Executive, Tuesday 14 February 2017 at 5.00pm

Transformation Programme - Leisure Review Procurement Plan

Approved Executive 1 paper

Executive approved this item on Tuesday 14 February 2017. Below is the council's own wording, with the papers it was decided on.

Item73

Resolved

RESOLVED that the Procurement Plan for the market testing and potential outsourcing of the three major leisure sites outlined in the report be approved.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Recommendation

2.1That the Procurement Plan for the market testing and potential outsourcing of the three major leisure sites is approved.

Reasons for recommendation

3.1The Leisure review forms part of the Council’s wider Transformation Programme and has been exploring the ways in which the savings target of £1m could be achieved. It has been identified that the outsourcing of these three major sites could result in a saving in the region of £650,000. The Plan Phase Gateway review held on 8 December 2016 saw members support the direction of travel to market test these sites, and also support the Heads of Terms upon which any agreement with a contractor will be based.

3.2In line with the Contract Standing Orders it is required that procurement plans over the value of £400k require sign off by the Director and Executive Member. However, in light of the significant nature of this procurement the approval of The Executive is sought in respect of this procurement plan.

Alternative options considered

4.1Various sourcing options were considered during the Analyse Phase of the review including retaining the service in-house and cessation of the services but the current proposal was the proposed way forward.

5 SUPPORTING INFORMATION

5.1The leisure review is led by the Director of Environment, Culture and Communities, supported by a Project Board involving managers from outside the leisure field who can contribute to the review and external specialist advisors, Activist. The project has reviewed the performance of the Council’s leisure offering within the borough and examined the financial position associated with operating the leisure facilities at all leisure sites.

5.2The recommendations from the Gateway Review was to market test the three major leisure sites based on the Heads of Terms supported by Members who attended. Unrestricted

Those Heads of Terms are the framework for detailed specifications and contract terms which are in the process of being finalised.

5.2As this is above the OJEU threshold, the opportunity to tender will be advertised on OJEU as well as the South East Business Portal and Contracts Finder.

5.3The cost quality split is shown in the procurement plan.

5.4The anticipated timetable for the procurement process will be as follows:

Task DATE

Procurement Plan Sign Off 21 February 2017

Project advertised on the S.E Business Portal 1 March 2017

PQQ response deadline 31 March 2017

PQQ evaluation process complete 13 April 2017

ITT issued 14 April 2017

ITT response deadline 13 July 2017

Evaluation Process Complete October 2017

Executive decision to award November 2017

Contract award December 2017

Contract start date 1 March 2018

6 ADVICE RECEIVED FROM STATUTORY AND OTHER OFFICERS

Borough Solicitor

6.1Legal comments have been made in the Procurement Plan.

Borough Treasurer

6.2The financial implications of the procurement exercise are set out under section 5 of the Procurement Plan. The costs of the exercise will be met from the Transformation Programme.

Equalities Impact Assessment

6.3Attached as Annex A to the Procurement Plan.

Strategic Risk Management Issues Unrestricted

6.4Key risks and issues identified within the Procurement Plan itself.

Consultation

Principal Groups Consulted

7.1The Analyse Phase gateway Review was held on 14 July 2016 where members were asked to support a number of recommendations, one being that the outsourcing of the three major sites be considered in further detail.

A member workshop was help on 2 November 2016 and a staff workshop on 3 November 2016; the feedback received from these sessions has informed the formulation of the Heads of Terms.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transformation Programme: Leisure Review Procurement PlanReport 210 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
PB
Councillor Paul Bettison OBE CONChair, present
DG
Councillor Dr Gareth Barnard CONVice-Chair, present
DB
Councillor Dale Birch CONCommittee Member, present
MB
Councillor Marc Brunel-Walker CONCommittee Member, present
MD
Councillor Mrs Dorothy Hayes MBE CONCommittee Member, present
PH
Councillor Peter Heydon CONCommittee Member, present
IM
Councillor Iain McCracken CONCommittee Member, present
CT
Councillor Chris Turrell CONCommittee Member, present
PP
Priya PatelClerk, expected

On this subject at Bracknell Forest

Search all
  1. Transformation Programme - Leisure Review Procurement PlanThis decision
  2. Transformation Programme - Libraries Stock Management RestructureNoted

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies