Environment, Culture and Communities Overview & Scrutiny Panel approved this item on Tuesday 19 September 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the minutes of the meeting of the Panel held on 11 July 2017 be approved as a correct record and signed by the Chairman. Arising from minute 163, it was reported that a very interesting and informative briefing session about Sustainable Drainage Systems (SuDS) had been held, although rather poorly attended by members. A separate session would be held for Town and Parish Councillors. Arising from minute164, the query raised at the last meeting concerning the vehicular access serving a development scheme in York Town Road, Sandhurst, remained unresolved. Officers were requested to ensure the Highways team enforced the satisfactory completion of the works by the developer without further delay.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
Report to Environment, Culture and Communities Overview & Scrutiny Panel
Unrestricted
ENVIRONMENT, CULTURE AND COMMUNITIES OVERVIEW & SCRUTINY PANEL 11 JULY 2017 7.30 - 9.25 PM
Present: Councillors Porter (Vice-Chairman), Brossard, Finnie, [name removed], [name removed], [name removed] and [name removed] for absence were received from: Councillors Angell and [name removed]: Councillor Mrs Hayes MBE and Turrell
Also Present: Andrea Carr, Overview and Scrutiny Officer Linda Gizzie, Cemetery and Crematorium Manager Andrew Hunter, Chief Officer: Planning, Transport & Countryside Damian James, Head of Performance and Resources Steve Loudoun, Chief Officer: Environment & Public Protection Vincent Paliczka, Director of Environment, Culture & Communities Councillor Peacey
153. Election of Chairman RESOLVED that Councillor Angell be elected Chairman of the Environment, Culture and Communities Overview and Scrutiny Panel for the 2017/18 Municipal Year.
154. Appointment of Vice Chairman RESOLVED that Councillor Porter be appointed Vice-Chairman of the Environment, Culture and Communities Overview and Scrutiny Panel for the 2017/18 Municipal Year.
COUNCILLOR PORTER IN THE CHAIR
155. Minutes and Matters Arising RESOLVED that the minutes of the meeting of the Panel held on 7 March 2017 be approved as a correct record and signed by the Chairman.
Arising from minute 148 [Design Supplementary Planning Document] the Panel noted that information had been circulated to members regarding the maximum number of satellite dishes permitted on homes. 156. Declarations of Interest and Party Whip There were no declarations of interest relating to any items on the agenda, nor any indication that Members would be participating under the party whip.
157. Urgent Items of Business There were no urgent items of business.
158. Public Participation No submissions had been made by members of the public under the Council’s Public Participation Scheme for Overview and Scrutiny.
159. Highways Maintenance Contract: Annual Report The Panel considered a report on the second year’s performance of Ringway Infrastructure Services Ltd (RIS), who were appointed as the Council’s Highways, Maintenance and Works Contractor on 1 October 2014.
The level of performance of the contract was monitored through the use of key performance indicators (KPI’s), which if successfully met could result in the award of an additional year on the contract. Accordingly, following another satisfactory year, the contract had been extended and the original seven year contract would now run for nine years until 2023. The continuity was to the benefit of both parties and RIS had the security to invest in the contract with confidence.
The Panel also considered the Ringway Annual Report to the Council together with a resume of the issues dealt with by the Management Board to ensure a satisfactory performance. Actions included: Measures to embed the necessary changes required in the early months of the new contract; Taking on the challenges presented by the town centre works, including working with other contractors; and Recovery of the position in relation to initial underperformance in some KPI’s to reach the required standard by the year end.
Three particular projects from 2016 were highlighted: The Coral Reef Highway Scheme and A322 Bagshot Road resurfacing The LED street lighting project The Town Centre Redevelopment works
Arising from questions and discussion, the Panel noted that the contractor had been able to deliver approximately £32k of savings through efficiencies, and that through the contractors ‘buying power’ the LED street lighting project would realise around £400k of savings. The Traffic Management target of a maximum 4% of Fixed Penalty Notices issued on permits granted would reduce from 4% to 3% for the year ahead, since the 2016 figure had amounted to just 0.74%.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Culture and Communities Overview & Scrutiny Panel at Bracknell Forest and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.