Resolved
RESOLVED that the proposed pricing in appendix A of the agenda papers be agreed and that the detailed capital position in confidential annexe C of the agenda papers be noted.
Executive agreed this item on Tuesday 6 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the proposed pricing in appendix A of the agenda papers be agreed and that the detailed capital position in confidential annexe C of the agenda papers be noted.
1.1To update the Executive on current progress with the Coral Reef enhancement project, preparations for opening and agreeing proposed pricing for the facility.
2.1That the Executive agrees the proposed pricing in appendix A
2.2That the Executive note the detailed capital position in confidential annexe C
3.1As the Coral Reef enhancement project nears completion the Executive can be briefed on more detailed plans related to the reopening of the facility. As per the Council’s constitution, the Executive also needs to approve the proposed charges for entry.
4.1Not applicable
5 SUPPORTING INFORMATION
5.1Construction update (Photographs in appendix B up to 1st week May 2017)
Construction started Coral Reef complete
20th June 2016 Late August
Due to the replacement roof required on Sauna World this element of the project is approximately 3 weeks behind the main programme. Opening date for facility is yet to be confirmed.
5.1.1 The construction on site is drawing to a close and preparations are well advanced in relation to opening. Current construction progress is good and remains on programme. Areas that are currently (1st week of May 2017) being worked on are –
Reception and toilets – furniture has been installed and floor tiling progressing well. Sanitary ware installation is progressing
Coconut Grove - air handling unit installed in ceiling and catering equipment has been delivered
1 Unrestricted
Changing Village – wall tiling complete along with new floor drainage
Main pool – roof steel frame and structural deck are complete and service installation commenced
Coral Spa – demolition of old roof complete. Steel frame of new roof installed and sheeting commenced
Flume tower – superstructure complete and internal wall systems commenced along with roof structure
Flumes – installation has commenced with the run outs around the splash pool and preassembly of flume sections in car park is complete. Sections are being transported round to the rear of the site and most of the supporting flume columns have been installed
5.1.2 This has been a complex scheme and whilst the overall programme has gone smoothly there have been significant issues which arose during the build which could not have reasonably been foreseeable. These have been managed well by the contractor Brymor Construction Ltd but incurred unavoidable costs. The following is not an exhaustive list of unavoidable variations but areas that have created largest challenges have included –
During strip out, Coconut Grove ceiling was found to be structurally unsound. As a result this area required significant redesign, rebuilding and included a new air handling unit. This additional work required £115k from the contingency. This did not impact on the overall construction programme.
During strip out, Sauna World ceiling was found to be structurally unsound. This required complete demolition, redesign, and fabrication and installation of a new steel roof. This additional work required £210k from the contingency and is approximately 3 weeks behind the main programme.
On removal, parts of the internal drainage within Changing Village have been found to be not built to standard. Work was undertaken to rectify this issue and the additional work required £53k from the contingency. This did not impact on the overall construction programme.
Additional repairs were required for the Glulam beams over and above those identified in the timber repairs report. This work required £122k from the contingency.
On tile removal in changing Village significant substrate issues were discovered. This has involved re-patching walls in order that new tile can be applied successfully to a solid foundation. This additional work required £47k from the contingency but did not impact on the overall construction programme.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Coral Reef Pre-opening ReportReport | 724 KB | DownloadRead as text |
Follow Executive at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Sep 2024 | Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... | Noted | Open |
| 17 Sep 2024 | Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... | Agreed | Open |
| 17 Sep 2024 | Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. | Approved | Open |
| 17 Sep 2024 | Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... | Noted | Open |
| 17 Sep 2024 | Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.