( i ) that approval be given to the proposed 2015-16 programme of Development Funded projects and the relevant Heads of Service authorised to deliver this programme using the allocated budget and resources available; (ii) that the 2015-16 allocation of £10.43m of S106 funding in the following split: £4.8m for Education; £0.6m for Transportation, £0.5m for Parks and Sports; £0.1m for Landscaping; £0.2m for Employment & Enterprise; £1.5m for Affordable Housing; £2.3m for Environment & Sustainability; £0.05m for Healthcare; and £0.4m for specific projects in Growth Areas, be noted; (iii) that any necessary statutory or non-statutory consultation and the consideration of any objections or representations be undertaken by the relevant Heads of Service responsible for delivering the projects; (iv) that the Director of Planning and Regeneration be authorised to approve and relevant Heads of Service to deliver projects in 2015-16 over and above the allocations and projects detailed herein where the exceptional circumstances criteria as set out in section 3.7, in the report from Strategic Director, Regeneration and Growth, are met.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report seeks the approval of Cabinet for the proposed spatial and thematic allocation of Section 106 funds for expenditure in 2015-16 and commissioning specific projects and budget amounts detailed herein.
1.2The allocation and projects have been reported to CMT in November and PCG in December and this report reflects feedback from those two meetings.
1.3This report has been prepared with the involvement of the Operational Directors of Planning & Regeneration, Housing and Employment, Property & Projects, Environment & Neighbourhoods, Environment & Protection and other relevant officers responsible for regeneration and inward investment across the borough.
Recommendations
2.1That Cabinet approves the proposed 2015-16 programme of Development Funded projects and authorises the relevant Heads of Service to deliver this programme using the allocated budget and resources available.
2.2That Cabinet notes the 2015-16 allocation of £10.43m of S106 funding in the following split: £4.8m for Education; £0.6m for Transportation, £0.5m for Parks and Sports; £0.1m for Landscaping; £0.2m for Employment & Enterprise; £1.5m for Affordable Housing; £2.3m for Environment & Sustainability; £0.05m for Healthcare; and £0.4m for specific projects in Growth Areas.
1 2.3 That Cabinet notes that any necessary statutory or non-statutory consultation and the consideration of any objections or representations shall be undertaken by the relevant Heads of Service responsible for delivering the projects.
2.4That Cabinet authorises the Director of Planning & Regeneration to approve and relevant Heads of Service to deliver projects in 2015-16 over and above the allocations and projects detailed herein where the exceptional circumstances criteria as set out in section 3.7, below, are met.
Background
3.1Section 106 agreements are legal agreements between local authorities and developers, which are linked to a planning permission. Planning obligations are secured within S106 agreements when it is considered that a development will have negative impacts that cannot be addressed by conditions to the planning permission. Where the Developer cannot directly mitigate the impact the Council can instead take a financial contribution to undertake works. Section 106 obligations should only be used where a planning condition would not be effective or relevant. Regulation 122 of the Community Infrastructure Levy 2010 (as amended) sets out three tests to be satisfied where a planning obligation must be: (a) necessary to make the development acceptable in planning terms; (b) directly related to the development; and (c) fairly and reasonably related in scale and kind to the development. Accordingly, these tests are now law and must be met to comply.
3.2This report is concerned with the allocation of those funds which have been paid by developers held by the Council (hereafter “development funds”).
3.3Development funds secured via S106 agreements can only fund those projects which meet the terms of the agreements from which the funding is derived and can be returned to the developer if the monies are not spent within the period specified in the terms and conditions of the Agreement.
3.4Objectives for the selection and shortlisting of projects are split into “Essential” criteria and “Desirable” criteria:
Essential criteria • meets the terms of the legal agreement; • mitigates the impact of the development from which funding is derived; and • has Member support
Desirable criteria • meets the objectives of the Borough Plan and the Regeneration Plan and helps to facilitate growth; • meets Service Area objectives; • is capable of attracting additional funding streams; and • has local community support
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.