i. that the report which identified opportunities for collaborative procurement and improved service provision in the future, be noted; ii. that an exemption from standing orders for the procurement of interim Highway Maintenance Framework Agreements on the basis of good operational reasons as set out in Section 3 of the report be agreed and the establishment of these Framework Agreements as listed in paragraph 3.2 of the report be approved. iii. iv. that the appointment to the Highways Maintenance Framework Agreements of the contractors listed in Appendix 1from 1 st August 2012 until 31 st March 2013 be approved.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report considers the contractual situation regarding the Council’s management of Highways Maintenance. It proposes an effective seven month extension of the existing arrangements in order to maximise potential benefits from the emerging collaborative contract procurement across London and accordingly requests authority to award framework agreements as required by Contract Standing Order No 88.
Recommendations
2.1The Executive notes the contents of this report which identifies opportunities for collaborative procurement and improved service provision in the future.
2.2The Executive agree to an exemption from standing orders for the procurement of interim Highway Maintenance Framework Agreements on the basis of good operational reasons as set out in Section 3 of this report and approves the establishment of these Framework Agreements as listed in paragraph 3.2
2.3The Executive approve the appointment to the Highways Maintenance Framework Agreements of the contractors listed in Appendix 1from 1st August 2012 until 31st March 2013.
Executive Version 8 19 September 2011 6 September 2011 3.0 Detail
The current contractual arrangements for Highways Maintenance Works
3.1The Council spends between £7-8M a year on highways works across the borough, a significant proportion of which is funded by Transport for London, and from the Council’s own capital programme and some from the Council’s revenue budget. This is a fluctuating budget, and covers a wide range of works, from significant investments in junctions to minor repairs of tarmac.
3.2At present the Council is not in any collaboration to deliver this work. In 2008, the Council let framework agreements for the following activities:
• Cold planing and carriageway resurfacing • Hand laid bituminous surfacing • Paving and repairs • Anti-skid road surfacing (high friction coating) • Street furniture painting and repairs • Line markings
3.3European legislation permits the award of either a single contractor framework or a multi-contractor framework which must, where possible, have a minimum of 3 contractors on it. The framework agreements let in 2008 are all multi- supplier framework agreements with 3 contractors appointed to each framework. The multi-contractor framework agreements mitigate the risk of not being able to resource labour to meet the required outputs.
3.4In procuring the framework agreements in 2008, at the contract evaluation stage, the contractor offering the best value for money was determined for each framework, not only overall but also for each type of work delivered within the framework. As such the Council contracts with different contractors under the framework agreements depending on the nature of the works or services required.
3.5The appointed contractors are used to deliver work ranging from minor responsive maintenance repairs to carriageway resurfacing, pavement upgrades, traffic schemes, CPZs and town centre improvements. Selection of contractors to deliver theses defined works has been in accordance with the best value evaluation detailed in paragraph 3.4 although a mini-competition is held between contractors on the framework where elements of the work are outside the scope of the contract, to ensure best value for money.
3.6The framework agreements commenced in August 2008 for a period of 3 years with an option to extend for a further year. The contractors have performed satisfactorily with no claims and disputes. Only one supplier has dropped out of frameworks 4 & 5 as they were unable to continue to commit to the contracted rates. Following meetings with contractors to discuss further efficiencies (resulting in potential savings in the region of 2% p.a.) and an evaluation of whether the framework agreements still provide value for money
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.