London Borough of Brent
Executive, Monday 13 June 2011 at 7.00pm

Authority to award construction contract - Albert Road Resource Centre - John Billam Playing Fields, Woodcock Hill, Kenton

Approved Executive 1 paper

Executive approved this item on Monday 13 June 2011. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

that approval be given to the award of the main construction contract for construction of a new Day Care Centre at John Billam Playing Fields to replace the one currently situated at Albert Road to Wates Construction Limited in the Contract Sum of £4,315,097.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Executive

Recommendations

The Executive is requested to:

2.1Approve the award of the main construction contract for construction of a new Day Care Centre at John Billam Playing Fields to replace the one currently situated at Albert Road to Wates Construction Limited in the Contract Sum of £4,315,097.

3.0DETAIL

3.1On 14 July 2009 Executive provided approval in principle to the relocation of the Adult Day Care Centre from Albert Road to provide a modern purpose built facility in a more centrally located area and also to facilitate the proposals for regeneration of the South Kilburn area.

3.2Following a search by officers of a suitable alternative site on 16 November 2009 the Executive approved the John Billam Playing Fields site as the preferred alternative location for this facility. This approval was subject to the appropriation of the site for planning purposes and also to the grant of planning permission. Members were subsequently informed during the Executive meeting held on 26 July 2010 of the progress made in securing the site and the outcome of stakeholder consultation. Members also approved the total budget estimate for construction at

Last revised Master Document £4.755million and approved the requisite variation to the long lease already in existence on this site and granted in favour of Gujarati Ayra Association London (GAA London).

3.3The site identified for the new building is shown on the attached plan in Appendix 2; also attached as Appendix 1 is the final design of the proposed building.

3.4In December 2010, in accordance with standing order 86 (d) (ii), Officers agreed to Brent Council’s participation in the IESE Framework Agreement in order to approve an enabling works package by the selected IESE Framework contractor. The enabling works contract was subsequently awarded to Wates Construction Limited and they are currently on site. The enabling package had become a requirement of the variation of the GAA London’s lease from the Council and had to be completed prior to the Council entering into contract for the main works.

3.5On 15 October 2010 the GAA London entered into an Agreement for Deed of Variation and Surrender of Part (‘Agreement’) with the Council to allow the Council to carry out the necessary works, namely;

a) The re-provision of 108 car parking spaces to the south of Kenton Hall.

b) The re-surfacing of the access road layout and internal access ways including to the front of Kenton Hall.

c) The reinstatement of the car park to the north of Kenton Hall to landscaped open (green) space.

d) The black top finish to the car parking spaces the access road layout and internal access ways

Pursuant to the Agreement, the GAA London are obliged to enter into the deed of variation with the Council when the re-provision of the car parking spaces and the re-surfacing of the access road referred to in (a) and (b) above, but excluding the black top finish to the car parking spaces, access road layout and internal accessways, are completed.

When the deed of variation is completed, the deed will incorporate additional land in the GAA London lease for additional car parking and will also surrender back to the Council the area of land to the north of Kenton Hall which will be used as landscaped open (green) space.

4.0PROCUREMENT OF THE MAIN WORKS CONTRACT

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Authority to award construction contract: Albert Road Resource Centre: John Billam Playing Fields, Woodcock Hill, KentonReport 613 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 19 attended
AJ
Councillor Ann John OBEChair, present
MB
Councillor Muhammed ButtVice-Chair, present
MA
Councillor Mary ArnoldCommittee Member, present
LB
Councillor Lincoln Beswick MBECommittee Member, present
GC
Councillor George CraneCommittee Member, present
LJ
Councillor Lesley JonesCommittee Member, present
JL
Councillor Janice LongCommittee Member, present
JM
Councillor Jim MoherCommittee Member, present
RM
Councillor Ruth MoherCommittee Member, present
JP
Councillor James PowneyCommittee Member, present
EA
Councillor Emad Al-EbadiCommittee Member, in attendance
BC
Councillor Bhagwanji ChohanCommittee Member, in attendance

All 19 on the meeting page

On this subject at Brent

Search all
  1. Authority to award construction contract - Albert Road Resource Centre - John Billam Playing Fields, Woodcock Hill, KentonThis decision
  2. Authority to award a contract for a Single Delivery Partner for the South Kilburn Regeneration ProgrammeDecided
  3. Authority to Direct Award a Contract for Children's Public Health Services (0-19 years) Health Visiting and School NursingApproved
  4. Authority to delegate decision to Authorise Award of Contract(s) for (i)Transportation and Reprocessing of Co-Mingled Recycling Materials (Lot 1) & (ii) Reprocessing of Fibre Material (Lot 2).Noted
  5. Authority to Award Contract for Secure Cycle Parking - Bike Hangers & NestsApproved
  6. Authority to Award Contract for Temporary Recruitment Services (Managed Service Provider)Approved

More from Brent Executive

All decisions
MeetingDecisionOutcome
16 Jun 2014 Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ... Approved Open
16 Jun 2014 Adult Home Care Services - framework appointments(i) that approval be given to the appointment to the West London Alliance Framework to provide Home Support of those ... Approved Open
16 Jun 2014 Advocacy Services - Learning Disabilities, Safeguarding, Mental Health and Older People and Young People with Physical Disabilities( i ) t hat Voiceability Limited be awarded a contract as lead organisation for a consortium for Advocacy Services fo... Noted Open
16 Jun 2014 Safer Lorry Scheme( i ) that the principle of creating a new pan-London traffic order requiring minimum safety features for all HGVs ov... Agreed Open
16 Jun 2014 Leasing of Office Accommodation Brent Civic Centre, Engineers Way, Wembley, HA9 0FJthat a lease of up to 10 years be entered into on office accommodation in the Civic Centre in accordance with the det... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies