Resolved
Granted subject to a revised Condition 6 regarding car parking.
Planning Committee decided this item on Wednesday 12 February 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Granted subject to a revised Condition 6 regarding car parking.
Committee Report Item No. 03
Planning Committee on 12 February, Case No. 12/3089 2014
Planning Committee Map Site address: SKL House, 18 Beresford Avenue, Wembley, HA0 1YP
© Crown copyright and database rights 2011 Ordnance Survey 100025260
This map is indicative only. RECEIVED: 20 November, 2012
WARD: Alperton
PLANNING AREA: Wembley Consultative Forum
LOCATION: SKL House, 18 Beresford Avenue, Wembley, HA0 1YP
PROPOSAL: Erection of first floor extension to front of building, alterations to the front forecourt layout, reduction in width to existing vehicle access, retention of existing extraction plant/wood burner installation to the rear and change of use from office (B1a) to a mixed use with B2 (general industrial), B8 (warehouse & distribution) with ancillary office and ancillary showroom (as amended by revised plans).
APPLICANT: UKB Ltd
CONTACT: Mann Associates Ltd.
PLAN NO'S: See Condition 2 __________________________________________________________ BACKGROUND This application was deferred by Planning Committee on 11 December 2013. The decision by Members to defer was to allow for the application to be re-considered with an Officer from Environmental Health present at Committee.
Prior to this the application had been deferred from previous Committee's. The application timeline is summarised below;-
· Application deferred from Planning Committee on 18 September 2013 after it came to light a database error had occurredd which meant that not all interested parties had been notified of the Committee arrangements. In these circumstances it was considered appropriate to defer the application to allow the Committee notification issue to be rectified before the application is considered.
· Prior to this the application had been deferred from the Planning Committee meeting of 13 February 2013 in order to allow Members request to undertake a site visit. The intention at that time was to report to the March Committee after the site visit had been carried out.
· Shortly before the Members site visit was due to take place in March 2013 Officers became aware a large piece of plant equipment had recently been erected to the rear of the building. Local residents had bought this to Officers attention. It has since been established that this is a wood burner, and it had been transferred from another site owned by the applicant in Alperton. The applicant was advised that the installation of this plant requires planning permission, and as it is critical to how the use of the building would operate on a day-to-day basis that it would need to be considered at the same time as proposals to extend the building and change it's use. Revised details were requested so that the wood burner could also be considered. As this installation represents a material change to the original submission then it was deemed necessary to re-consult neighbouring properties on these amended proposals. So in light of the request for revised details and the need to re-consult Officers had to request that Members deferred the application. A Members site visit still took place as arranged on 9 March 2013, and the application was deferred from the March committee.
Revised details (including plans and specification) relating to the wood burner were received in April 2013, and further consultation on these changes carried out on 14 May 2013.
Discussion on the wood burner, its visual impact, what it is used for and the impact this has on local amenity is set out in the 'remarks' section (see paragraph's 13 - 19). Also in response to the re-consultation exercise further representations were received. These are also discussed in the 'consultation' section within the main body of the report. UPDATE FROM ENVIRONMENTAL HEALTH SINCE DEFERRAL IN DECEMBER 2013 Since deferral on 11 December 2013 a surprise site visit was carried out by EH, on 19/12/13. At this time the wood burner was in full operation, and no smoke was visible from the burner stack.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SKL House, 18 Beresford Avenue, Wembley, HA0 1YP 03 (Ref. 12/3089)Report | 467 KB | DownloadRead as text |
Follow Planning Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Aug 2026 | Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... | Decided | Open |
| 5 Aug 2026 | Declarations of interestsNo declarations of interest were made during the meeting. | Decided | Open |
| 5 Aug 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... | Approved | Open |
| 5 Aug 2026 | 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... | Agreed | Open |
| 5 Aug 2026 | Any Other Urgent BusinessThere was no other urgent business. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.