RESOLVED that Council approve an in-year supplementary capital approval of £13.7m to enable the scheme to be progressed as part of the capital programme, noting that this is the total scheme costs to be joint funded (50:50) by Bracknell Forest Council and Warfield Parish Council using s106 and Community Infrastructure Levy funding with some temporary borrowing. Community Safety Plan 2025-28 On the proposition of Councillor Purnell, Cabinet Member for the Environment, Community and Housing and seconded by Councillor Temperton it was RESOLVED that the Community Safety Plan 2025-28 is approved. Youth Justice Plan 2024-27 On the proposition of Councillor Purnell, Cabinet Member for the Environment, Community and Housing and seconded by Councillor Watts it was RESOLVED that the Youth Justice Plan 2024-27 is approved and noted that the Youth Justice Plan 2024-27 is expected to be delivered by utilising external and internal funding, including £36,111 of time limited grant funding.
Word for word from the decision Bracknell Forest published for this meeting.Source: democratic.bracknell-forest.gov.uk
1.1Since the Council agenda for the meeting on the 12 September 2024 was published, the Cabinet has met three times, on the 17 September, 15 October and 12 November. This report summarises decisions taken by reference to the relevant portfolio within which they fall.
1.2Updated Forward Plans for the Cabinet and other Council meetings are published every Friday and can be viewed online at www.bracknell-forest.gov.uk. Full details on the decisions taken by individual portfolio holders can also be accessed online through the Council’s website.
Recommendation
2.1Council is asked to approve the recommendations set out at paragraphs 5.1.1, 5.6.1 and 5.7.1.
Reasons for recommendations
3.1The reasons for recommendations are set out in the supporting information and in the reports considered by the Cabinet. The relevant reports that the Cabinet considered can be found here.
Alternative options considered
4.1Alternative options are discussed in the relevant individual reports considered by the Cabinet. The relevant reports that the Cabinet considered can be found here.
5 Supporting Information
Leisure, Culture, Public Protection and Democracy
5.1Warfield Community Hub
5.1.1 RECOMMENDED that Council approves an in-year supplementary capital approval of £13.7m to enable the scheme to be progressed as part of the capital programme, noting that this is the total scheme costs to be joint funded (50:50) by Bracknell Forest Council and Warfield Parish Council using s106 and Community Infrastructure Levy funding with some temporary borrowing.
5.1.2 Cabinet supported the development of a community hub in Warfield, with a funding model based on 50:50 cost sharing between Bracknell Forest Council and Warfield Parish Council and approved the Partnership Agreement which was approved by Warfield Parish Council on 20 August 2024. The signing of the agreement is delegated on behalf of Bracknell Forest Council to the Borough Solicitor and will be legally binding after both parties sign the agreement and date the same. Cabinet also approved the Strategic Procurement Plan for the building design and works including early/enabling works.
5.1.3 Cabinet agreed that the contract award for the Phase 1 Pre-Construction Services (RIBA Stage 3 design / Planning Permission and RIBA Stage 4) is delegated to the Executive Director: Communities in consultation with the Cabinet Member for Leisure, Culture, Public Protection and Democracy; the contract award for Phase 2 Main Works – RIBA Stage 5 onwards (including any demolition/early/enabling works) is delegated to the Executive Director: Communities in consultation with the Cabinet Member for Leisure, Culture, Public Protection and Democracy and agreed that the decision to appropriate the land at Priory Fields for planning purposes under Section 122(1) of the Local Government Act 1972 is delegated to the Assistant Director: Property in consultation with the Executive Director: Communities subject to a planning consent being obtained together with any consequent actions arising from the consent.
5.1.4 Warfield has been underserved in terms of community centre facilities compared to other parts of the borough. The community is currently served by Brownlow Memorial Hall, however it is not large enough to meet the needs of this growing community. The hub will support community engagement, cohesion, and wellbeing; it aligns with the Council Plan 2023-27 priority to ensure ‘community development and spaces encourage a cohesive and engaged community’.
5.2Disclosure and barring service (DBS) checks for councillors, co-opted members and mayoral consorts
5.2.1 Cabinet agreed to adopt the disclosure and barring service (DBS) checks for councillors, co-opted members and mayoral consorts’ policy.
5.2.2 An independent review of the DBS regime was carried out by Simon Bailey CBE QPM in April 2023 to provide assurance to government ministers about the effectiveness of the regime in safeguarding children and vulnerable adults.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.