( i ) that approval be given to proceed with the remediation work at St Raphael’s and Brentfield Estates in accordance with the remediation design approved by the Environment Agency using the £1,422,525 grant monies allocated; (ii) that it be noted that the grant funding will only cover the cost of basic re-instatement of fencing and turf, and that Brent Housing Partnership (BHP) proposes to make a contribution from its capital budgets for necessary works outside the scope of the grant such as re-instatement of sheds etc; (iii) that the timing issues relating to the works set out in paragraphs 3.11 – 3.16 of the report from the Director of Environment and Neighbourhood Services be noted and that, in view of the urgent requirement to ensure that works are completed by 31 March 2012, an exemption from Standing Orders has been sought and granted from the Director of Finance and Corporate Resources on grounds of extreme urgency pursuant to Standing Order 84(b) after consultation with the Director of Legal and Procurement, exempting the procurement from the requirement to seek Executive authority to go out to tender for remediation works and exempting the requirement to use a single stage or two stage tender process; (iv) that the procurement process for remediation works being followed as set out in paragraphs 3.16 and 3.17 of the report be noted and the Director of Environment and Neighbourhood Services be authorised to award the contract for remediation works following the identification of a preferred contractor.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1Following an Executive decision on 26 July 2010 sixty one properties in St Raphael’s and Brentfield estates have been formally determined as contaminated and a remediation statement has been written setting out how the remediation will be undertaken and by when.
1.2An award of grant to cover the costs of the remediation works has been made by the Environment Agency which requires the works to be completed by 31 March 2012. This report informs the Executive of the procurement process proposed and of an exemption to Standing Orders approved on the grounds of extreme urgency to allow tenders to be invited to meet the demanding timetable and avoid potential loss of grant.
Recommendations
2.1Members agree to proceed with the remediation work at St Raphael’s and Brentfield Estates in accordance with the remediation design approved by the Environment Agency using the £1,422,525 grant monies allocated.
2.2Members note that the grant funding will only cover the cost of basic re- instatement of fencing and turf, and that Brent Housing Partnership (BHP)
Meeting: Executive Version no.3.0 Date 17 August 2011 Date 3 August 2011 proposes to make a contribution from its capital budgets for necessary works outside the scope of the grant such as re-instatement of sheds etc.
2.3Members note the timing issues relating to the works set out in paragraphs 3.11 – 3.16 and that, in view of the urgent requirement to ensure that works are completed by 31 March 2012, an exemption from Standing Orders has been sought and granted from the Director of Finance and Corporate Resources on grounds of extreme urgency pursuant to Standing Order 84(b) after consultation with the Director of Legal and Procurement, exempting the procurement from the requirement to seek Executive authority to go out to tender for remediation works and exempting the requirement to use a single stage or two stage tender process.
2.4Members note the procurement process for remediation works being followed as set out in paragraphs 3.16 and 3.17 and authorise the Director of Environment and Neighbourhood Services to award the contract for remediation works following the identification of a preferred contractor.
3.0Detail
3.1The Council has a statutory duty under Part II(A) of the Environmental Protection Act 1990 and the Contaminated Land (England) Regulations 2006to inspect land in the Borough and identify potentially polluted land which could pose a risk to human health. Where such land is identified the council has a further duty to assess whether the pollution poses a significant possibility of significant harm to human health. Where it determines that it does so, the council must act to remove that risk of harm by securing the remediation of the land or otherwise.
3.2A phased soil investigation was undertaken to look for contamination associated with the historic sewage works from October 2008 to June 2010 at St Raphael’s and Brentfield Estates.
3.3Benzo-a-pyrene levels that may pose a significant possibility of significant harm have been identified in three areas, two areas of St Raphael’s Estate and one in Brentfield estate. Benzo-a-pyrene is a known carcinogen.
3.4Members considered this issue on 26 July 2010 and agreed a number of recommendations including:
1. a safe determination value of 17 ppm for benzo-a pyrene
2. that further assessment of 138 properties be undertaken in order to identify the exact number of properties which exceed the 17ppmdetermination value.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.