Bracknell Forest Council
Planning Committee, Thursday 21 May 2026 at 6.30pm

24/00660/FUL - Land At Phase 5C Bucklers Park, Nine Mile Ride, Bracknell

Approved Planning 1 paper

AI summaryBracknell Forest Planning Committee approves 29 new homes at Bucklers Park Phase 5C, replacing a planned municipal depot, subject to S106 obligations including 35% affordable housing and SANG/SPA mitigation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved29 dwellings plus 3 re-orientated dwellings
MoneyCIL £231.66 per sqmPlus S106 contributions and £800 admin fee
What happens nextS106 agreement to be completedBefore Assistant Director: Planning can authorise approval
Who it affectsBucklers Park, Nine Mile Ride, BracknellSite is countryside outside settlement boundary

What was decided

The Planning Committee resolved to approve the application, authorising the Assistant Director: Planning to grant permission subject to completion of a Section 106 agreement and the conditions set out in the report. Report P196

The S106 agreement must cover eight matters: affordable housing, on-site Biodiversity Net Gain (with 30 year management and monitoring), Open Space of Public Value, SuDS monitoring fee, community facilities contribution, Thames Basin Heaths SPA mitigation, highways mitigation, and road adoption with PAF clauses. Report P189, P190, P191, P192, P193, P194, P195

The scheme replaces a previously approved municipal depot on the wider allocation with 29 dwellings and additional public open space, with the depot access road no longer built. Report 1.3, P33

Why

The Council cannot demonstrate a five year housing land supply, so the NPPF 'tilted balance' applies and policies for housing supply are out of date; the 29 dwellings contribute to housing supply with 10 (35%) as affordable units. Report 1.6, 9.4, 10.1, 10.2, 10.6

The site is outside the defined settlement boundary and contrary to Local Plan Policies LP1, LP2 and LP35, and to Saved Policy SA5 which allocated it for a municipal depot, but the officer found only limited landscape harm, partly screened by retained woodland. Report 1.5, 9.3, 9.5, 9.16, 9.21, 10.4

Officers concluded that the adverse impacts of approval would not significantly and demonstrably outweigh the benefits, including affordable housing, open space gains, and the loss of the depot access which benefits biodiversity. Report 1.6, 10.12, 10.13

What happens next

Complete the Section 106 agreement covering the eight listed obligations before the Assistant Director: Planning issues the approval. Report P188, P196

The applicant must secure 0.5 hectares of SANG capacity from a third party provider, pay a SAMM contribution calculated per bedroom, and pay a £800 administration and monitoring fee, all on completion of the S106. Report 9.80

Conditions require submission and approval of materials, finished floor levels, boundary treatments, a Sustainability Statement, a net zero carbon report, accessibility/M4(2) and M4(3) details, and a full SuDS scheme with verification, before development proceeds or is occupied. Report P203, P204, P205, P206, P207, P208, P209, P210, P211, P212, P213, P214, P215, P216

The money

  • £231.66 CIL rate per square metre for Class C3 residential at the TRL, Crowthorne site Report 9.86
  • £800 S106 administration and monitoring fee for Thames Basin Heaths SPA Report 9.80
  • 35% on-site affordable housing 10 affordable dwellings plus commuted sum for 0.15 of a unit Report 9.67, 9.68, 9.69

Options considered

  • Chosen: Approve with S106 and conditions (officer recommendation). Tilted balance under NPPF; benefits of 29 dwellings and 10 affordable units outweigh limited landscape harm Report 1.6, P7, 10.13
  • Rejected: Refuse. Adverse impacts not considered to significantly and demonstrably outweigh benefits given lack of five year supply Report 9.4, 10.12

Implications

  • Legal: Approval is conditional on a Section 106 agreement under the Town and Country Planning Act 1990; the Council carried out a Habitats Regulations Assessment and required SANG and SAMM to avoid adverse effect on the Thames Basin Heaths SPA. Report 9.70, 9.75, 9.81
  • Financial: Developer pays CIL at £231.66 per square metre, S106 contributions for affordable housing, BNG management and monitoring, community facilities, highways mitigation, plus SAMM and £800 admin fee. Report 9.86, 9.80, P189, P190, P192, P193, P194
  • Equalities: Two of the 10 affordable rented dwellings are provided to Part M4(3)(2)(a) wheelchair adaptable standard, meeting the 5% wheelchair housing requirement under Policy LP38. Report 9.84, P208
  • Climate: Conditions require a Sustainability Statement targeting 110 litres/person/day water efficiency and a report demonstrating how the scheme contributes to net zero carbon for regulated emissions. Report P206, P207
  • Risk: A phase-specific Construction and Environmental Management Plan must address badgers, breeding birds including Little Ringed Plover, amphibians and reptiles, and any contamination from previous phases. Report 9.59, 9.60, 9.61
  • Environment and climate: The scheme must achieve a minimum 10% Biodiversity Net Gain on site, with on-site BNG managed for at least 30 years under a Habitat Management and Monitoring Plan. Report 9.64, P190

Who and where

  • Future residents of the 29 new dwellings at Bucklers Park Phase 5C Report 5.4, 9.68
  • Households in need of affordable housing in the borough (10 affordable units provided) Report 9.67, 9.68
  • Existing and future residents of the wider Bucklers Park development who gain additional public open space and the removal of the depot access road Report 9.90
  • Users of the Thames Basin Heaths Special Protection Area, mitigated by SANG and SAMM contributions Report 9.73, 9.78
  • Crowthorne Parish Council, which recommended approval
  • Neighbouring properties including Oaklands, Nine Mile Ride, and properties along Foresters Way Report 3.1, 9.36
  • Highways users on South Road, Dukes Ride and bus routes through S106 highways mitigation Report P194, 9.51
  • The Bucklers Park Hub, which would benefit from a community facilities S106 contribution Report P167, P192

Timeline

  • 26/10/23: Phase 5A reserved matters (111 dwellings) approved under 22/01043/REM Report 4.3
  • 12/12/23: Phase 5B full application (90 dwellings) approved under 22/01051/FUL Report 4.4
  • Pending (as of report): Depot reserved matters under 22/01046/REM pending Report 4.5
  • 2026-05-21: Planning Committee resolves to approve 24/00660/FUL subject to S106 and conditions
  • Within three years of permission: Development must begin, per standard condition under Section 91 of the Town and Country Planning Act 1990 Report P197

Plain English for the jargon

  • BNG: Biodiversity Net Gain, a measurable improvement in biodiversity for a development, required here at a minimum 10% on-site.
  • SANG: Suitable Alternative Natural Greenspace, provided to divert recreational pressure away from the Thames Basin Heaths Special Protection Area.
  • SAMM: Strategic Access Management and Monitoring, a financial contribution towards managing visitor pressure on the Thames Basin Heaths SPA.
  • CIL: Community Infrastructure Levy, a per square metre charge on new development, set at £231.66 for residential development on this site.
  • Tilted balance: The NPPF paragraph 11(d) presumption in favour of sustainable development, applied where the Council cannot demonstrate a five year housing land supply.
  • TBH SPA: Thames Basin Heaths Special Protection Area, a European protected site for which the development lies within the 400m to 5km buffer.
  • HMMP: Habitat Management and Monitoring Plan, required for at least 30 years of on-site BNG management.
  • SuDS: Sustainable Drainage Systems, used to manage surface water runoff on the site.
  • PAF clauses: Provisions within the S106 agreement relating to the adoption of roads by the local highway authority.
  • SALP: Site Allocations Local Plan (2013), which contains Saved Policy SA5 allocating the wider TRL site.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED that f ollowing the completion of a planning obligation(s) under Section 106 of the Town and Country Planning Act 1990 relating to: 1. Provision of Affordable Housing 2. On-site BNG, to include: • Management of the on-site BNG for a minimum 30 years in line with HMMP • Monitoring fee 3. Open Space of Public Value 4. SuDS monitoring fee 5. Community facilities contribution towards f facilities in the area, such as The Bucklers Park Hub. 6. Measures to avoid and mitigate the impact of residential development upon the Thames Basins Heath SPA 7. Highways mitigation contribution for measures at South Road, Public Transport, Dukes Ride and / or other projects capable of serving the site. 8. Adoption of roads within the development and PAF clauses. The Assistant Director: Planning be authorised to APPROVE the application subject to the following conditions amended, added to or deleted as the Assistant: Director: Planning considers necessary: 1. The development hereby permitted shall be begun before the expiration of three years from the date of this permission. REASON: To comply with Section 91 of the Town and Country Planning Act 1990. 2. The development hereby permitted shall be carried out only in accordance with the following approved plans: Application Boundary Plan – Ref. 5C-001 Rev C Site Layout SL-OP2 Rev T Site Wide Layout SL-5C-03 A Colour Site Layout SL-5C-02 B Mix and Tenure Plan SP-5C-101 D Parking Plan SP-5C-103 C House Type Plan SP-5C-106 C Character Area Plan SP-5C-107C Rear Garden Sizes SP-5C-108 C Building Heights Plan SP-5C-109 C House Type 2BA & 3BA-1 Proposed Elevations 5C-2BA-3BA-1-ELE-002 D House Type 2BA & 3BA-1 Proposed Floor Plans 5C-2BA-3BA-1-FP-002 D House Type 2BA Proposed Elevations 5C-2BA-ELE-001 D House Type 2BA Proposed Floor Plans 5C-2BA-FP-001 D House Type 3BA & 2BA-1 Proposed Elevations 5C-3BA-2BA-1_ELE-001 D House Type 3BA & 2BA-1 Proposed ... view the full minutes text for item 7.
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Planning Committee

Summary

1.1The application proposes a development of 29 dwellings as an extension to the Bucklers Park development which was a mixed use site allocated within the Site Allocations Local Plan (SALP) (2013). The site of the proposed housing lies beyond the settlement boundary within the countryside. The application proposes the creation of public open space on the site of the proposed depot as indicated in the site’s allocation and within the original outline planning permission granted for the site which lies within the settlement boundary.

1.210 dwellings would be provided as affordable housing together with a commuted sum. The proposed housing would integrate into the existing Bucklers Park development, continuing the character areas, prescribed by the Design Code for the wider development.

1.3The scheme, which results in the loss of the Depot Scheme and the associated access road, increases open space across the site and through the use of appropriate s106 obligations and conditions, will protect and enhance biodiversity, mitigate its impact on the Thames Basin Heaths SPA and provide appropriate levels of infrastructure.

1.4The scheme provides a level of parking that meets the Council’s adopted parking standard.

1.5The harm identified within the scheme results from not complying with Local Plan Policies LP1, LP2 and LP 36, and SALP Policy Policy SA 5 which identifies the land for open space and allocated for a depot, however there are significant benefits which are considered to outweigh the harm such as the provision of 29 additional dwellings including the provision of 10 affordable units. Limited landscape harm has been identified with the proposal still considered to recognise the intrinsic character and beauty of the countryside.

1.6The Council cannot demonstrate a 5 year housing land supply and when applying the ‘tilted balance’ it is considered that the adverse impacts of approving the application would not significantly or demonstrably outweigh the benefits and therefore the application is recommended for approval.

RECOMMENDATION Planning permission be granted subject to the prior completion of a s106 agreement and the conditions set out in Section 11 of this report.

2. REASON FOR REPORTING APPLICATION TO COMMITTEE

2.1The development is contrary to Site Allocations Plan Policy SA5 which requires the provision of a municipal depot and is contrary to Local Plan Policies LP 1 and LP 2 as housing does not form an accepted type of development in the countryside. The application has been advertised as a departure to the Local Plan, and it is brought to the Planning Committee in compliance with the Council’s Scheme of Delegation, in such instances.

Planning Committee 3. PLANNING STATUS AND SITE DESCRIPTION

PLANNING STATUS Countryside Area identified for a municipal depot under 13/00575/OUT where open space is proposed. Area identified for open space under 13/00575/OUT where housing proposed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
24/00660/FUL: Land At Phase 5C Bucklers Park, Nine Mile Ride, BracknellReport 1.9 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 13 attended
TB
Councillor Tricia Brown LABChair, present
SC
Councillor Sheila Collings GreenVice-Chair, present
TM
Councillor Tina McKenzie-Boyle CONCommittee Member, present
PF
Councillor Peter Frewer LABCommittee Member, apologies
DH
Councillor Dorothy Hayes CONCommittee Member, present
JP
Councillor Jenny Penfold LABCommittee Member, present
DL
Councillor Donna Louise Pressland LABCommittee Member, present
MT
Councillor Mary Temperton INDGCommittee Member, present
PS
Councillor Patrick Smith LIB DEMCommittee Member, present
CT
Councillor Cath Thompson LABCommittee Member, present
TV
Councillor Tony Virgo CONCommittee Member, apologies
NZ
Councillor Nazar Zahuruddin LIB DEMCommittee Member, present, as expected, virtual

All 13 on the meeting page

On this subject at Bracknell Forest

Search all
  1. 24/00660/FUL - Land At Phase 5C Bucklers Park, Nine Mile Ride, BracknellThis decision
  2. 24/00724/FUL - Land Adjacent To Silver Trees Birch Lane Ascot SL5 8RFRefused
  3. 25/00439/FUL - Land Adjacent To The Russets Hancombe Road SandhurstApproved
  4. PS 24/00786/FUL - The Woodlands, Upper Broadmoor Road, CrowthorneApproved
  5. PS 24/00122/FUL - Land At Bog Lane and New Forest Ride BracknellAgreed
  6. 24/00785/FUL Land at Osborne Lane Warfield BracknellApproved

More from Bracknell Forest Planning Committee

All decisions
MeetingDecisionOutcome
13 Aug 2026 PA/2026/0294 - High Street Car Park, The Ring, Bracknell, RG12 1GNRESOLVED that the application be APPROVED subject to the amended conditions raised both in the supplementary report a... Approved Open
16 Jul 2026 PS 25/00616/REM - White Gates Mushroom Castle Winkfield Row Bracknell Berkshire RG42 7PLRESOLVED that the application be APPROVED subject to the following conditions as amended and added to at the meeting ... Approved Open
16 Jul 2026 24/00724/FUL - Land Adjacent To Silver Trees Birch Lane Ascot SL5 8RFRESOLVED that the application be REFUSED for the following reasons: 01. The proposal is for the construction of a new... Refused Open
16 Jul 2026 PA/2026/0438 - 7 Alben Road, Binfield, Bracknell, RG42 4HURESOLVED that the application be APPROVED subject to the following conditions: 1. The development hereby permitted sh... Approved Open