RESOLVED that i. the progress made by Bracknell Forest Cambium Partnership for the period December 2022 to December 2023 be noted. ii. the proposed JV Business Plan for the Bracknell Forest Cambium Partnership as set out in Annex A and the financial budget and forecast as set out in Confidential Annex B.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1The first Business Plan for the Property Joint Venture (JV), which is a partnership between the Council and Countryside Partnerships (UK) Limited (“Countryside”), was agreed by the Council at its meeting on 25 November 2020 and covered the period 2020- December 2023. This set out the agreed objectives for the Joint Venture over this period, included anticipated budgets and profits from the first 3 sites anticipated to be developed. The Bracknell Forest Cambium Partnership was formally incorporated as a limited liability partnership (LLP) in December 2020.
1.2This report sets out the progress made against the Business Plan objectives to the end of December 2023. It also outlines the activities and ambition proposed by the Partnership for the period to December 2026.
1.3Under the legal agreements the Business Plan is required to be reviewed and any changes agreed annually or as reasonably requested by each partner. The refreshed JV Business Plan (attached as Annex A) has been agreed by the LLP Board to be recommended to each partner organisation for consideration and approval.
Recommendations
That the Executive:
2.1Notes the progress made by Bracknell Forest Cambium Partnership for the period December 2022 to December 2023;
2.2Approves the proposed JV Business Plan for the Bracknell Forest Cambium Partnership as set out in Annex A and the financial budget and forecast as set out in Confidential Annex B.
3 Reasons for Recommendation(S)
3.1The recommendations 2.1 and 2.2 support the fulfilment of Bracknell Forest Cambium Partnership’s objectives and aligns with the legal agreements entered into by the partners, which require the agreed JV Business Plan to be formally reviewed each year.
3.2The scope of the JV Business Plan has not changed materially since inception in 2020, although the Jubilee Gardens site is now be considered as part of a wider master planning of secondary sites, such as the Southern Gateway and Eastern Gateway Development area, The Southern Gateway also now includes High Street car park as Phase 1 of the Southern Gateway development. To note a separate report is being considered by Executive in March 2024 on the proposals for the Southern gateway and wider consultation. There is no obligation for the Council to enter into any exclusivity arrangements on additional sites and each site will be subject to Executive approval prior to any initial site development proposal (ISDP) being put to the Council for consideration.
3.3The Executive has agreed the ISDP for the Depot side in October 2023 which will now be developed for planning submission and subsequently a Settled Site Development Plan will be put to Executive for approval prior to land being drawn down into the JV.
3.4The Business Plan includes ambitions for the Southern Gateway which supports the council in its vision for the Town centre. The key points are to blend build form and landscape, improve connectivity on foot; cycling and for public transport; supporting the town centre economy with new cultural activities; mixed use; green spaces and high-quality offices and homes.
4 Alternative Options Considered 4.1 Members could choose not to endorse the Business Plan and instruct the Partnership to rework any parts that cause concern. However, as there are no proposed significant amendments to the Business Plan 2020-23 that have not previously been considered and endorsed by Members, it is felt that this would not be easily justified.
5 Supporting Information
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo...
Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.