meant an increased cost of disposal of c£150,000.
5.3Along with many other councils, the re3 partnership unsuccessfully sought to challenge the clarification. Since then, officers have sought an alternative and available process by which to treat street sweepings.
5.4The re3 Project Team has recently been in discussions with the EA in order to seek confirmation on two emergent processing options. Alongside the necessity for cheaper processing of this material, it is also extremely important that the process will qualify as ‘recycling’ or ‘recovery’ in relation to our statutory reporting.
5.5The clarification received by the re3 Project Team from the EA shows that elements of the composition of street sweepings will be ‘recycled’, such as sand and gravel, while other elements are likely to continue being ‘disposed’ of.
5.6Street sweepings are composed of a range of different materials. A trial is commencing in early October in order to determine the exact processing requirements for re3 street sweepings. The trial will also allow the individual councils and their street sweeping teams to make necessary changes in operational practice (e.g. handling and ultimate delivery of street sweepings to the re3 facilities). OFFICIAL
5.7Once the trials are complete, and subject to any operational amendments that are deemed necessary, it is expected that the new reprocessors will continue to receive street sweepings from the re3 area.
5.8Information on the likely impact of this new initiative will be gleaned from the trial and the re3 Project Team will report back on the likely savings and performance implications.
Re3 Material Reclamation Facility (MRF)
5.9The re3 MRF has recently processed 200 tonnes of mixed recyclable material from another of the Contractor’s contracts. This opportunity was a temporary one, providing contingency cover. The processing of third-party material by the Contractor reflects the willingness of the councils’ JWDB for utilisation of the re3 facilities to increased. As an opportunity to learn what implications there are from processing additional material it has been worthwhile. The outcomes and learning are being assessed and will be reported.
5.10As part of the ongoing maintenance of the re3 MRF, a short period of enforced shutdown is planned for November 2015. Works to replace the steel conveyor chains from the bag splitter will take 7-10 days - though expected to affect only a single working week. Other preventative maintenance is also being carried out during this period. The Contractor is planning to hold re3 material, rather than send recyclables to be processed elsewhere.
Sutton Courtenay MRF
5.11The re3 Project Team have been in discussion with our Contractor, FCC, for some time on the subject of processing re3 material through the FCC MRF at Sutton Courtenay. Commissioning and capacity issues have thus far delayed the prospect of re3 material being processed by the facility.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Partnership Progress ReportReport | 66 KB | DownloadRead as text |
Follow Joint Waste Disposal Board at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Jun 2026 | Election of ChairRESOLVED that Councillor Finn McGoldrick be elected Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | Election of Vice-ChairRESOLVED that Councillor Stephen Newton be elected Vice-Chair of the Board for the municipal year 2026/27. | Decided | Open |
| 11 Jun 2026 | re3 Progress ReportRESOLVED that 1 the contents of this report be noted. 2 a proposal on the simplification of the DIY charging structur... | Noted | Open |
| 11 Jun 2026 | re3 Strategy ReportRESOLVED that 1 the re3 Strategy 2026–2031 be approved and progressed through each partner council’s decision-making ... | Approved | Open |
| 11 Jun 2026 | re3 Finance Report - part oneRESOLVED that the year end financial position for FY25/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.