Item6

Resolved

( i ) that this Executive’s agreement to the interim service strategy agreed on 16 January 2012 be reconfirmed; (ii) that the proposal to use the closed buildings in Kensal Rise, Neasden and Cricklewood as part of the Council’s library service and interim service delivery strategy be rejected due to the conclusive need to provide a service from Willesden Green.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Executive

Summary

1.1This report responds to call in by the Overview and Scrutiny Committee on 1 February 2012 of the Willesden Green Redevelopment Project which RESOLVED:- that the Executive be recommended to reconsider proposals for the interim service delivery strategy and specifically consider the use of some closed existing libraries and the costings involved for the proposed strategy in order to provide a comprehensive interim library service for residents.

1.2This report builds upon the information that was provided to the Executive on 16 January 2012 Willesden Green Library Centre (WGLC) Redevelopment. Since that date, Brent Council’s Library Transformation Project has successfully been upheld in the Supreme Court having previously been upheld in the High Court and the Court of Appeal.

1.3This report shows that the on-going need for a library in Willesden Green is proven and supported by the courts; therefore the use of closed library buildings is not appropriate.

Recommendations

2.1That the Executive reconfirms its agreement to the interim service strategy agreed on 16 January 2012.

2.2The Executive rejects the proposal to use the closed buildings in Kensal Rise, Neasden and Cricklewood as part of the Council’s library service and interim

Meeting Executive Version no. 2.2 Date 13 February 2012 Date 6 February 2012 service delivery strategy due to the conclusive need to provide a service from Willesden Green.

3.0Detail

3.1The interim service delivery strategy is thorough and comprehensive and was covered in detail in the original January 2012 Executive report in paragraphs 6.4-6.36 and is summarised again below. The plan will develop further in the seven months before the redevelopment. The costs of delivering the interim service strategy are set out in Appendix 1 and are fully covered by the current budget for Willesden Green Library Centre (WGLC).

3.2The interim service delivery strategy also builds upon the Library Transformation Project (LTP), approved by the Executive in April 2011. The improvements are set out in detail in that report, but some of the key areas include: • 7 day a week opening at all the Council’s libraries • Improved online services including virtual reading groups, improved reservation services and more reference materials • An extensive home delivery and outreach service • Exciting events and courses • More public involvement in future stock development • Additional support for children, young people, families and people with disabilities

3.3In addition to this the new Civic Centre at Wembley will open by June 2013, providing access to a larger library, more study space and public IT facilities.

Interim library service 3.4 During the redevelopment core library functions will be provided from Grange Road (located next door to the current WGLC) and another location in the heart of Willesden Green (the negotiation will be finalised once the Development Agreement is signed).

3.5Whilst the size of the book stock in the physical library building will be temporarily reduced during the redevelopment Officers are working to minimise the impact on active borrowers. During the redevelopment the reservation service for which there is currently a fee will be free and the speed of reservation service will be improved, giving access to the full collection of 6 million books. Customers will be able to obtain any stocked title within five working days and any unstocked title within two weeks (currently 7 days and three weeks). The current WGLC is 1,368m2 and holds 60,000 books (on loan and on shelves). During the interim, 30,000 books will be on loan and on the shelves in roughly 270m2 of library space across 2 buildings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Reference of item considered by Call in Overview and Scrutiny Committee: Willesden Green redevelopment projectReport 184 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
AJ
Councillor Ann John OBEChair, present
MB
Councillor Muhammed ButtVice-Chair, present
MA
Councillor Mary ArnoldCommittee Member, present
LB
Councillor Lincoln Beswick MBECommittee Member, present
GC
Councillor George CraneCommittee Member, present
LJ
Councillor Lesley JonesCommittee Member, present
JL
Councillor Janice LongCommittee Member, present
JM
Councillor Jim MoherCommittee Member, present
RM
Councillor Ruth MoherCommittee Member, present
JP
Councillor James PowneyCommittee Member, present
BC
Councillor Bhagwanji ChohanCommittee Member, in attendance
SC
Councillor Shafique ChoudharyCommittee Member, in attendance

All 17 on the meeting page

On this subject at Brent

Search all
  1. Reference of item considered by Call in Overview and Scrutiny Committee - Willesden Green redevelopment projectThis decision
  2. Reference of item considered by Scrutiny Committees (if any)Decided
  3. Reference of item considered by Scrutiny Committees (if any)Decided
  4. Reference of item considered by Scrutiny Committees (if any)Decided
  5. Reference of item considered by Scrutiny Committees (if any)Decided
  6. Reference of item considered by Scrutiny Committees (if any)Decided

More from Brent Executive

All decisions
MeetingDecisionOutcome
16 Jun 2014 Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ... Approved Open
16 Jun 2014 Adult Home Care Services - framework appointments(i) that approval be given to the appointment to the West London Alliance Framework to provide Home Support of those ... Approved Open
16 Jun 2014 Advocacy Services - Learning Disabilities, Safeguarding, Mental Health and Older People and Young People with Physical Disabilities( i ) t hat Voiceability Limited be awarded a contract as lead organisation for a consortium for Advocacy Services fo... Noted Open
16 Jun 2014 Safer Lorry Scheme( i ) that the principle of creating a new pan-London traffic order requiring minimum safety features for all HGVs ov... Agreed Open
16 Jun 2014 Leasing of Office Accommodation Brent Civic Centre, Engineers Way, Wembley, HA9 0FJthat a lease of up to 10 years be entered into on office accommodation in the Civic Centre in accordance with the det... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies