i ) That it be agreed that an outdoor gym be installed at Barham Park; ii) That officers review the timeline for the installation of the Gym as determined by the funding arrangements and if possible, undertake community consultation regarding the preferred location of the outdoor Gym in relation to locations A, B and D detailed in the report from the Director of Environment and Neighbourhoods; iii) that if it is not possible to undertake community consultation regarding the location of the outdoor Gym whilst complying with the required timeframe for installation, or if the outcome of the consultation was inconclusive, location B as detailed in the report from the Director of Environment and Neighbourhoods be agreed as the preferred location of the outdoor gym. i ) That it be agreed that an outdoor gym be installed at Barham Park; ii) That officers review the timeline for the installation of the Gym as determined by the funding arrangements and if possible, undertake community consultation regarding the preferred location of the outdoor Gym in relation to locations A, B and D detailed in the report from the Director of Environment and Neighbourhoods; ... view the full minutes text for item 6.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1To consider whether the Trust wants an outdoor gym to be provided at Barham Park and if so to agree the location for the outdoor gym. The funding is available from S106 monies and by a grant from Wembley National Stadium Trust and is therefore at no cost to the Trust.
Recommendations
2.1That Members agree that an outdoor gym be installed at Barham Park.
2.2Select a preferred location for the outdoor gym from the options proposed in paragraphs 3.12 and shown on the attached plan.
3.0Detail 3.1 In the summer of 2014, the Council bid on behalf of the Trust for external funding to create an outdoor gym in Barham Park. The application was successful and Wembley National Stadium Trust (WNST) Fund will provide £20,000 (approx. 50%) of the total costs for the supply and installation of the gym with the remaining money allocated from S106 funding. Funding the outdoor gym is therefore available at no cost to the Trust, however there will be ongoing inspection and maintenance costs associated with the provision of the gym.
3.2Officers have put together a number of potential locations for the outdoor gym in Barham Park.
3.3The outdoor gym would consist of a macadam base with a number of outdoor gym equipment stations spread across the macadam surface. Although the size will not be confirmed until bids are received, the approximate size of the outdoor gym would be 100m2 with approximately eight pieces of equipment that would provide 12 stations or exercises.
3.4Below is a list of the proposed locations within the Park along with each locations advantages and disadvantages. A site plan is attached as Appendix A with the letters associated with the table below shown on the plan.
Meeting: Barham Trust Committee Version no.2 Date: 28 January 2015 Date: 14/1/15 -1- 1 3.5 A planning application would be submitted for the provision of the gym on the agreed preferred location.
Location Advantages Disadvantages Reference Away from houses Funfair would be located very close to Provide opportunities for parents to the gym and may not be usable when exercise whilst child is in playground the funfair is on site. Close to children’s play area and may get heavily used by children who are A not the target users of this equipment. Potential to create ‘hang-out’ area in park. May get complaints that it is located too close to the playground
Close to existing footpaths Potential to create ‘hang-out’ area in Central location so easily accessible park. from the east and west park B entrances. Away from houses Visible from Harrow Road
Close to existing footpath Potential to create ‘hang-out’ area in Close to entrance near park. Easily accessible from east entrance Less accessible than option B C of park Closer to Old Peoples Home off Visible from Harrow Road Copeland Avenue
Away from houses Potential to create ‘hang-out’ area in Centrally located park Very close to historic core of park D Somewhat ‘tucked away’. Poor visibility from the road Close to the parks Building.
3.6Officers preferred locations is location reference B
Financial implications
4.1The installation costs will be funded by external funding and s106 contributions. The ongoing inspection and maintenance costs will form part of the overall running costs of the park met by the Council’s Sports and Parks service
Legal implications
5.1The terms and conditions of the grant from the Wembley National Stadium Trust (WNST) Fund are similar to grant terms applicable to other funds for recreational and sporting facilities and equipment .
5.2The use of the land as a gym is consistent with the recreational purposes of the Trust and the Section 5 of the Charities Act 2011.
Meeting: Barham Trust Committee Version no.2 Date: 28 January 2015 Date: 14/1/15 -2- 1 Meeting: Barham Trust Committee Version no.2 Date: 28 January 2015 Date: 14/1/15 -3- 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.