CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Brent
Planning Committee, Wednesday 21 October 2009 at 7.00pm

LDF - progress and proposed changes for examination

Agreed Planning 1 paper

Planning Committee agreed this item on Wednesday 21 October 2009. Below is the council's own wording, with the papers it was decided on.

Item2

Resolved

- That the Executive be recommended to agree the proposed changes to the Core Strategy as set out in appendix 1 to the report, for consultation.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Planning Committee

Summary

1.1Progress with the Council’s Local Development Framework (LDF), particularly the Core Strategy and Site Specific Allocations documents which will form the new development plan is explained and Committee is asked to recommend minor changes to the Core Strategy for approval by the Council’s Executive for consultation in advance of Examination by a Planning Inspector early in 2010.

Recommendations

2.1That the Planning Committee recommends that Executive agrees the proposed changes to the Core Strategy set out in Appendix 1, for public consultation.

3.0Detail

Introduction

3.1The proposed submission versions of both the Core Strategy and the Site Specific Allocations DPDs were published for public consultation in June 2009. There were 400 representations made by 46 respondents. Of these representations, 166 were that the document is sound whereas 234 considered it to be unsound. On September 30th the council submitted the Core Strategy, and all the representations made, as well as a schedule of non-material changes, to the Secretary of State for examination by a planning inspector. A summary of the key issues arising from the representations is attached as Appendix 2.

3.2It is intended that the Site Specific Allocations DPD will be submitted either by the end of the year or early in 2010. The reason this DPD was not submitted at the same time as the Core Strategy is that

Planning Committee Version (No 1) (21st Oct. 2009) (8th Oct. 2009

Created by Neevia Document Converter trial version http://www.neevia.com Created by Neevia Document Converter trial version Planning Inspectorate guidelines indicate that they would not wish to hold an examination into site allocations until after the report on he Core Strategy examination. This will not be before spring 2010.

Proposed Changes

3.3Since the consultation period ended, discussions with potential objectors and stakeholders have resulted in proposals to make a few minor changes to policy. Members are asked to recommend these proposed changes to the Executive when it meets on November 16th. These proposed changes are set out in full in Appendix 1.

3.4The first change is very minor and is proposed, in part, in response to a recommendation from the Government Office for London. This is basically to encapsulate the objective of achieving the London Plan target for affordable housing (70% social housing and 30% intermediate) in policy rather than merely in supporting text. It is a requirement of Government planning policy as set out in PPS3 that Local Development Frameworks include such a policy. This does not alter any of the objectives of the strategy.

3.5The remaining two changes concern policy on climate mitigation and, in particular, how this relates to Wembley (policies CP19 and CP7). A number of objections were received to policy CP19, particularly to expectation in policy that development would have to connect to decentralised energy networks. Concerns were expressed, including by the GLA, that proposals for such networks were not sufficiently advanced and that there was a need to set out the Council’s plans for delivering sustainable energy infrastructure. Officers recognise that further development work would be needed before developers could be asked to connect to such networks and, in particular, some assessment of the viability / feasibility. In these circumstances officers recommend that the wording of policy CP19 be changed to allow developers the opportunity to demonstrate that connecting to decentralised networks is not feasible. At the same time the infrastructure sought for Wembley will include District-wide Combined Cooling Heat and Power “if feasible”. These relatively minor changes are likely to overcome some of the objections relating to the soundness of the Core Strategy.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LDF: progress and proposed changes for examinationReport 133 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 12 attended
SK
Councillor Suresh KansagraChair, present
JP
Councillor James PowneyVice-Chair, apologies
MA
Councillor Mohammad AnwarCommittee Member, apologies
EB
Councillor Eddie BakerCommittee Member, apologies
MC
Councillor Mark CumminsCommittee Member, present
SG
Councillor Simon GreenCommittee Member, absent
SH
Councillor Sami HashmiCommittee Member, present
CH
Councillor Chunilal HiraniCommittee Member, present
JM
Councillor Jim MoherCommittee Member, apologies
RM
Councillor Ruth MoherCommittee Member, apologies
HP
Councillor Harihar PatelCommittee Member, apologies
BT
Councillor Bobby ThomasCommittee Member, apologies

On this subject at Brent

Search all
  1. LDF - progress and proposed changes for examinationThis decision
  2. Local Planning Issues and LDF ProgressNoted

More from Brent Planning Committee

All decisions
MeetingDecisionOutcome
5 Aug 2026 Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... Decided Open
5 Aug 2026 Declarations of interestsNo declarations of interest were made during the meeting. Decided Open
5 Aug 2026 Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... Approved Open
5 Aug 2026 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... Agreed Open
5 Aug 2026 Any Other Urgent BusinessThere was no other urgent business. Decided Open