Bracknell Forest Council
Executive, Tuesday 18 June 2024 at 5.30pm

Safety Valve - Construction Projects Strategic Procurement Plan

Approved Executive 2 papers

Executive approved this item on Tuesday 18 June 2024. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

RESOLVED that i. the Executive approves this Strategic Procurement Plan to tender the appointment of two separate main contractors under 2 separate JCT Building Contracts, to create additional SEMH and SRP provision across 2 sites within the borough (subject to securing planning approval). ii. authority be delegated to the Executive Director, Communities and the Executive Member for Children, Young People and Learning, to award the works contracts to the providers meeting the requirements of the contract. Subject to sufficient resources.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Executive

Purpose of report

1.1To recommend the Strategic procurement approach to commission the building works to create a new SEMH school and an SRP provision, to address the insufficient specialist places within the Borough.

2. Recommendation(s)

2.1That the Executive approves this Strategic Procurement Plan to tender the appointment of two separate main contractors under 2 separate JCT Building Contracts, to create additional SEMH and SRP provision across 2 sites within the borough (subject to securing planning approval).

2.2That the Executive delegate authority to the Executive Director, Communities and the Executive Member for Children, Young People and Learning, to award the works contracts to the providers meeting the requirements of the contract. Subject to sufficient resources.

2.3Advertising

In order to meet the Council’s Contract Standing Orders, the construction projects will be delivered using a compliant framework, where the contractors will be required to submit an expression of interest for the three projects. The Council will than select one contractor for each project to develop elements of the technical design and carry out the construction works.

• Performance Specification, drawings and the contract documents will be prepared by the Councils Managing Partner • The works will be contracted in accordance with a JCT Building Contract 2016

The Crown Commercial Service (CCS) Construction Works and Associated Works Framework will be accessed, via Lots. The Framework Lots are divided based upon project value. Each Lot requires that a mini competition be carried out where all suppliers within the appropriate Lot are invited to bid, therefore 2 separate mini competitions will be conducted. The Framework allows for the allocation of multiple industry standard contracts therefore, the Council must be clear with bidders that JCT terms will be used from the available pool.

2.4Tender Evaluation

The tenders will be evaluated, based on a 50/50 cost/quality split. This split allows for the contract to be awarded to the best all round bid for quality, rather than just cost alone, preventing a situation where the lowest tender may outweigh a poor-quality submission. 3. Reasons for Recommendation(s)

3.1It is a requirement of the contract standing orders, that the Executive approve any strategic procurement plan with a value more than £1m. This decision seeks approval for the procurement process.

Alternative options considered

4.1Consideration has been given to seek contractors through a 2-stage restricted procurement process, but this would require a minimum period of 16 months to conclude and secure a contractor. Therefore, this would not be a viable solution and would delay the delivery of school place being available as required.

5. Supporting Information

5.1To deliver the Councils Safety Valve construction programme, which includes 4 projects, Bucklers Park, All Saints, Sandhurst and Edgbarrow. The latter 3 schemes are to be funded by Bracknell Forest and Council approved their inclusion in the capital programme at its meeting in January 2024.

5.2For the Bucklers Park new Autism School, the Council submitted a self-delivery business case in February 2024, seeking to ensure a firm delivery date was programmed. Whilst the initial feedback from the DfE was supportive, the risk profile associated with this approach was not felt to be in the Council’s best interests. It has therefore been agreed, in consultation with the Executive Members during April 2024, that the DfE will lead delivery of the project as originally expected, in collaboration with the Council. Therefore, the procurement of the main contractor will be under-taken by the DfE through the DfE framework of contractors, with support from the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Initial equalities screening record form (Final)Appendix B 112 KB Download
PDF
Safety Valve: Construction Projects Strategic Procurement PlanReport 96 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 9 attended
MT
Councillor Mary Temperton LABChair, apologies
HP
Councillor Helen Purnell LABVice-Chair, in the Chair, present
RB
Councillor Roy Bailey LABCommittee Member, present, as expected, virtual
PB
Councillor Paul Bidwell LABCommittee Member, apologies
GG
Councillor Guy Gillbe LABCommittee Member, present
IJ
Councillor Iskandar Jefferies LABCommittee Member, absent
KN
Councillor Kathryn Neil LABCommittee Member, present
MW
Councillor Megan Wright LABCommittee Member, present
KG
Kevin GibbsOfficer, expected

On this subject at Bracknell Forest

Search all
  1. Safety Valve - Construction Projects Strategic Procurement PlanThis decision
  2. Safety Valve UpdateDecided
  3. Safety Valve Programme PlanApproved

More from Bracknell Forest Executive

All decisions
MeetingDecisionOutcome
17 Sep 2024 Town Centre Off Street Day Rate Car Park ChargesRESOLVED that i. the Executive noted the options on charging tariffs for The Avenue, Braccan Walk and Weather Way car... Noted Open
17 Sep 2024 Housing Supplementary Planning Document (SPD) consultationRESOLVED that i. the content of the Draft Housing SPD is agreed. ii. a public consultation on the Draft Housing SPD b... Agreed Open
17 Sep 2024 Approval of Biodiversity Action Plan 2024-2029RESOLVED that the Bracknell Forest Biodiversity Action Plan (BAP) 2024-2029 and supporting summary document is approved. Approved Open
17 Sep 2024 Council Plan Overview Report Q1RESOLVED that the performance of the council over the period from April to June 2024 highlighted in the Overview Repo... Noted Open
17 Sep 2024 Quarterly update on SEND ImprovementRESOLVED that the Executive: i. notes the progress made on implementing the SEND WSOA to improve services to children... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies