Resolved
Granted temporary planning permission subject to conditions and to the final agreement of the Environment Agency.
Planning Committee agreed this item on Wednesday 23 November 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Granted temporary planning permission subject to conditions and to the final agreement of the Environment Agency.
Committee Report Item No. 08
Planning Committee on 23 November, Case No. 11/2367 2011 Planning Committee Map Site address: Wembley Arena, Engineers Way & Wembley National Stadium, Olympic Way, Wembley, HA9
© Crown copyright and database rights 2011 Ordnance Survey 100025260
This map is indicative only. RECEIVED: 9 September, 2011
WARD: Tokyngton
PLANNING AREA: Wembley Consultative Forum
LOCATION: Wembley Arena, Engineers Way & Wembley National Stadium, Olympic Way, Wembley, HA9
PROPOSAL: Erection of temporary structures, a temporary retractable walkway and cable bridge across Engineers Way, vehicle and pedestrian access areas, temporary secure perimeter fencing and civil engineering works to level surface of land to north of Engineers Way. Proposal includes the temporary closure of Engineers Way from the 18th July 2012 to the 13th August 2012. The proposed temporary works are to facilitate the hosting of events at Wembley Arena and Wembley National Stadium during the London 2012 Olympics.
APPLICANT: LOCOG
CONTACT: Savills (L & P) Ltd
PLAN NO'S: See condition 2. __________________________________________________________
RECOMMENDATION Grant Temporary Planning Permission subject to the final agreement of the Environment Agency.
EXISTING This application relates to an area located around Wembley Arena and Wembley Stadium.
Wembley Arena is London’s second largest indoor arena, located opposite Wembley Stadium. It is primarily used for music events but has also held sporting events such as boxing, martial arts, darts, basketball, ice hockey, and the Badminton World Championships.
Wembley Stadium Station, Wembley Park Station and Wembley Park Station all within easy walking distance offering direct rail services to Marylebone and Euston Stations and access to the Jubilee, Metropolitan and Bakerloo lines.
The site falls within the Wembley Growth Area and overlaps with both Quintain Estate’s Stage I Masterplan and its North West Lands Masterplan areas. A number of significant new developments have recently been completed within the area and a number are under construction including the Council’s new Civic Centre which lies on the opposite side of Engineers Way to the Arena.
PROPOSAL Both Wembley Arena and Wembley Stadium have been selected as venues as part of the London 2012 Olympics The Arena will be hosting the badminton and rhythmic gymnastic competitions and the Stadium the football.
In order to facilitate the hosting of these events planning permission is being sought by the London Organising Committee of the Olympic Games (LOCOG) for a number of temporary structures including warm up courts, site compounds, a temporary retractable walkway and cable bridge across Engineers Way, vehicle and pedestrian access areas and temporary security fencing and for works to level the surface of an area of land to the north of Engineers Way. In addition Engineers Way will be closed to the public for the period 18th July to 13th August 2012 inclusive (27 days).
It is anticipated that all temporary structures will be removed September 2011.
HISTORY Wembley Arena is an existing venue, built in 1934 for the Empire Games, originally called the Empire Pool, it was designed as an indoor venue for swimming. The venue has historical links with the Olympics hosting the swimming events for the 1948 Summer Games. This Grade II listed building was comprehensively refurbished and re-opened in 2006 as part of Quintain's Stage I masterplan consent granted in 2004. The Stage I development is well underway, with Wembley Arena and Arena Square operating, 520 mixed-tenure homes delivered, and more building work underway on a new Hilton Hotel and student accommodation. Work on the retail outlet centre and cinema multiplex is expected to commence in either this or next month.
The Arena is owned by Quintain but managed by Live Nation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Wembley Arena, Engineers Way & Wembley National Stadium, Olympic Way, Wembley, HA9 (Ref.11/2367)Report | 820 KB | DownloadRead as text |
Follow Planning Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Aug 2026 | Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... | Decided | Open |
| 5 Aug 2026 | Declarations of interestsNo declarations of interest were made during the meeting. | Decided | Open |
| 5 Aug 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... | Approved | Open |
| 5 Aug 2026 | 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... | Agreed | Open |
| 5 Aug 2026 | Any Other Urgent BusinessThere was no other urgent business. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.