( i ) that approval be given to the award of a contract for pre-construction services to Morgan Ashurst in relation to the construction works at Sudbury Primary School; (ii) that approval be given to the award of a contract to Morgan Ashurst , with a maximum sum stated in the report from the Director of Children and Families, for the construction works at Sudbury Primary School to provide part new build accommodation and part remodel (and refurbishment) of the existing buildings.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report requests Executive approval for the award of a contract in relation to the construction works at Sudbury Primary School, estimated at £7,068,885. The contractor is from the IESE (Improvement and Efficiency South East) Buildings Work-stream Construction Framework. These works will involve part newbuild and part remodel and refurbishment of existing buildings to provide additional capacity at Sudbury Primary School to enable them to accommodate an expanded 4FE [840 children from Year R to Year 6 plus a Nursery] Primary School.
Recommendations
The Executive is recommended to:
2.1Note the award of a contract for pre-construction services in the sum of £35,241 to Morgan Ashurst in relation to the construction works at Sudbury Primary School.
2.2Agree to the award of a contract to Morgan Ashurst with a maximum sum of £7,068,885 for the construction works at Sudbury Primary School to provide part new build accommodation and part remodel (and refurbishment) of the existing buildings.
3.0Detail
3.1Sudbury Primary School is a maintained Local Authority Foundation School. The school specialises in art, music and ICT teaching and there are accelerated programmes in all year-groups to cater for more able pupils; its pupils come from diverse ethnic and cultural backgrounds. It was identified as one of the schools to be expanded by 1FE with funding mainly from the PCP resource allocation.
3.2In its Primary Capital Programme - Primary Strategy for Change (PCP- PSfC) submitted to the DCSF in June 2008, the Council acknowledges an increasing demand for school places across all year groups, with most acute demand in central and west Brent, particularly in Wembley Central, Sudbury and Alperton wards, where the majority of primary school places are full.
3.3At their meeting of 26 May 2009, Executive approved the allocation of up to £6.50m from PCP funding to support the expansion proposal by 1FE at Sudbury Primary School, supported by the school’s own resources of £1.5M and, if required, a School Loan of up to £300k to address its specific accommodation requirements, including an external canopy and an additional wet play area to the main hall for pupils. The total provision for the scheme is now an estimated £8,264,459 of which the maximum construction cost is £7,068,885. A breakdown of scheme budget is detailed below:
Total Scheme Costs Source Available Amount £8,264,459.00 Primary Capital Programme £6,500,000.00 Budget Share £1,252,000.00 Devolved Formula Capital £248,000.00 Loan under School Loan Scheme up to: £300,000.00 £8,264,459.00 £8,300,000.00
This budget will enable the following scheme costs to be met:
AMOUNT ELEMENT Fees £1,060,333 Design Team £35,241 Pre-Construction Construction £7,068,885 Construction contract FFE £100,000 Furniture and Fixed Equipment
3.4In addition to the main contract, a total of £408,250 Sure Start monies is budgeted against the new-build Children’s Centre, landscaping and ground works services. The procurement and works package for this package of works is not the subject of this report. It is being procured separately given the different nature of the building and construction technology. The procurement for this will begin shortly with a contract award aimed for Autumn 2010 upon confirmation of Planning approval. Project details
3.5The expansion of Sudbury Primary School, by 1FE to 4FE is an essential step that enables the Council to meet its statutory duty to provide school places; it features as a high priority in the Council’s March 2009 submission to the former DCSF (now DfE) for funding from Primary Capital Programme (PCP).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.