Progress Report 2025/26

Noted Finance 1 paper

AI summaryBreckland Governance and Audit Committee noted progress on the 2025/26 Internal Audit Plan, which includes a limited assurance opinion on procurement and 10 outstanding recommendations all past their due date.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgress with Internal Audit Plan 2025/26 and outstanding recommendations noted
MoneyNot stated
What happens nextVarious implementation datesMost actions due between April and November 2026
Who it affectsCouncil-wide audit and riskInternal audit activity across Breckland District Council

What was decided

The Committee noted progress with the Internal Audit Plan 2025/26 and outstanding internal audit recommendations.

Why

The Progress Report is provided to assist the Council in discharging its responsibilities for internal audit and to give assurance that the Internal Audit function is acting in accordance with the Internal Audit Standards. Report 1.1, 3.1

The report covers five final audit opinions issued during the period, the most significant being a limited assurance opinion on procurement. Report P32, P80

What happens next

Management action plans are in place with implementation dates running from April to November 2026, including urgent actions on procurement compliance by 30 September 2026. Report P87, P89, P90

The Contracts and Procurement Manager is to issue a UK3 Planned Procurement Notice for temporary accommodation and continue reporting non-compliance to the Corporate Management Team. Report P83, P84

An external quality assessment of the internal audit service is due in December 2027, with a gap analysis under way. Report P37

The money

  • £2.55m Procurement expenditure in Q1 2025/26 not notified to Contracts and Procurement Team (37% of total) Report P83
  • £1.70m Procurement expenditure in Q2 2025/26 not notified to Contracts and Procurement Team (27% of total) Report P83
  • £3.42m Procurement expenditure in Q3 2025/26 not notified to Contracts and Procurement Team (39% of total) Report P83
  • £564k Temporary accommodation expenditure in Q1 2025/26 not notified to Contracts and Procurement Team Report P84
  • £716k Temporary accommodation expenditure in Q2 2025/26 not notified to Contracts and Procurement Team Report P84
  • £1,193k Temporary accommodation expenditure in Q3 2025/26 not notified to Contracts and Procurement Team Report P84

Options considered

  • Chosen: Note progress with the Internal Audit Plan 2025/26 and outstanding recommendations. Standard reporting requirement to assist the Committee in discharging its oversight responsibilities Report 1.1, 3.1

Implications

  • Legal: Significant procurement expenditure was undertaken without confirmation of compliance with the Procurement Act 2023 or the Council's Contract Procedure Rules; one sampled contract lacked a signed Conflict of Interest Declaration Form. Report P80, P83, P84
  • Risk: The Risk Management audit gave a reasonable assurance opinion, identifying that risk processes rely heavily on one individual, training is informal, strategic risks are not mapped to corporate priorities, and no terms of reference exist for the Corporate Management Team. Report P51, P53
  • Staffing: Resilience in the Performance and Risk function is identified as a major issue, with risk management activity reliant on one individual and the workload set to increase due to local government reorganisation. Report P51, P53
  • Other: The Housing Services and Temporary Accommodation audit found instances where Housing Advice Forms and supporting documents were not promptly uploaded, decision letters were delayed, banding justifications were inconsistent, and a data cleanse of the housing register has not been completed. Report P39, P41

Who and where

  • Breckland District Council services subject to internal audit review Report P24, P29, P30, P31, P32, P33
  • Contracts and Procurement Team and service areas undertaking procurement Report P83, P87, P88
  • Performance and Risk Team and senior leaders Report P51, P57, P58
  • Housing Solutions Team and housing applicants on the Housing Register Report P39, P45, P46, P48, P49
  • Private sector landlords and HMO licence applicants Report P66, P71

Timeline

  • 30/04/2026: Update HMO licensing fees on the Council website and review past licences Report P71
  • 01/06/2026: Complete periodic reviews of case records on Locata Pro for housing triage Report P45
  • 05/06/2026: Establish timeframes for issuing housing decision letters and banding justification criteria Report P46, P48
  • 01/07/2026: Complete data cleansing exercise for housing register legacy cases Report P49
  • 31/08/2026: Ensure all Conflicts of Interest Declaration Forms are completed and signed Report P90
  • 30/09/2026: Ensure all procurement complies with legislation and Contract Procedure Rules; add defined risk appetite categories Report P58, P87
  • 31/10/2026: Increase capacity in the Performance and Risk Team and provide refresher training; map strategic risks to corporate priorities; thematic reporting of operational risks; develop CMT terms of reference; expand risk management framework guidance Report P57, P59, P61, P62, P63, P64
  • 30/11/2026: Ensure temporary accommodation procurement is compliant with legislation and Contract Procedure Rules Report P89
  • December 2027: Next External Quality Assessment of the internal audit service is due Report P37

Plain English for the jargon

  • EIAS: Eastern Internal Audit Services, the partnership that provides internal audit to the Council, hosted by South Norfolk Council
  • Limited assurance: An audit opinion indicating the system of internal controls is generally inadequate or not operating effectively, requiring significant improvements
  • Reasonable assurance: An audit opinion indicating the system of internal controls is generally adequate and operating effectively but with some improvements required
  • Substantial assurance: An audit opinion indicating a robust system of internal controls operating effectively
  • GIAS: Global Internal Audit Standards, the professional standards the internal audit function must follow
  • HMO: House in Multiple Occupation, a property rented out to at least three people who are not from one household
  • PPN: Planned Procurement Notice, a UK3 notice used under the Procurement Act 2023 to engage the marketplace
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item33/26

Resolved

RESOLVED that progress with the Internal Audit Plan 2025/26 and outstanding internal audit recommendations be noted.
Word for word from the decision Breckland published for this meeting. Source: democracy.breckland.gov.uk

Follow this further

Built from Breckland's papers

What the report saysPro

Report to Governance and Audit Committee, 28 pages

Background

1.1The Governance and Audit Committee receive updates on progress made against the Internal Audit Plan and is provided with details of any outstanding internal audit recommendations. This report forms part of the overall reporting requirements to assist the Council in discharging its responsibilities in relation to the internal audit activity.

2.0CURRENT PROGRESS

2.1The position in relation to the completion of the Internal Audit Plan 2025/26 is shown within the report. Details concerning any outstanding internal audit recommendations are also provided.

Reasons for recommendation

3.1The Governance and Audit Committee receive the Progress Report on Internal Audit activity, and details of any outstanding internal audit recommendations. In doing so, the Committee receives assurance that the Internal Audit function is acting in accordance with the Internal Audit Standards.

4.0IMPLICATIONS

4.1Corporate Priorities

4.1.1 Internal Audit helps to ensure that the service areas reviewed and ensuring that they are working towards the efficient and effective delivery of the Council’s corporate priorities.

4.2Financial

4.2.1 The Internal Audit Plan is currently within the approved budget for 2025/26.

Risk management

4.3.1 Internal Audit planning starts with the Council’s key risks, which then directs the audit plan for the financial year. Internal Audit reports then identify risks and control weaknesses within the Council which are highlighted in this report, with appropriate management action being agreed to mitigate these risks within agreed timeframes. Background papers: - None

Lead Contact Officer Name and Post: Teresa Sharman, Head of Internal Audit for Breckland District Council Telephone Number: 01603 430138 Email: [email protected]

Director / Officer who will be attending the Meeting Teresa Sharman, Head of Internal Audit.

Key Decision: No

Exempt Decision: No

Appendices attached to this report: Appendix A - Progress Report 2025/26 Appendix A

EASTERN INTERNAL AUDIT SERVICES

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Progress Report 2025/26Report 28 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 17 attended
RK
Councillor Robert KybirdChairman, present
LK
Councillor Linda KingVice-Chairman, present
HC
Councillor Harry ClarkeCommittee Member, apologies
MK
Councillor Mark Kiddle-MorrisCommittee Member, present
WR
Councillor William RichmondCommittee Member, present
DW
Councillor David WickersonCommittee Member, present
DF
David FowlerCo-Optee, in attendance
AC
Alison ChubbockOfficer, in attendance
TC
Toby CowperOfficer, in attendance
RP
Ryan PackOfficer, in attendance
DR
David RiglarOfficer, in attendance
TS
Teresa SharmanOfficer, in attendance

All 17 on the meeting page

On this subject at Breckland

Search all
  1. Progress Report 2025/26This decision
  2. Internal Audit Progress Report 2025/26Noted

More from Breckland Governance and Audit Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Risk FrameworkRESOLVED that the revised Risk Management Framework be approved with the next scheduled review in 24 months (2 years)... Approved Open
18 Jun 2026 Internal Audit Annual Report and OpinionRESOLVED that: 1) the contents of the Annual Opinion Report of the Head of Internal Audit be considered and received;... Noted Open
12 Feb 2026 Internal Audit Progress Report 2025/26RESOLVED that progress with the Internal Audit Plan 2025/26 and outstanding internal audit recommendations were revie... Noted Open
12 Feb 2026 Internal Audit Plan 2026/27, Charter and MandateRESOLVED that the Internal Audit Plan 2026/27 and Internal Audit Charter and Mandate be approved. Approved Open
12 Feb 2026 Accounting Policies 2025-26RESOLVED that the accounting policies for 2025-26 at Appendix 1 of the report be agreed. Agreed Open