( i ) that the increase in scheme costs by £400,000 from £2.2m to 2.6m be noted, and that this will be funded from the Schools Main Capital Programme at £1m and £1.6m is to be resourced from BNSV monies; (ii) that authority be delegated to the Director of Regeneration and Major Projects to appoint and award a contract to the preferred ‘Contractor A’, who is named in Appendix 3 to the Director’s report and is a contractor from the IESE Framework Agreement in relation to the construction works at , to not exceed £2.35m, subject to an adjustment as considered necessary to the Main Capital Programme , in accordance with the needs of other schools expansion projects on this resource and with the agreement of the Director of Finance and Corporate Services.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1The Executive has noted in 11 August and 15 November 2010 reports that demand for primary school places is forecast to exceed supply in the borough and that by 2015-16, 1680 new primary places will be required.
1.2In its strategy to address the shortage, the Executive had agreed, on 11 August 2010, that the Council’s allocation of Basic Need Safety Valve monies, supported by the School’s Main Capital programme allocations to primary schools for expansion, be utilised.
1.3In the November 2010 Executive report, Park Lane Primary School is identified as a recipient of a share of the Basic Need Safety Valve (BNSV) monies to address expansion and remodelling proposals. The subject report notes that project costs have increased from an estimated £2.2m to an estimated £2.6m, due to necessary re-design and demolition costs. Project costs are to be met within both BNSV monies and the Schools main Capital Programme. In order to meet tight timelines of BNSV spend, this report requests to delegate authority to the Director of Regeneration and Major Projects to appoint and award a contract to a contractor from the IESE (Improvement and Efficiency South East) Framework Agreement to undertake required new build and remodelling works at Park Lane Primary School.
1.4The award of contract to ‘ Contractor A’ via delegated authority to the Director of Regeneration and Major Projects is estimated at £2.35m which is the budget sum set aside; such sum to be subject to an adjustment from the Main Capital Programme, as he considers necessary and as further detailed in
v4 paragraph 3.7 and with the agreement of the Director of Finance and Corporate Services.
2.0Recommendations The Executive is recommended:
2.1To note the increase in scheme costs by £400,000 from £2.2m to 2.6m. This will be funded from the Schools Main Capital Programme at £1m and £1.6m is to be resourced from BNSV monies.
2.2To delegate authority to the Director of Regeneration and Major Projects to appoint and award a contract to the preferred ‘Contractor A’, who is named in Appendix 3 and is a contractor from the IESE Framework Agreement in relation to the construction works at Park Lane Primary School, to not exceed £2.35m, subject to an adjustment as considered necessary to the Main Capital Programme, in accordance with the needs of other schools expansion projects on this resource and with the agreement of the Director of Finance and Corporate Services.
3.0Detail
Proposed scheme
3.1The Executive noted in the 11 August 2010 Executive report the shortage of primary school places in the borough. Brent Council has proposed the expansion of Park Lane Primary School to increase the number of Year R to Y6 places from 1 Form of Entry (FE) to 2FE and to also improve the quality of accommodation through additional specialist rooms, including the provision of a food & science classroom, a library resource, staff Planning, Preparation and Assessment room and a new hall. In addition works will also include improving the school’s accessibility; the installation of a lift and the provision of improved KS1 inter-related internal and external play areas.
3.2Park Lane Primary School is a co-educational, non-denominational Community school for age 3 -11 pupils. It is a popular one form of entry school i.e. 30 places per year group and is currently operating Reception to Year 3 as 2FE on a (now) permanent basis, following Planning Permission to physically expand. The expansion of Park Lane Primary School by 1FE to 2FE is an essential step that enables the Council to meet its statutory duty to provide school places and to enable the additional year classes to progress through the school.
Contribution of the scheme in delivering school places
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.