Environment, Culture and Communities Overview & Scrutiny Panel approved this item on Tuesday 11 July 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the minutes of the meeting of the Panel held on 7 March 2017 be approved as a correct record and signed by the Chairman. Arising from minute 148 [Design Supplementary Planning Document] the Panel noted that information had been circulated to members regarding the maximum number of satellite dishes permitted on homes.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Executive Members: Councillors [name removed], McCracken and Turrell
Also Present: Andrea Carr, Policy Officer (Overview and Scrutiny) Andrew Hunter, Chief Officer: Planning, Transport & Countryside Damian James, Head of Performance and Resources Steve Loudoun, Chief Officer: Environment & Public Protection
142. Minutes and Matters Arising RESOLVED that the minutes of the meeting of the Panel held on 10 January 2017 be approved as a correct record and signed by the Chairman.
143. Declarations of Interest and Party Whip There were no declarations of interest relating to any items on the agenda, nor any indication that Members would be participating under the party whip.
144. Urgent Items of Business There were no items of urgent business.
145. Public Participation No submissions had been made by members of the public under the Council’s Public Participation Scheme for Overview and Scrutiny.
146. Contaminated Land The Panel considered a report setting out the Council’s responsibilities in relation to contaminated land in the Borough, as defined by the Environmental Protection Act 1990.
For land to be designated as ‘contaminated land’ it had to meet three criteria. Firstly, there must be an identified contaminant, secondly an identified receptor that was likely to be harmed by the contaminant should the two come in contact, and thirdly a feasible pathway by which the two could connect. The legislation provided powers for the remediation of contaminated land, whereby planning conditions could be imposed to deal with associated risks on land brought forward for development.
Local risks had been assessed through a desk top survey in 1999/2000 of historical sites where industrial or waste disposal activities had taken place. Some 2,500 potentially contaminated sites had been identified in the Borough. There were also three former local authority landfill sites in the Borough. Longhill and Longshot Lane were former landfill sites which needed active monitoring by the Council to ensure compliance with regulatory standards. The third landfill site at Strongs Heath was closed in 1998, and was managed by the Council on behalf of all the Berkshire Authorities on terms regulated by the Environment Agency. This necessitated the ongoing management of the site and monitoring of gas and leachate.
The following points arose from questions and discussion: Details of the 2,500 sites were held on the contaminated land register which was available for public inspection. Some individuals chose to obtain information via a Freedom of Information request rather than attending to inspect the public register. The Council was not required to monitor the majority of these sites since they posed no actual risk (in the context of the legal definition in the Act) Where development proposals were submitted, the Council as Planning Authority could refuse permission unless satisfactory measures were proposed to remediate the contamination or otherwise mitigate any risk to health.
Strongs Heath landfill site was designed and built as a ‘dilute and disperse’ site. It is regulated by the Environment Agency. The nature of the equipment on the site is such that it currently has to be kept secure The day to day on-site management has been outsourced to specialists who arrange for the methane from the site to be drawn off and burnt by an onsite flare and for leachate to be extracted and sent for specialist disposal.
147. Coral Reef The Head of Performance and Resources made a presentation to the Panel on the progress of the refurbishment at Coral Reef.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Culture and Communities Overview & Scrutiny Panel at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.