( i ) that approval be given to the following the principles of redevelopment: o that the existing Stonebridge Day Centre be redeveloped to provide new housing o that the listed Stonebridge Primary School be permanently expanded from two Forms of Entry (2FE) to three Forms of Entry (3FE) accommodating ‘bulge classes’ currently located at Stonebridge Day Centre – subject to School Governing Body consent o that the existing Adventure Playground be re-planned and improved o that the Stonebridge Open Space be re-planned and improved o and that residential development is bought forward in order to better utilise the lands (ii) that public consultation and negotiation be undertaken on the development proposals with local stakeholders in particular, the managers of the Adventure Playground, the Welsh School and the Secretary of State in relation to land adjacent to Stonebridge Primary School; (iii) that approval be given to the disposal of the surplus former Stonebridge Day Centre and of any new housing land as indicated in Appendices 1 and 2 of the Director’s report; (iv) that authority be delegated authority to the Operational Director Property and Projects, to agree the detailed terms of the disposal transaction(s) in conjunction with the Director of Finance and Corporate Services; (v) that it be noted that, subject to confirmed scheme costs, there could be a requirement for additional funding. If this is required there will be a separate report to Executive. This could be met from the potentially increased receipt from the Day Centre over and above that included in the capital disposals programme; (vi) that approval be given to the Stonebridge Open Space being taken as a contribution toward the funding of overall redevelopment scheme proposals.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1The subject land is as detailed in Appendix 1 and 2, comprising the former Stonebridge Day Centre currently Stonebridge Primary School Annexe, Stonebridge Primary School including the Welsh School and adjoining lands including the Adventure Playground and Stonebridge Open Space.
1.2The report sets out redevelopment proposals, as per the Urban Initiatives options and capacity study (Appendix 3) and South Studio RIBA stage A & B options and capacity study (Appendix 4) which indicate that the following could be achieved:
- That the existing Stonebridge Day Centre be redeveloped to provide new housing;
- That the listed Stonebridge Primary School be permanently expanded from two Forms of Entry (2FE) to three Forms of Entry (3FE) accommodating ‘bulge classes’ currently located at Stonebridge Day Centre – subject to School Governing Body consent;
- That the existing Adventure Playground be re-planned and improved;
- That the Stonebridge Open Space be re-planned and improved; and
- That residential development is bought forward in order to better utilise the lands.
Recommendations
That the Executive approve:
Meeting Version no.2 Date Date 2.1 The principles of redevelopment as described in 1.2 above.
2.2To undertake public consultation and negotiation on the development proposals with local stakeholders in particular, the managers of the Adventure Playground, the Welsh School and the Secretary of State in relation to land adjacent to Stonebridge Primary School.
2.3The disposal of the surplus former Stonebridge Day Centre (Appendix 1) and of any new housing land (Appendix 2).
2.4To provide delegated authority to the Operational Director Property and Projects, to agree the detailed terms of the disposal transaction(s) in conjunction with the Director of Finance and Corporate Services.
2.5That Executive note that, subject to confirmed scheme costs, there could be a requirement for additional funding. If this is required there will be a separate report to Executive. This could be met from the potentially increased receipt from the Day Centre over and above that included in the capital disposals programme.
2.6The Stonebridge Open Space will be taken as a contribution toward the funding of overall redevelopment scheme proposals
3.0Detail
Background
3.1The former Stonebridge Day Centre comprises a 1960’s building of 1,500 m2 on a site of 0.59 Ha in the middle of which is a residential building that was sold many years ago on a long leasehold basis. The Day Centre was closed as part of the review of day centre provision in 2012 (Appendix 1).
3.2The Day Centre is currently being partially used to accommodate primary school/bulge classes until 2015/16. These bulge classes are being managed by Stonebridge Primary School.
3.3Stonebridge Primary School is located very close to the Day Centre, comprising a handsome Grade II listed Victorian Building of 3,000m2 which currently operates as a 2FE primary school, which given its age does not offer the flexibility that modern schools provide (Appendix 2).
3.4The school is owned by Brent Council, along with the difficult to manage adjoining open space, a relatively well used and popular adventure playground and waste land. Opposite the school is the Our Lady of Lourdes Roman Catholic Primary School owned by the Diocese of Westminster.
3.5The sites are located close to Stonebridge tube station, with good bus routes. It is noteworthy that these Stonebridge lands are located around 0.5 miles away from Bridge Park Sports Centre.
Meeting Version no.2 Date Date 3.6 A cross departmental Officer group involving Property, Planning, Education, Health and Social Care, Environment and Neighbourhood Services, have worked in partnership reviewing land and existing arrangements in order to better utilise lands for the benefit of Brent.
Options – Stonebridge Day Centre
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting- that the minutes of the previous meeting held on 22 April 2014 be approved as an accurate record of the meeting. - ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.