Resolved
that the contract for the construction works at Manor School be awarded to Cosmur Construction Ltd.
Cabinet decided this item on Monday 15 December 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
that the contract for the construction works at Manor School be awarded to Cosmur Construction Ltd.
1.1In August 2014 Cabinet approved the allocation of additional funds to meet estimated costs of providing additional school places at Manor School in order to meet the Council’s statutory duty (£2.182m total project cost). Cabinet also approved the commencement of the procurement process for the building contract works, based on pre-tender considerations set out in the report.
1.2Tenders have been received and evaluated on the basis of the evaluation criteria as set out in the August Report. As such, this report requests authority to award a building contract, as required by Contract Standing Order No 88. This report summarises the process undertaken in tendering this contract and recommends to whom the contract should be awarded.
1.3A further report is being submitted to the 15 December Cabinet seeking authority to permanently expand Manor School. As a result, the recommendation to award a contract contained in this report is subject to Cabinet agreeing the permanent expansion of Manor School.
The Cabinet is recommended to:
Meeting: Cabinet Report Version no.4 Date: 15 December 2014 Date 24 November 2014 2.1 Award the works contract for the construction works at Manor School to Cosmur Construction Ltd at a price of £953,572, subject to Cabinet approval of the permanent expansion of Manor School.
3.0Detail
3.1Brent Council has a statutory duty to ensure sufficient school places are provided. There is a shortfall of Special Educational Needs (SEN) school places to meet current and projected demand. The Council has been awarded Targeted Basic Need (TBN) grant funding of £1.541m by the Education Funding Agency (EFA) in order to provide an additional 44 SEN Places at Manor School. In order to comply with the conditions of that grant funding and therefore retain it, all 44 additional places must be available and all of the TBN funding allocated to the project must be fully spent by 31 August 2015. At the August 2014 meeting, Cabinet noted that the total estimated cost of works (£2.182m) required to provide these additional places exceeded the TBN funding available and approved the allocation of additional funds (£641k) from the Council’s Basic Needs Capital Grant allocation to assist in delivery of the additional school places. There is sufficient funding to deliver this project.
3.2This report seeks the award of contract for the proposed building works which will enable Manor School, a special school catering for children aged between 4 and 11, to increase its capacity from 132 school places to 176 pupil numbers. Key stakeholders, in particular Manor School Governing Body, the school Head and other staff members have had input in the proposed scheme design and have fully co-operated in accommodating pre-main contract works (enabling works), which commenced in summer 2014 and completed in November 2014, whilst operating day-to-day school management.
3.3The proposed main building contract works achieved Planning Consent on 17 September 2014 and include part new-build and part alterations/re-modelling works as well as considerable and much required improvements to the external play areas. The proposed design refurbishment, alterations and new- build proposals will support the education delivery, facilities and amenities for pupils and so enhance pupils’ educational and life-skills experience once works are completed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Recommendation for Award of a High Value Construction Contract at Manor SchoolReport | 113 KB | DownloadRead as text |
PDF |
rg-manor-construction-appb-(2)Report | 32 KB | Download |
PDF |
rg-manor-construction-eia-appcReport | 328 KB | Download |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.