Capital Budget 2016/17

Agreed Executive 2 papers

Executive agreed this item on Tuesday 23 February 2016. Below is the council's own wording, with the papers it was decided on.

Item32a

Resolved

RESOLVED that the Executive: i. Recommends to the Council General Fund capital funding of £59.983m for 2016/17 in respect of those schemes listed in Annexes A – E of the Borough Treasurer and Chief Executive’s report. The inclusion of an additional budget of £1m for Invest to Save schemes. The inclusion of £2.440m of expenditure to be funded from S106 as outlined in paragraph 5.33. of the Borough Treasurer and Chief Executive’s report. That those schemes that attract external grant funding are included within the Capital Programme at the level of funding received. ii. Agrees that capital schemes that require external funding can only proceed once the Council is certain of receiving the grant. iii. Reviews the indicative programme for 2017/18 and 2018/19 in the light of resources available and spending priorities in December 2016.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendations

That the Executive:

2.1Recommends to the Council

a) General Fund capital funding of £59.983m for 2016/17 in respect of those schemes listed in Annexes A – E. b) The inclusion of an additional budget of £1m for Invest to Save schemes. c) The inclusion of £2.440m of expenditure to be funded from S106 as outlined in paragraph 5.33. d) That those schemes that attract external grant funding are included within the Capital Programme at the level of funding received. 2.2 Agrees that capital schemes that require external funding can only proceed once the Council is certain of receiving the grant.

2.3Reviews the indicative programme for 2017/18 and 2018/19 in the light of resources available and spending priorities in December 2016.

Reasons for recommendations

3.1The reasons for the recommendations are set out in the report.

Alternative options considered

4.1The alternative options are considered in the report. 5 SUPPORTING INFORMATION

Capital Resources

5.1Each year the Council agrees a programme of capital schemes. In the past these schemes have been funded from three main sources:

 the Council’s accumulated capital receipts  Government Grants  other external contributions

5.2The Local Government Act 2003 brought in radical changes to the financing of capital expenditure and from that date, the Government no longer issued borrowing approvals. Instead, under a new “prudential framework”, Councils can set their own borrowing limits based on the affordability of the debt.

5.3As the Council’s accumulated capital receipts have been fully utilised, the Council returned to a position of internal borrowing in 2010 and as such a revenue contribution is required each year to repay this internal borrowing. Once the Council’s current level of investments is exhausted the Council will need to borrow externally.

5.4The Council’s estimated total usable capital receipts at 31st March 2016 are zero. As a debt free authority the Council is partly reliant on capital receipts to fund its capital programme, although interest generated from capital receipts can also help support the revenue budget in the short term. The Council still receives a share of any Right-To-Buy proceeds from Bracknell Forest Homes in addition to a share of capital receipts from the VAT Shelter scheme.

5.5The proposed capital programme for 2016/17 has been developed, therefore, on the assumption that it will be funded by a combination of Government grants, other external contributions and borrowing in addition to £5m of capital receipts. With such a large programme there is a likelihood that the Council may need to borrow externally however this will depend largely on the progress made at Binfield Learning Village, Coral Reef and the availability of cash balances held throughout the year. Internal resources will be used in the first instance and borrowing from external sources (eg the PWLB or the Green Investment Bank) will be used when necessary. The financing costs associated with the General Fund Capital Programme have been provided for in the Council’s revenue budget plans which also appear on tonight’s agenda.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget 2016/17Report 295 KB DownloadRead as text
PDF
Capital Programme Annexes A-EAppendix 19 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
PB
Councillor Paul Bettison CONChair, present
DG
Councillor Dr Gareth Barnard CONVice-Chair, present
DB
Councillor Dale Birch CONCommittee Member, present
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
PH
Councillor Peter Heydon CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
CT
Councillor Chris Turrell CONCommittee Member, present
KS
Katharine SimpsonClerk, expected

On this subject at Bracknell Forest

Search all
  1. Capital Budget 2016/17This decision
  2. Capital Budget 2016/17Approved
  3. Capital Budget 2015/16Approved
  4. Draft Capital Budget 2015/16Approved
  5. Capital Budget 2013/14Agreed

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open