RESOLVED that i. the Council extends its Refuse Collection Contract with SUEZ for a further 8 years from 1 April 2019 based on the option appraisal as set out in A(2) of restricted Annex 1 of the Executive Director: Delivery’s report subject to current terms and conditions as need to be amended to reflect legislative change and those required in respect of operational need such as those highlighted in paras 5.15, 5.16, 5.19, 5.21, 5.25 and 5.28. ii. once the Government Strategy for Waste is produced in the Autumn, officers report back to the Executive with a review of options to introduce further changes to the collection offer.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The Council has a Contract with SUEZ that ends on 31 March 2019. The Contract includes provision for an extension for a further 8 years.
1.2This paper sets out the outcome of detailed negotiations for the extension of that Contract relative to the foreseeable needs over the next Contract Term. This paper contains fiscal information and projections as at a point of time. It informs the likely budget need based on reasoned estimates.
Recommendations
2.1That the Council extends its Refuse Collection Contract with SUEZ for a further 8 years from 1 April 2019 based on the option appraisal as set out in A(2) of restricted Annex 1 subject to current terms and conditions as need to be amended to reflect legislative change and those required in respect of operational need such as those highlighted in paras 5.15, 5.16, 5.19, 5.21, 5.25 and 5.28, and
2.2That, once the Government Strategy for Waste is produced in the Autumn, officers report back to the Executive with a review of options to introduce further changes to the collection offer.
Reasons for recommendations
3.1The Council has to renew its Waste Collection Contract from April 2019. The decision needs to be taken now because there is a long lead in for the build of a new fleet of vehicles.
Alternative options considered
4.1The option not to extend the current contract was considered. The Council had the option of bringing the service back in house should it wish to do so. Doing so would incur a significant set up cost and whilst the Council could subsequently re-tender the Contract the TUPE’d staff would have gained and secured benefits that could impact on future cost. The existing Contract was awarded following a competitive tendering process and SUEZ has evidenced the ability to deliver the required service to the required standards over the term. The Terms of the Contract have also been tested over that period of time and proven to meet the Council’s needs. SUEZ has provided an excellent service since 2011 and risk of change and the cost of re-tendering would be high and almost certainly would outweigh the likely gain on a like for like basis. Such options were therefore discounted.
5 SUPPORTING INFORMATION
Overview
5.1The current Contract includes for the collection of the Borough’s household waste; waste from some BFC schools, some Council-owned premises and a small number of external organisations such as Parish and Town Councils. The Contract commenced on 1 August Unrestricted
2011 and runs until 31 March 2019. The Terms of the Contract allow for an extension for a further 8 years.
5.2As part of the review of the arrangements the new Contract will focus on domestic collections. As a result many of the non domestic premises such as schools, Town and Parish offices are being advised that they need to make alternative arrangements. The Contract provides the means for BFC premises to access SUEZ commercial services and assistance is being offered where required. The changes will result in better control of the waste stream and less contamination. Where necessary arrangements will be made to assist in the transition particularly in schools.
5.3The number of households including flats has grown over the current Term from 46,750 in March 2011 to 49,270 in 31 March 2018. The projected demographic growth over the next Term is for a further 7,500 properties. The projections do not break down to house type and as we have seen the trend has been towards building more flats and large estates. This seems unlikely to change and both bring their own challenges that have to be considered in relation to the nature and make-up of the fleet.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.