Refused planning permission for the following reasons: (1) Height, scale, massing & density of the development in the Mapesbury Conservation Area and in close proximity to Willesden Green Conservation Area and Grade II Listed Willesden Green Station. (2) Inadequate provision of on-site affordable housing. (3) Absence of legal agreement to secure Community Access Plan, Sustainability, job & training opportunities for local residents (‘Brent 2 Work’), Considerate Contractors Scheme, Travel Plan and Permit Free.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
This map is indicative only. RECEIVED: 14 November, 2013
WARD: Mapesbury
PLANNING AREA: Kilburn & Kensal Consultative Forum
LOCATION: 110 Walm Lane, London, NW2 4RS
PROPOSAL: Demolition of existing Public House and Conservative Club and erection of 2 to 10 storey building containing A4/D1 use unit on ground floor and 53 residential units on the ground and upper floors (13 x one bed, 30 x two bed and 10 x three bed). Formation of revised vehicular access from Walm Lane to basement car park comprising 23 parking spaces and associated amenity space, landscaping works and pedestrian access from Walm Lane, subject to Deed of Agreement dated under Section 106 of the Town and Country Planning Act 1990, as amended (revised description).
APPLICANT: Fairview New Homes Ltd
CONTACT:
PLAN NO'S: Refer to Condition 2 __________________________________________________________ RECOMMENDATION To:
(a) Resolve to Grant Planning Permission, subject to an appropriate form of Agreement in order to secure the measures set out in the Section 106 Details section of this report and referral to the Secretary of State, or (b) If within a reasonable period the applicant fails to enter into an appropriate agreement in order to meet the policies of the Unitary Development Plan, Core Strategy and Section 106 Planning Obligations Supplementary Planning Document, to delegate authority to the Head of Area Planning, or other duly authorised person, to refuse planning permission
SECTION 106 DETAILS The application requires a Section 106 Agreement, in order to secure the following benefits:-
(i) Payment of the Council's legal and other professional costs on completion of the deed in (a) preparing and completing the agreement and (b) monitoring its performance.
(ii) Notification of material start 28 days prior to commencement;
(iii) Affordable Housing - 10 shared ownership units (3 x one-bed, 3 x two-bed and 4 x three-bed) + £138,346 offsite contribution + financial review mechanism on an open book basis;
(iv)Community Access Plan - to secure a minimum of 18 hours per week for community use, requirement to find alternative accommodation for Busy Rascals (existing community use) during the construction period; and provision for the ancillary community space to continue to operate in the event that the A4 use is not occupied;
(v) Sustainability - submission and compliance with the Council's Sustainability check-list ensuring a minimum of 48.4% score is achieved. Compliance with Code for Sustainable Homes Code Level 3 and carbon reduction of 40% improvement on 2010 Building Regulation (with compensation should it not be delivered);
(vi) Notify Brent 2 Work of forthcoming job and training opportunities associated with the development;
(vii) Join and adhere to the Considerate Contractors scheme; (viii) Provision of a Travel Plan for the site;
(ix) Enter into a permit free arrangement to remove the rights of future residents and visitors being able to apply for a permit to park on neighbouring streets
CIL DETAILS This application is liable to pay the Community Infrastructure Levy (CIL). The total amount is £1,382,214.75 of which £1,167,110.71 is Brent CIL and £215,104.04 is Mayoral CIL.
This application is proposing to demolish the existing building which has a floorspace of 753sqm. The deductions in respect of demolition will only apply where the existing building has been in continuous lawful use for at least six months in the 12 months prior to the development being permitted. This occupancy test is not applied until the final pre-commencement condition is approved.
It should also be noted that the scheme may be eligible to relief on the levy on the parts of the chargeable development which are intended to be used as social housing. CIL Liable? Yes/No: Yes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.