Council Plan Overview Report - Q1

Decided Executive 2 papers

AI summaryCabinet notes the Q1 2026/27 Council Plan performance report covering April to June 2026, which flags a potential £5.160m overspend including emerging issues and shows 93% of 126 council actions in progress.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCabinet noted Q1 2026/27 performance and Overview and Scrutiny recommendations
Money£5.160m potential overspendIncluding emerging issues; £0.671m variance against approved budget excluding contingency
What happens nextOfficers to continue savings workIdentify in-year savings and manage directorate variances to avoid year-end overspend
Who it affectsCouncil-wide services and residentsPerformance covers all four Council Plan priorities and all directorates

What was decided

Cabinet noted the Q1 2026/27 performance overview covering April to June 2026, set out in Annex A. Report P2

Cabinet also noted recommendations made by the Overview and Scrutiny committee, in Annex B.

Why

The report provides Cabinet with a high-level summary of achievements and areas where performance does not meet targets, complementing the detailed directorate Quarterly Service Reports. Report 1.2, 1.4

It is the first quarterly report against the 2026/27 service plans noted by Cabinet on 19 May 2026, covering three new focus areas set by the new Leader: violence against girls and women, housing supply, and Deck regeneration. Report 1.3

The council faces financial sustainability pressure from the Government's Fair Funding 2.0 changes, prompting an early drive to identify in-year savings to reduce reliance on reserves. Report P62, 1.15

What happens next

The Corporate Management Team will work with Cabinet Members on scenarios to keep the overall budget balanced by year end. Report 1.17

Directorates will continue delivering savings, with several schemes marked on track and others under review, including delayed leisure agency model and waste management changes. Report P126, P127, P129, 1.16

Recruitment to a dedicated Alternative Provision Framework lead is required before that work can begin; SEND improvement and reform activity continues alongside inspection preparation. Report P166, P63

The money

  • £5.160m Potential council overspend including emerging issues at Q1 Report 1.16, P97, P89
  • £0.671m Variance against approved budget excluding Corporate Contingency Report 1.16, P97, P89
  • £5m In-year savings target to reduce drawing from reserves Report 1.15
  • £1.67m Community Infrastructure Levy receipts exceeding Q1 forecast Report P52
  • £1,259k Place directorate savings target for 2026/27 Report P115
  • £0.712m Current Communities directorate staffing overspend pressure Report P124

Options considered

  • Chosen: Note the Q1 2026/27 Council Plan Overview Report and Overview and Scrutiny recommendations. Standard quarterly performance reporting and oversight

Implications

  • Risk: Key challenges flagged include financial sustainability from Fair Funding 2.0, demand pressures in Children's and Adult Social Care, SEND reform and inspection readiness, and below-forecast housing delivery (87 net completions against a 148 forecast). Report P62, P63, P64
  • Equalities: The new focus areas for 2026/27 include tackling violence against girls and women, with Cabinet approving the Domestic Abuse Strategy 2026-32 and the All-Age Exploitation Strategy 2026-31. Report 1.3, P45
  • Climate: Cabinet approved a new Climate Change Strategy Delivery Plan with 108 projects and deliverables, including sustainable fuel across the waste fleet and decarbonisation of council buildings. Report P54
  • Staffing: Agency staff reliance and workforce planning are flagged as challenges, with CQC staff preparedness sessions being delivered to support inspection readiness. Report P63
  • Other: Performance against 89 indicators at Q1: 76 green (85%), 2 amber (2%), 11 red (12%); 126 actions: 6 complete (5%), 117 in progress (93%), 3 not started (2%). Report 1.5, 1.6, 1.9

Who and where

  • Bracknell Forest Council residents and service users across all directorates Report 1.2, 1.4
  • Children and young people with SEND and their families Report P43, P162, P164, P166
  • Children's Social Care and Adult Social Care clients and carers Report P138, P139, P170
  • Council staff, particularly in Communities and Resources directorates facing staffing budget pressures Report P118, P124
  • Housing applicants and homeless households, with delivery below forecast Report P64
  • Recycling service users, with contamination levels above forecast Report P64

Timeline

  • April 2026: Best Start in Life Plan published and submitted to Department for Education Report P166
  • 22 April 2026: Council endorsed the partnership Stronger Together Communities Strategy Report P47
  • May 2026: Cabinet approved new Climate Change Strategy Delivery Plan; Bridgewell supported living accommodation opened; LGA peer team report published Report P54, P48, P58
  • 19 May 2026: Cabinet noted the 2026/27 service plans that this report draws from Report 1.3
  • June 2026: Armed Forces Day event held; planning progressing for Pride and Communities Festival events; Stop Smoking Service fully mobilised Report P46, P45
  • 1 August 2026: Expected go-live date for Leisure agency model, delayed from 1 July 2026 Report P126
  • 30 September 2026: Target for new Education Transport Framework and Section 19 Exclusion Provision contract award Report P166
  • 31 March 2027: Target completion for most strategic actions under the Council Plan priorities Report P162, P165, P166, P167, P168, P169, P170

Plain English for the jargon

  • RAG status: Red, amber, green rating used to show whether an action or indicator is on track, slightly off track, or at significant risk.
  • CPOR: Council Plan Overview Report, the quarterly performance report against the Council Plan.
  • SEND: Special Educational Needs and Disabilities.
  • Fair Funding 2.0: Government changes to local authority funding referenced as creating financial sustainability challenges for the council.
  • Emerging Issues: Budget risks identified by directorates that are likely to affect the position but cannot yet be accurately quantified.
  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure.
  • SPD: Supplementary Planning Document, providing guidance on policies in the Local Plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item123

Resolved

RESOLVED that Cabinet: · NOTES the performance of the council over the period from April to June 2026, highlighted in the Overview Report in Annex A. · NOTES recommendations made by Overview and Scrutiny (Annex B).
Word for word from the decision Bracknell Forest published for this meeting. Source: democratic.bracknell-forest.gov.uk

Follow this further

Built from Bracknell Forest's papers

What the report saysPro

Report to Cabinet

Annex A

Council Plan Overview Report

Q1 2026/27 April – June 2026 Council Plan 2023-2027

Chief Executive: Susan Halliwell Contents Section 1: Chief Executive’s Overview ................................................................................3 Introduction .........................................................................................................................................3 Quarter 1 2026/27 highlights ..............................................................................................................7 Challenges identified and being addressed ......................................................................................10 Section 2: Budget position .................................................................................................10 Revenue budget monitoring..............................................................................................................10 Section 3: Strategic priorities .............................................................................................23 Engaged and healthy communities...................................................................................................23 Thriving and connected economy .....................................................................................................38 Green and sustainable environment .................................................................................................43 Ambitious, resilient and sustainable organisation .............................................................................48 Section 4: Corporate health ................................................................................................59 Summary of people data...................................................................................................................59 Summary of complaints ....................................................................................................................62 Learning from complaints .................................................................................................................64 Strategic risks and audits..................................................................................................................69

Key Actions: Status and RAG status applied by owner Activity has not yet started on this action, reasons are included in the comments Not started

Activity is underway to deliver this action, an update is provided in the comments In progress

Objectives have been achieved and action is complete Complete

Activity on this action is not being undertaken, reasons provided in comments Parked

Following a review, delivery of this action is no longer required Not required

Item is on track for completion, no concerns or notable risks Green

Some concerns but the action is expected to be delivered without significant risks Amber

Significant risk to delivery, attention/action is required Red

Indicators: RAG status and trends automatically calculated against target/forecast Performance is very good against target or forecast Green

Performance is slightly off target or forecast Amber

Performance is weak against target or forecast and requires attention Red

Trend in performance has improved compared to previous period Better

Trend in performance is worse compared to previous period1 Worse

No change in performance trend from previous period No change Trend not applicable: ‘Plan is best’ neither bigger nor smaller result is better; indicator is new, no N/A previous data to compare; or year to date, comparison with previous period is not appropriate.

CPOR – Quarter 1 2026-27 Page 2 Section 1: Chief Executive’s Overview Introduction 1.1 This report sets out an overview of the council’s performance for the first quarter of 2026/27 (April - June 2026), relating to the Council Plan 2023-27.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CPOR Q1 2627 Apr-Jun v4Report 2.1 MB DownloadRead as text
PDF
Council Plan Overview Report: Q1Report 99 KB Download

At this meeting

Whole meeting

Who was there

0 of 10 attended
HP
Councillor Helen Purnell LABChair, expected
PB
Councillor Paul Bidwell LABVice-Chair, expected
GG
Councillor Guy Gillbe LABCommittee Member, expected
IJ
Councillor Iskandar Jefferies LABCommittee Member, expected
MW
Councillor Megan Wright LABCommittee Member, expected
GP
Councillor Georgia Pickering LABCommittee Member, expected
RF
Councillor Ryan Frost LABCommittee Member, expected
SO
Councillor Stephen O'Regan LABCommittee Member, expected
JB
Jamie BeardsmoreClerk, expected
AM
Alex MiddletonOfficer, expected

On this subject at Bracknell Forest

Search all
  1. Council Plan Overview Report - Q1This decision
  2. Council Plan Overview ReportNoted
  3. Council Plan Overview Report - Q4Decided
  4. Council Plan Overview Report - Q3Noted
  5. Council Plan Overview Report - Q2Agreed
  6. Council plan overview reportDecided

More from Bracknell Forest Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Children and Young Persons Participation Strategy 2026 - 31RESOLVED that Cabinet: APPROVES the Children and Young Persons Participation Strategy 2026-31 and action plan followi... Approved Open
22 Sep 2026 Forestcare Digital Telecare & Telecare & ARCRESOLVED that Cabinet: · APPROVES the procurement of digital telecare equipment required to support the transition fr... Approved Open
22 Sep 2026 Parking Management & Enforcement Strategic Procurement PlanRESOLVED that Cabinet: · APPROVES the approach detailed in the confidential annex for procuring the parking managemen... Approved Open
22 Sep 2026 Procurement for GP LARC and NHS Health Check ServicesRESOLVED that Cabinet · APPROVES the strategic procurement plan for GP LARC and NHS Health Checks across Berkshire Ea... Approved Open
14 Jul 2026 Capital Expenditure Outturn 2025/26RESOLVED that the Cabinet: a) Notes the 2025/26 capital programme outturn position, subject to completion of the exte... Approved Open