RESOLVED that: i. the School Sponsor Appointment Plan for the new school to the north of Amen Corner be endorsed. ii. the updated timeline for the appointment of a school provider for the new school at Amen Corner North (Annex 1 of the Director of Children, Young People and Learning’s report) be noted.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
2.1To endorse the School Sponsor Appointment Plan for the new school to the north of Amen Corner. 2.2 To note the updated timeline for the appointment of a school provider for the new school at Amen Corner North (Annex 1).
Reasons for recommendations
3.1In order for the scheme to progress, Executive endorsement is required.
Alternative options considered
4.1Not applicable. The Executive is best placed to make the decision on providers to recommend to the Regional Schools Commissioner.
5 SUPPORTING INFORMATION
5.1The process for identifying a sponsor for a new school in the Borough is, in broad terms, for the Council to advertise the opportunity, for potential sponsors to make their proposals, which are scored and evaluated by the Council before a recommendation is made to the Regional Schools Commissioner (RSC) of the preferred provider. The RSC will make the final decision, taking into account the Council’s preference.
5.2It should be noted that detailed arrangements in relation to the appointment process overall are recommended for revision in a separate paper to the Executive on 17 November 2015. The Executive should also note that the responsibility for making decisions on sponsors to be appointed has changed from the Secretary of State to the Regional Schools Commissioner.
5.3The exercise to seek a sponsor for Amen Corner North will now run concurrently with the exercise for the Binfield Learning Village. The updated timeline is attached as Annex 1. The Executive should note that the timelines are based on the house build trajectories expected at the current time. These are outside the Council’s control and timings may subsequently be affected, in particular regarding implementation and opening dates. Unrestricted
6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS
Borough Solicitor
6.1Although the decision whether to enter into Academy arrangements with a sponsor rests formally with the Regional Schools Commissioner, he may consult with the local authority and be informed by its views when considering proposals made.
Borough Treasurer
6.2The Borough Treasurer is satisfied that no significant financial implications arise from the proposals set out in the supporting information.
Equalities Impact Assessment (EIA)
6.3An EIA is attached as Annex 2.
Strategic Risk Management Issues
6.4The main risks identified are:
Table 1: Key strategic Risk Management Issues
ISSUE RISK COMMENT Need to continually pay strict attention to timescales and maintain effective liaison with Not meeting timescales RSC/DfE. Programme 1 will jeopardise Simplify processes where Risk implementation. possible. Increase contingency in the process.
Gap in revenue funding in the initial years Scenario modelling can raise 2 Cost Risk following the school’s awareness and minimise risk opening. Extra costs could Need to maintain effective 3 Cost Risk emerge since we are liaison with DfE/RSC dependent upon the DfE. RSC not appointing the Need effective liaison with 4 Sponsor Risk sponsor recommended RSC and provide robust by the Council. recommendations to the RSC Successfully delivering Need to establish good the school if the sponsor relationships and effective 5 Sponsor Risk does not engage with the communications with the Council. sponsor appointed.
Background papers
Executive report, 11 June 2013, ‘Procedures for assessing applications for the establishment of a new school in Bracknell Forest’ Unrestricted
Department for Education, ‘The free school presumption; Departmental advice for local authorities and new school proposers’, July 2015
Contacts
David Watkins Chief Officer Strategy, Resources & Early Help 01344 354061 [email protected]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.