RESOLVED that the Executive approves the Strategic Procurement Plan set out in Appendix A of the report to tender the services for a single organisation to provide 24 hour Building Maintenance and Reactive Repairs Services for the Councils corporate stock and buy back schools.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The purpose of this report is to seek approval to commence with the procurement process, to appoint a single organisation to provide 24 hour Building Maintenance and Reactive Repairs Services across the portfolio of buildings in Bracknell.
2. Recommendation(s)
2.1That the Executive approves the Strategic Procurement Plan set out in Appendix A to tender the services for a single organisation to provide 24 hour Building Maintenance and Reactive Repairs Services for the Councils corporate stock and buy back schools.
3. Reasons for Recommendation(s)
3.1Contract Standing Orders
The value of this agreement will exceed the relevant PCR threshold. The Contract Standing Orders explain that a contract of such value is required to go to a formal tendering process to ensure value for money and compliance with current legislation. This is to ensure a fair and non-discriminatory competitive process, and equal treatment of all potential suppliers and contractors.
3.2It is a requirement of the contract standing orders that the executive approve any strategic procurement plan with a value more than £1m. This decision seeks approval for the procurement process.
Alternative options considered
4.1Framework options were explored however, none were a suitable match.
4.2Partnerships with neighbouring authorities were considered, however, it was found that the closest authorities had different methods of operation or used DLO’s (direct labour organisations) making them unsuitable. An Inter Authority Agreement would also need to be put in place which could take a year to complete.
5. Supporting Information
5.1Current arrangement
The current contract for Building Maintenance and Reactive Repair Services contract has been in place since 3rd February 2020, which has been successfully carried out.
KPI’s have been met, which are set out within the contract and achieved good customer feedback.
The contract was based on a fixed price for the 3 years with an option to extend for a further 2 year from 2023 until 2nd February 2025. OFFICIAL SENSITIVE (COMMERCIAL)
On the 9th February 2023, the Council granted an extension to the current contractor for 1 further year, which expires on 2nd February 2024, however there is an option to extend for a further year. Based on the current provider KPI’s and performance the Council would extend the contact for a further year and therefore the contract would expire on 1 February 2025.
5.2The Portfolio
The portfolio includes Schools (that purchase a schools Service Level Agreement), Libraries, Youth & Community Centres, Children & Adult Services premises, Housing Properties, and all other buildings owned and managed by Bracknell Forest Council. There are 591 locations throughout Bracknell.
5.3Timescales
Milestone Approximate Date Publish adverts in Contracts Finder and January 2024 Southeast Business Portal Deadline for returning Selection Early March 2024 Questionnaires Issue Invitation to Tender to shortlisted May 2024 suppliers Receive Response from Tenderers July 2024 Contract Award/Preferred Bidder Late September 2024 End of standstill period Early October 2024 Mobilisation Period from November / December 2024 Contract Start Date 1st February 2025
The contract will operate for a maximum of 10 years (5+3+2) years. This is initially set for 5 years, depending on KPI performance a further 3+2 years can be awarded after the 5th year.
5.4Financial Analysis
As set out in the Strategic Procurement Plan.
5.5Contract Award
The award of contract will be via a report to the Executive Director of Delivery and the Executive Member for Finance and Business Change in Late September 2024.
This will be a Key Decision.
6. Consultation and Other Considerations
Legal Advice
6.1Shown in Appendix A.
Financial Advice
6.2Shown in Appendix A OFFICIAL SENSITIVE (COMMERCIAL)
Procurement Advice
6.3Shown in Appendix A
6.4Other Consultation Responses
Strategic Procurement Group
7. Equalities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.