CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bracknell Forest Council
Executive, Tuesday 17 October 2023 at 5.30pm

Bridgewell Supported Living

Noted Executive 2 papers

Executive noted this item on Tuesday 17 October 2023. Below is the council's own wording, with the papers it was decided on.

Item37

Resolved

RESOLVED that: i. the progress to date on the design development is noted and the timetable in paragraph 5.27 is agreed. ii. the value improvement items to improve sustainability in paragraphs 5.11 is noted. iii. the revised strategic procurement plan for appointment of the provider of landlord services (Housing Association) and care services (Support Provider) for the provision of scheme for adults with learning disabilities as laid out in paragraphs 5.16 to 5.20 are noted. RECOMMENDED to Council to approve the additional cost of works for the new accommodation by £400k, changing the previous budget from £7.15m to £7.55m as detailed in paragraph 5.12.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Purpose of report

1.1The purpose of this report is to provide an update to Executive on the progress of the Bridgewell Supported Living project, which was approved for delivery by Executive on 21 June 2022. Key issues relating to capital cost of the building works and the strategic procurement plan for the procurement of the a) landlord service provider and b) the care & support service provider are highlighted in this report.

1.2Planning Permission for the scheme was granted in September 2023. A decision is now required to proceed to the next stage of the project, which includes commencing the construction works and agreeing the strategic procurement plan for the service providers.

Recommendations

That the Executive:

2.1Note the progress to date on the design development and agree the timetable in paragraph 5.27.

2.2Recommend to Council to approve the additional cost of works for the new accommodation by £400k, changing the previous budget from £7.15m to £7.55m as detailed in paragraph 5.12.

2.3Note the value improvement items to improve sustainability in paragraphs 5.11.

2.4Approve the revised strategic procurement plan for appointment of the provider of landlord services (Housing Association) and care services (Support Provider) for the provision of Bridgewell Supported Living scheme for adults with learning disabilities as laid out in paragraphs 5.16 to 5.20.

Reasons for recommendations

3.1As per the rationale set out in the previous Executive report, the service is needed because without the new accommodation, a large cohort of vulnerable people are either already or will soon be living in accommodation not suited to their needs, or unable to be adapted to be suited to their needs. People have the right to suitable accommodation as well as independence. On completion of the project, residents will have an increase in independence and reduction of social isolation. They will be able to enjoy freedom and independence and are encouraged to be in control of their lives, ensuring that they are supported to manage their daily living skills to the best of their ability.

3.2The added value of Supported Living is that parents / carers are enabled to better juggle their roles in caring and paid work, leading to improved well-being, avoiding a detrimental effect on the family’s financial circumstances. Ensuring the right accommodation with a person-centred care and support package will reduce escalation to costly residential placements.

3.3Design and Build: the design and build contractor (Neilcott Construction) was appointed through competitive restricted tender in January 2023. They have developed the design and obtained planning permission. As the concept design progressed into a detailed technical specification, Neilcott obtained pricing from their supply chain, which exceeds the budget by £400k. Further details are given in paragraphs 5.9 to 5.15.

3.4Provider Model: prior to commencing procurement activity, the Commissioning team has been working with Campbell Tickell (Subject matter expert consultancy) to undertake a detailed options appraisal of each of the commissioning models available for Bridgewell. Following this review, a change to the Strategic Procurement Plan is being requested that was previously approved by Executive in June 2022.

Alternative options considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SPP EIABridgewell_Project Final_230823Appendix A 167 KB Download
PDF
Bridgewell Supported LivingReport 8.5 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
MT
Councillor Mary Temperton LABChair, present
KN
Councillor Kathryn Neil LABVice-Chair, apologies
RB
Councillor Roy Bailey LABCommittee Member, present, as expected, virtual
PB
Councillor Paul Bidwell LABCommittee Member, present
GG
Councillor Guy Gillbe LABCommittee Member, present, as expected, virtual
IJ
Councillor Iskandar Jefferies LABCommittee Member, present
HP
Councillor Helen Purnell LABCommittee Member, present
MW
Councillor Megan Wright LABCommittee Member, present
AH
Councillor Adrian Haffegee GreenAdditional Members, present

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies