Grant consent subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning to agree the exact terms thereof on advice from the Director of Legal and Procurement Services.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
This map is indicative only. RECEIVED: 5 October, 2011
WARD: Wembley Central
PLANNING AREA: Wembley Consultative Forum
LOCATION: Central Square, Wembley, HA9
PROPOSAL: Erection of a new 5 storey block incorporating a retained station ticket hall and new platform access corridor 2729 sqm of new retail floor space, an 86 bedroom hotel including a bar and restaurant and 38 new residential flats. This is a replacement scheme for 'Building 2' of the original planning permission for the redevelopment of Central Square granted on the 13/10/2005 (reference 03/3765).
APPLICANT: Sowcrest Limited
CONTACT:
PLAN NO'S: See condition 2 __________________________________________________________
RECOMMENDATION Grant consent subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning to agree the exact terms thereof on advice from the Director of Legal and Procurement Services.
SECTION 106 DETAILS The original Scheme for the redevelopment of Central Square attracted a financial contribution of £1,067,808. Of this only £105,000 has been paid leaving £982,808 still owing. In addition the outstanding sum has now accrued approximately £195,000 of interest making the outstanding sum approximately £1,178,250.
As part of this application to amend the final phase of the scheme the developer is seeking to negotiate a reduction in the level of the contribution. A reduction of 30% on the outstanding sum, and the removal of any interest accrued up until now is sought. This would result in a reduction of the contribution owed by £489,842.
The contribution that Council would therefore receive for the completed scheme would be £688,408 plus the £105,000 of the original contribution that has been paid.
Justification The developer has provided financial data to officers demonstrating scheme to be un-profitable. This in itself would not normally be justification for a reduction in an agreed s106 contribution. The potential for a scheme to make a loss is part of the development risk. However there are other mitigating factors. The developer has provided 85 affordable dwellings or 35% of the total units built and proposed (240 units including the reduced number of flats to be provided in the revised proposals for Building 2). On recent comparable schemes in Wembley the level of affordable housing being agreed is significantly less.
The significant additional costs associated with building over the existing station deck also make building the final phase of the scheme unattractive. However even with a reduced Section 106 financial contribution the scheme has brought substantial benefits to the area. The completed first phases have provided much needed new retail floor space, replacing a tired and run down 1960’s shopping precinct, and resulting in new retail investment in the heart of the town centre. The first phases have also provided new private and affordable housing in the centre of Wembley and a new public square. The completed scheme will bring further benefits to the local economy through additional retail floor space and a new hotel and will greatly improve the appearance and physical environment of the area. It will also provide a new entrance to the station ticket hall and goes hand in hand with other station improvements planned or currently already underway by London Underground Ltd and Network Rail.
Given the benefits to Wembley and subject to a condition requiring that the scheme commences with 8 months of a decision being made officer’s consider the proposed reduction in financial contribution to be acceptable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.