( i ) that approval be given to appoint to the Framework the providers listed in paragraph 3.27 for Supporting People services for a period of four years; (ii) that approval to award five call-off contracts to the providers detailed in paragraph 3.32 for a period of two years followed by discretionary extensions of 1 year plus 1 year (up to a maximum of four years); (iii) that approval be given to exemption in accordance with Contract Standing Order 84(a) from the usual tendering requirements of Contract Standing Orders to renew the existing 26 Supporting People contracts referred to in paragraph 3.9 for 5 weeks and 9 weeks on the basis of good operational and financial reasons as set out in paragraph 3.9 of the report from the Directors of Adult Social Services and Regeneration and Major Projects.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report requests authority to award a Framework Agreement as required by Contract Standing Order No 88. This report summarises the process undertaken in tendering this Framework Agreement and, following the completion of the evaluation of the tenders, recommends providers to be appointed onto the Framework Agreement and the award of five (5) call-off contracts to the proposed Framework Providers.
1.2This report further requests authority to renew a number of existing contracts for 5 - 9 weeks to ensure planned implementation for the five call-off contracts referred to in Paragraph 1.1.
Recommendations
2.1That the Executive agrees to appoint to the Framework the providers listed in paragraph 3.27 for Supporting People services for a period of four (4) years.
2.2That the Executives approves to award five (5) call-off contracts to the providers detailed in paragraph 3.32 for a period of two (2) years London Borough of Brent Precedent 10(f) Page 1 Contract Procurement and Management Guidelines December 2003
2.3The Executive to give approval to an exemption in accordance with Contract Standing Order 84(a) from the usual tendering requirements of Contract Standing Orders to renew the existing 26 Supporting People contracts referred to in paragraph 3.9 for 5 weeks and 9 weeks on the basis of good operational and financial reasons as set out in paragraph 3.9 of this report.
3.0Detail
Background
3.1Supporting People is a national preventative programme administered by local government which aims to enable vulnerable people to live independently in the community through providing housing-related support services. Housing support workers, sheltered housing managers, women’s refuge workers, etc. support vulnerable adults to prevent hospital admissions, evictions, mental ill health, homelessness and anti-social behaviour. The budget is additionally utilised to provide a range of non-statutory welfare services including handyperson, accident prevention, and hospital discharge support. The programme provides support to over 3,500 people at any time, through 62 separate contracts, held across 38 providers.
3.2Responsibility for the commissioning of services to provide local housing-related support sits with Brent Council’s Adult Social Care (ASC) department. Governance of this service area is maintained jointly by the ASC Departmental Management Team and the Supporting People Commissioning Body.
3.3In Brent, the budget for local Supporting People services in 2012-13 is £9.9m; having been reduced by £1.8m when compared to the 2010-11 budget. These savings of £1.8m have been achieved primarily through negotiations with existing service providers which resulted in reductions to the hourly rate for support in line with benchmarked rates paid across the West London sub-region.
3.4This service area and associated budget are currently subject to the One Council Supporting People Project, which is tasked with delivering further savings of £900k in 2013-14 which is dependent on the successful re-procurement of existing contracts.
3.5On 12th March 2012, approval for arrangements to procure Supporting People services for existing contracts terminating in 2012 was granted by the Executive. The Executive authorised Council Officers to extend current contracts to enable the Council to utilise the West London Alliance Supporting People Framework, which at the time of report was London Borough of Brent Precedent 10(f) Page 2 Contract Procurement and Management Guidelines December 2003
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.