( i ) that the proposed £10.2M investment in Brent’s transport infrastructure, an increase of 36% above that in 2012-13, be noted; (ii) that approval be given to invest the Brent highways capital programme for 2013/14 of £3.5 million as follows: % of Brent capital Budget Amount (£ 000’s) Footways Major footway improvements (long sections) 44% 1,525 Footway improvements (short sections) 4% 150 Public realm improvements 3% 125 Sub-total 51% 1,800 Carriageways Resurfacing of unclassified roads 38% 1,300 Resurfacing of B & C Class roads 4% 150 Resurfacing of short sections 4% 150 Sub-total 46% 1,600 Contingencies for TfL schemes 3% 100 Total 100% 3,500 (iii) that approval be given to the proposed 2013/14 highway improvement schemes and reserve schemes listed in Appendices 2 & 3; (iv) that the funding of £5.147million from TfL to fund a wide range of transport improvements for Brent’s residents through the LIP programme (set out in Appendix 5 of the report from the Director of Environment and Neighbourhood Services) and the £724,000 Principal A Road maintenance programme (set out in Appendix 2 of the Director’s report) be noted.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1In 2012-13 roughly £7.5 million will have been spent improving Brent’s transport infrastructure: resurfacing 7 miles of road and 4 miles of footway and building over 20 schemes to improve safety and accessibility for our residents.
1.2In 2013-14 over £10.2 million will be spent improving Brent’s roads, footways and transport infrastructure. This is a 36% increase and will be funded by Brent Council, Transport for London (TfL) and Section 106 funds from developers.
1.3Of the total £10.2 million investment, £5.1 million has been allocated to Brent by TfL to support Brent’s Local Implementation Plan (LIP) with a further £724,000 for Principal (A) roads. Details of the LIP and A road programme are provided in this report.
1.4It is proposed to allocate £3.5 million of Brent capital to maintain the highway network, subject to approval of the Budget and Council Tax report on 11 February 2013 and full Council approval on 25 February 2013.
1.5This report sets out recommendations for how Brent’s £3.5 million capital budget should be allocated through a prioritised programme of:
• Major and minor pavement upgrades; • Road resurfacing; and • Improvements to the public realm.
Recommendations
Executive Version 2.1 11 February 2013 Updated 29 January 2013 2.1 That the Executive notes the proposed £10.2M investment in Brent’s transport infrastructure, an increase of 36% above that in 2012-13.
2.2That the Executive agrees to invest the Brent highways capital programme for 2013/14 of £3.5 million as follows:
Amount % of Brent (£ 000’s) capital Budget Footways Major footway improvements (long sections) 44% 1,525 Footway improvements (short sections) 4% 150 Public realm improvements 3% 125 Sub-total 51% 1,800 Carriageways Resurfacing of unclassified roads 38% 1,300 Resurfacing of B & C Class roads 4% 150 Resurfacing of short sections 4% 150 Sub-total 46% 1,600 Contingencies for TfL schemes 3% 100 Total 100% 3,500
2.3That the Executive approves the proposed 2013/14 highway improvement schemes and reserve schemes listed in Appendices 2 & 3.
2.4That the Executive note the funding of £5.147million from TfL to fund a wide range of transport improvements for Brent’s residents through the LIP programme (set out in Appendix 5) and the £724,000 Principal A Road maintenance programme (set out in Appendix 2).
3.0DETAIL
3.1Highway Improvements in 2012-13
3.1.1 Our focus is to improve and maintain the roads, footways and transportation network to enhance the environment and improve the safety of Brent residents, and those passing through the Borough.
3.1.2 By 31 March 2013, roughly £7.5 Million (funded by Brent, TfL and S106) will have been spent on improving Brent’s transport infrastructure:
• 38 roads (7 miles in length) will have been resurfaced; • 4 miles of footways will have been resurfaced and improved: • 6 major improvement schemes will be delivered, including: o Sudbury Town Centre improvements o Harrowdene Road Traffic Calming o Wembley Corridor Accessibility scheme o Ealing Road Safety Scheme o Willesden Green Accessibility improvements o Donnington Road 20MPH Zone Executive Version 2.1 11 February 2013 Updated 29 January 2013 • 16 local improvement schemes will be delivered including; o Dudden Hill Lane Safety Scheme o Willesden High Road Safety Scheme o Kenton Road Safety Scheme o Chichele Road Safety Scheme o School Travel Plan Engineering Measures o Bus stop accessibility improvements
3.1.3 Appendix 1 lists major footway upgrades and road resurfacing works carried out in the borough during 2012/13.
3.2Improving the condition of Brent’s roads in 2013-14
3.2.1 Brent’s roads are one of its most important physical assets. The table below sets out their condition by indicating the percentage of each length of road type where maintenance should be considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.