Internal Audit Progress Report 2013/14

Noted Finance 2 papers

Audit Committee noted this item on Wednesday 19 March 2014. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

that the progress made in achieving the 2013/14 Internal Audit Plan and the review of fraud work be noted.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Audit Committee

Audit Committee 19 March 2014

Report from the Chief Finance Officer For Information Wards Affected: ALL

Internal Audit Progress Report 2013/14

1. Summary 1.1. This report presents a summary of the work of Internal Audit and the Investigations Team from 1st April 2013 to 28th February 2014. The appendix provides further details of audit reports issued.

2. Recommendations 2.1. That the Audit Committee notes the progress made in achieving the 2013/14 Internal Audit Plan and the review of fraud work.

3. Detail

Internal Audit - Progress 3.1. The Internal Audit Plan for 2013/141 comprises 1,248 days, including 48 days brought forward from the previous year which were not delivered. The majority, 953 days, of the plan is delivered through Mazars Public Sector Internal Audit Limited called off from a framework contract procured by Croydon Council. A small in-house team deliver a further 295 days.

3.2As at 28th February 2014 a total of 888 (71%) days have been delivered against the plan. At a similar point last year some 84% had been delivered and the

1 majority of the key financial systems audit work was already in progress during quarter 3.

3.3In the current year, as a result of the delays in the implementation of the One Oracle Financial System, the main financial systems audits (Accounts Receivable; Accounts Payable; General Ledger and Payroll) have had to be delayed and replaced with other audit work in quarter 4.The original audit plan, agreed by the Audit Committee in March 20131 has been subject to amendment. Where projects are removed or deferred, the consequent available resource is allocated to new projects. The key changes to the plan are set out below:

• Key Financial Systems – Additional 25 days added to plan for testing both pre and post migration transactions on Oracle (accounts payable, receivable, general ledger and payroll)

• Sexual Health Contracts - 10 day audit removed and to be covered as part of Public Health Grants to Voluntary Organisations.

• Placements – 25 day audit added to at the request of management

• Brent Foster Carers – 12 day audit added to plan at the request of management although . This audit has now been postponed to the 2014/15 financial year due to delays in the implementation of a new payments system.

• Kingsbury Resource Centre – 10 day audit added to plan at the request of management.

• Private Nurseries – 25 day audit added to plan as a result of two fraud enquiries.

• Highways Maintenance - Deferred by Audit and Investigation due to other projects being required

• Vale Farm Contract – Removed from plan as contract re-let in November 2013 and Ealing Council will be responsible for contract management.

• Procurement – Audit deferred due to delays in the implementation of One Oracle Category Management.

2 • Ward Working - 15 days replaced by an audit of Grants to Voluntary Organisations due to issues highlighted as a result of another audit.

• Appointeeship & Deputyship account balances verification work – 20 days added to plan due to earlier investigation work.

• Safeguarding Adults audit – 15 days removed from plan due to delays in completion of two projects.

• Tudor Gardens Residential Home audit – added to plan as replacement for safeguarding audit.

• Parking Audit – 20 days removed from plan due to restructure within Environment & Neighborhoods. Audit will now be undertaken in 2014/15.

• John Billam Centre & New Millennium Day Care Centre establishment audits – 20 days replacement for parking audit.

• Community Infrastructure Levy – 10 days added to plan so that this can be undertaken as a separate audit from the S106 audit due to the deferring regimes and requirements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4a Internal Audit Progress Report appendix 1Appendix 184 KB Download
PDF
Internal Audit Progress Report 2013/14Report 219 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 5 attended
DE
David EwartChair, present
EA
Councillor Emad Al-EbadiCommittee Member, present
MC
Councillor Mark CumminsCommittee Member, present
CH
Councillor Claudia HectorCommittee Member, present as substitute
ZV
Councillor Zaffar Van KalwalaCommittee Member, apologies, sent representative

On this subject at Brent

Search all
  1. Internal Audit Progress Report 2013/14This decision
  2. Internal Audit Interim Report 2025-26 - AddendumNoted
  3. Review of Internal Audit External Quality Assessment OutcomesNoted
  4. Internal Audit Interim Report 2022-23Noted
  5. Internal Audit 2021-22 Annual Report - Addendum ReportNoted
  6. Draft Internal Audit Strategic Plan and Counter Fraud Plan for 2022/23Approved

More from Brent Audit Committee

All decisions
MeetingDecisionOutcome
20 Mar 2017 Minutes of the previous meetingRESOLVED that the minutes of the previous meeting, held on 11 January 2017, be approved as an accurate record of the ... Approved Open
20 Mar 2017 The Role of the Audit Committee in Local Government Ombudsman (LGO) ReportsRESOLVED that the contents of the report be noted. Noted Open
20 Mar 2017 External Audit Progress ReportRESOLVED that the contents of the External Audit Progress Report be noted. Noted Open
20 Mar 2017 Annual Report on Grant Claims and Returns 2015-16RESOLVED that (i) The contents of the Annual Report on Grant Claims and Returns 2015-16 be noted; and (ii) Officers f... Noted Open
20 Mar 2017 Internal Audit & Counter Fraud Progress ReportRESOLVED that the progress made in delivering the 2016/17 Internal Audit Plan, and the associated counter fraud work,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies