Grant planning permission subject to conditions as amended in conditions 2, 5 and 9, an addition of conditions 10 and 11 and delegate authority to the Head of Area Planning, or other duly authorised person, to agree the exact terms thereof as amended, on advice from the Director of Legal and Procurement. If the applicant fails to demonstrate the ability to provide for the s106 terms and meet the policies of the Unitary Development Plan, Core Strategy and Section 106 Planning Obligations Supplementary Planning Document by concluding an agreement within an appropriate timescale, to delegate authority to the Head of Area Planning, or other duly authorised person, to refuse planning permission.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
This map is indicative only. RECEIVED: 19 June, 2012
WARD: Northwick Park
PLANNING AREA: Wembley Consultative Forum
LOCATION: Northwick Park Hospital, Watford Road, Harrow, HA1 3UJ
PROPOSAL: Demolition of existing single storey building and the erection of a part 1, part 2 and part 3 storey building in order to provide a new accident and emergency department on land adjacent to blocks G and E of Northwick Park Hospital. Proposal includes a partial realignment of the existing site access road the creation of new access roads, new ambulance and public drop off areas, pedestrian ramps and footpaths, plant room, new retaining walls and landscaping.
APPLICANT: The Northwest London Hospital NHS Trust
CONTACT: The Northwest London Hospital NHS Trust
PLAN NO'S: See condition no 2 __________________________________________________________ RECOMMENDATION Grant planning permission subject to the completion of a satisfactory Section 106 or other legal agreement and delegate authority to the Head of Area Planning, or other duly authorised person, to agree the exact terms thereof on advice from the Borough Solicitor
If the applicant fails to demonstrate the ability to provide for the s106 terms and meet the policies of the Unitary Development Plan, Core Strategy and Section 106 Planning Obligations Supplementary Planning Document by concluding an agreement within an appropriate timescale, to delegate authority to the Head of Area Planning, or other duly authorised person, to refuse planning permission.
SECTION 106 DETAILS The application requires a Section 106 Agreement, in order to secure the following benefits:
1. Payment of the Council’s legal and other professional costs in (i) preparing and completing the agreement and (ii) monitoring and enforcing performance. 2. Within 3 months of any occupation, submit for approval and adhere to an updated Travel Plan for the Hospital, including car sharing measures. 3. Sustainability - Prior to material start, the submission and approval of a detailed sustainability implementation strategy including BREEAM Excellent design stage assessment for the new A& E building and measures to implement material details of the approved Sustainability Checklist to achieve a minimum score of 50%, in addition to adhering to the ICE Demolition Protocol, and implementation of those approved details. Within 3 months of any occupation submission of BREEAM Post Construction Certificate to demonstrate ‘Excellent’ level has been achieved, with compensation should it not be delivered. 4. Prior to material start submission and approval of details demonstrating that the carbon reduction target (25% improvement over TER of 2010 Building Regulations on all systems) will be met on-site and implementation of the approved details. Where it is clearly demonstrated and the Council agrees that specific targets cannot be fully achieved on-site, any shortfall may be provided off-site or through works to other buildings within Hospital site (providing this does not represent double counting) as agreed by the Council, or an in lieu contribution to secure delivery of carbon dioxide savings elsewhere. 5. Join and adhere to the Considerate Contractors scheme and submit a Certificate of Compliance for verification within 3 months of any occupation.
And, to authorise the Head of Area Planning, or other duly authorised person, to refuse planning permission if the applicant has failed to demonstrate the ability to provide for the above terms and meet the policies of the Unitary Development Plan and Section 106 Planning Obligations Supplementary Planning Document by concluding an appropriate agreement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.