i . that the design and build contract for the Civic Centre be awarded to Skanska Construction UK Limited; ii. that the Assistant Director (Civic Centre) with the Director of Legal and Procurement be authorised to finalise the terms of appointment.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report summarises the procurement process undertaken by the Council to procure a Design & Build contractor and requests authority to award a contract for the appointment of a Design & Build contractor for the new Civic Centre.
1.2The development of the Civic Centre in Wembley is one of the Council’s highest priority projects and is a key component of the Council’s Improvement & Efficiency Strategy 2008-2012. With the appointment of the design and build contractor all the pieces will be in place to ensure the building will be ready for occupation in June 2013.
1.3A supplementary report will be tabled at the meeting identifying the successful tenderer.
Recommendations
2.1That the Executive awards the design and build contract for the Civic Centre to the organisation named in the supplementary report.
2.2That the Assistant Director Civic Centre with the Director of Legal and Procurement be authorised to finalise the terms of appointment.
Background
3.1On 19 October 2009 the Executive received a report from the Chief Executive requesting authority to procure a Design & Build contractor. The Executive accordingly gave approval to procure a Design & Build contractor and approved pre-tender issues as required by the Council’s Contract Standing Orders 88 and 89, including the evaluation criteria.
The Tender Process and Council’s Contract Standing Orders
3.2The Design & Build contractor has been procured using the Restricted Procedure in accordance with the EC Directive 2004/18 (the Classic Directive), the Public Contracts Regulations 2006 (the Regulations) and the Council's Contract Standing Orders. At tender stage a single stage process was adopted (with some construction tenders there is the potential to run a two-stage tender).
3.3The form of contract is based on the JCT Design and Build contract 2005 (with 2007 amendments) with further bespoke amendments.
Stage One - Pre – Qualifying Stage
3.4On 11 December 2009 the contract notice was placed in the Official Journal of the European Union (OJEU) to seek initial expressions of interest. The notice specified the Council’s requirement to procure a Design & Build contractor and that the scope of works were to finalise the design and construct the Civic Centre.
3.5Tenderers were advised the Council had employed a full design team who had completed the design up to RIBA stage E and secured detailed planning permission. It was a condition of tendering that the successful tenderer would accept a novation of the Council's current design team.
3.6Tenderers were advised variant tenders would not be accepted.
3.7Twenty-two organisations expressed an interest in response to the OJEU notice and they were issued with an information pack and pre- qualification questionnaire (PQQ) to complete by 12 noon on 12 February 2010. Fourteen PQQs were returned in accordance with the deadline.
3.8The following assessment process was followed to decide pre- qualification:
Stage 1: All applicants were initially assessed against the PASS/ FAIL criteria to filter out non-compliant tenders. These were agreed at a joint workshop with procurement adviser present.
Stage 2: Individual scoring on the relevant sections of the PQQ was undertaken by the assessment team. Stage 3: This involved a group review of the collated scores. The final score for each prospective bidder was achieved by consensus with procurement adviser present.
Stage 4: A recommendation on the short listed prospective bidders was prepared and submitted to the Civic Centre Programme Board for approval.
3.9The six organisations that had scored the highest of the fourteen organisations that had responded to the PQQ were then invited to tender.
Stage Two – Invitation to Tender
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.