Resolved
Planning permission granted subject to conditions and informatives .
Planning Committee decided this item on Wednesday 12 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Planning permission granted subject to conditions and informatives .
Committee Report Item No. 10 Planning Committee on 12 January, 2011 Case No. 10/2367 __________________________________________________ RECEIVED: 21 September, 2010
WARD: Tokyngton
PLANNING AREA: Wembley Consultative Forum
LOCATION: Unit 4, Second Way, Wembley, HA9 0YJ
PROPOSAL: Change of use from warehouse (Use Class B8) to waste transfer station (Use Class Sui Generis)
APPLICANT: Recycling express limited
CONTACT: JPB Architects
PLAN NO'S: See condition 2 __________________________________________________________
RECOMMENDATION Approval
EXISTING The subject site comprises an industrial unit on Second Way. The site is situated within the Strategic Employment Area therefore surrounding uses are predominantly industrial. Temporary planning permission was granted on the site in 2008 for a change of use from B8 to a waste transfer station (use class Sui Generis) for a period of two years.
PROPOSAL Change of use from warehouse (Use Class B8) to waste transfer station (Use Class Sui Generis)
HISTORY 10/1054 - Details pursuant to condition 7 (air-quality assessment) of planning permission reference 08/1506, dated 14 November 2008, for change of use from warehouse (Use Class B8) to waste-transfer station (Use Class Sui Generis) and installation of tank to front elevation of site Granted - 22/06/2010
09/2641 - Removal of condition 8 (requiring the submission of a construction and freight logistics plan) of planning permission 08/1506, dated 14/11/2008, for change of use from warehouse (Use Class B8) to waste-transfer station (Use Class Sui Generis) and installation of tank to front elevation of site Granted - 12/02/2010
08/3191 - Details pursuant to condition 3 (dust suppression system), 5 (vehicle washing facilities), 9 (training employment strategy), 10 (solar thermal panels), 11 (waste target monitoring) of full planning permission reference 08/1506 dated 14 November 2008 for Change of use from warehouse (Use Class B8) to waste transfer station (Use Class Sui-Generis) and installation of tank to front elevation of site Granted - 14/08/2009 08/1506 - Change of use from warehouse (Use Class B8) to waste transfer station (Use Class Sui-Generis) and installation of tank to front elevation of site Granted - 14/11/2008
POLICY CONSIDERATIONS Brent's Unitary Development Plan 2004 BE2 - Townscape: Local Context & Character EP2 - Noise & Vibration EP3 - Local Air Quality Management EP4 - Potentially Polluting Development TRN3 - Environmental Impact of Traffic TRN4 - Measures to Make Transport Impact Acceptable TRN22 - Parking Standards - Non-residential Developments
LDF Core Strategy 2010 CP20 - Strategic and Borough Employment Areas
SPDs Wembley Masterplan
SUSTAINABILITY ASSESSMENT n/a
CONSULTATION Standard three week consultation period carried out between 08 October 2010 and 29 October 2010 in which 12 properties were notified.
Two letters of objection have been received from neighbouring units which raise the following concerns: • Infestation of flies and rats increased since the commencement of the use • Dust and waste deposits in the air have increased • Rubbish scrapped up against wall shared with Unit 5 resulting in damp and a crack • Closure of public right of way due to serious damage which has occurred to the building
Internal Consultees
Transportation - No objections
Environment Agency - No objections
Environmental Health - Response remains pending. Comments from EH officers will be reported within the Supplementary Report
REMARKS Background
The use in question was granted temporary planning permission for a two year period in 2008. This application seeks to extend this permission further. The application is referable to the Mayor of London under Category 2B (a) of the Schedule of the Order 2008. A response has been received from the Mayor stating that proposal does not have any strategic issues and as a result, no further consultation is required.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Unit 4, Second Way, Wembley, HA9 0YJ (Ref. 10/2367)Report | 161 KB | DownloadRead as text |
Follow Planning Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Aug 2026 | Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... | Decided | Open |
| 5 Aug 2026 | Declarations of interestsNo declarations of interest were made during the meeting. | Decided | Open |
| 5 Aug 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... | Approved | Open |
| 5 Aug 2026 | 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... | Agreed | Open |
| 5 Aug 2026 | Any Other Urgent BusinessThere was no other urgent business. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.