(i) that it be noted that the draft Stopping Up Order had been advertised in accordance with the requirements of Section 247 TCPA 1990 and that in response to the consultation, 5 consultees had informed the Council that they had apparatus in the area. Of these responses, the National Grid objected to the draft Stopping Up Order and Thames Water reserved the right to object if assurances were not given regarding its apparatus; (ii) that the objections raised to the proposed Stopping Up Order detailed in the report be noted; (iii) that the Stopping Up Order be agreed and advertised subject to the resolution of the objections detailed in the report from the Strategic Director of Environment and neighbourhoods.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report seeks authorisation to make a Stopping Up Order for an area of public highway consisting of footpaths, roads, a podium area and ancillary land at Durham Court, Kilburn Park Road and Gloucester House, Cambridge Road, London NW6 under Section 247 of the Town and Country Planning Act 1990 (TCPA 1990).
1.2This Order is required to complete the development of the Durham Court and Gloucester House site which will provide for 4-8 storey blocks comprising 236 flats (134 private and 102 affordable (social rent)), an energy centre for the South Kilburn Neighbourhood Decentralised Heating System, basement car- park, associated landscaping and general amenity space, and the provision of a replacement public space and play area.
Recommendations
2.1That members note that the draft Stopping Up Order has been advertised in accordance with the requirements of Section 247 TCPA 1990 and that in response to the consultation, 5 consultees have informed the Council that they had apparatus in the area. Of these responses, the Nationalgrid objected to the draft Stopping Up Order and Thames Water reserve the right to object if assurances are not given regarding its apparatus.
2.2That the Committee note the objections in this report, and approve the Stopping Up Order and agree that it should be advertised following the resolution of these objections.
3.0Detail
General Purposes Committee – Version 4.0 6 January 2015 22 December 2014 3.1 Planning consent was granted following the Planning Committee meeting of 23rd September 2014 for demolition of 209 existing dwellings and garages at Gloucester House and Durham Court and erection of 4-8 storey blocks comprising of 236 flats (134 private and 102 affordable (social rent)), an energy centre for the South Kilburn Neighbourhood Decentralised Heating System, basement car-park, associated landscaping and general amenity space, provision of replacement public play space and stopping up of existing public footpath between Cambridge Road and Kilburn Park Road.
3.2This development is part of the Council’s South Kilburn Regeneration development programme.
3.3There will be no other significant changes to the design or traffic and parking management arrangements on the area of highway to be stopped up.
3.4A draft Stopping Up Order was made under Section 247 TCPA 1990 to enable the redevelopment to take place. A copy of the Order is attached at Appendix 1, together with the relevant plan showing the proposed area to be stopped up and the notice advertised on 14th November 2014 in the local press and the London Gazette. Statutory consultees, namely utility companies with apparatus at the site and the Greater London Authority were notified of the proposed Stopping-Up Order by e-mail and correspondence.
3.5The Council advertised the Stopping Up Order and received five responses from utility companies with apparatus in the vicinity. These were from: • OpenreachBT dated 24th November 2014 • Nationalgrid dated 14th November 2014 • Thames Water dated 13 November 2014 • Virgin Media dated 20th November 2014 • London Underground dated 13th November 2014
3.6The response from Nationalgrid was an objection as it has apparatus in the vicinity. Nationalgrid require a more detailed assessment, following which they may decide to retract their objection, or require a grant of easement over the affected main or the diversion of that main prior to retracting their objection. Council officers will pursue a more detailed assessment and negotiate with Nationalgrid to have this objection withdrawn.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingIt was RESOLVED that the minutes of the previous meeting held on Monday 13 October 2025 be approved as a correct record.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.