RECOMMENDATION: (a) to grant planning permission, subject to an appropriate form of Agreement in order to secure the measures set out in the Section 106 Details section of the report, subject to conditions listed after paragraph 93, or (b) If within a reasonable period the applicant fails to enter into an appropriate agreement in order to meet the policies of the Unitary Development Plan, Core Strategy and Section 106 Planning Obligations Supplementary Planning Document, to delegate authority to the Head of Planning, or other duly authorised person, to refuse planning permission, subject to the conditions set out in the Draft Decision Notice. DECISION: (a) Planning permission granted subject to an appropriate form of Agreement in order to secure the measures set out in the Section 106 Details section of the report and conditions as set out in the Draft Decision Notice; (b) If within a reasonable period the applicant fails to enter into an appropriate agreement in order to meet the policies of the Unitary Development Plan, Core Strategy and Section 106 Planning Obligations Supplementary Planning Document, to delegate authority to the Head of Planning, or other duly authorised person, to refuse planning permission.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
COMMITTEE REPORT Planning Committee on 2 July, 2015 Item No 03 Case Number 15/1456
SITE INFORMATION RECEIVED: 10 April, 2015
WARD: Wembley Central
PLANNING AREA: Wembley Consultative Forum
LOCATION: Alperton Community School, Ealing Road, Wembley, HA0 4PW
PROPOSAL: Demolish all buildings on site (except the John Boyle Centre, Children Centre and Site managers accommodation) and erection a four storey 9 form entry secondary school for 1700 pupils (1350 11-16 years old and 350 post 16), together with associated car parking, servicing and circulation space, multi-use games areas and other hard and soft landscaping.
APPLICANT: Kier Construction
CONTACT: Nicholas Hare Architects LLP
PLAN NO'S: Refer to Condition 2 __________________________________________________________ SITE MAP Planning Committee Map Site address: Alperton Community School, Ealing Road, Wembley, HA0 4PW
This map is indicative only. SELECTED SITE PLANS SELECTED SITE PLANS Proposed Site Plan Proposed Ground Floor Plan Proposed Elevations Proposed Elevations Visual - Aerial South East RECOMMENDATIONS To:
(a) Resolve to Grant Planning Permission, subject to an appropriate form of Agreement in order to secure the measures set out in the Section 106 Details section of this report, subject to conditions listed after paragraph 93, or (b) If within a reasonable period the applicant fails to enter into an appropriate agreement in order to meet the policies of the Unitary Development Plan, Core Strategy and Section 106 Planning Obligations Supplementary Planning Document, to delegate authority to the Head of Planning, or other duly authorised person, to refuse planning permission , subject to the conditions set out in the Draft Decision Notice. A) PROPOSAL Demolish all buildings on site (except the John Boyle Centre, Children Centre and Site managers accommodation) and erection a four storey 9 form entry secondary school for 1700 pupils (1350 11-16 years old and 350 post 16), together with associated car parking, servicing and circulation space, multi-use games areas and other hard and soft landscaping.
The construction work will take place in two phases. Phase 1 will commence in October 2015, and will involve the demolition of the existing buildings within the southern end of the site. Phase 1 is proposed to be complete for December 2016, with the lower school moving into the phase 1 area. The remaining buildings will be demolished as part of phase 2, commencing from the existing boilerhouse, working south and then the buildings to the north of the site. Phase 2 is programmed to be completed in December 2017. On the completion of phase 2, the final decant of the upper school will be undertaken.
Further details on the project programme and timescales are set out within paragraphs 47 to 51 below.
B) EXISTING The application site comprises Alperton Community School. It is a secondary school that currently offers 1,645 places for pupils aged 11 to 19, along with standard mild learning difficulties/special educational needs (MLDS/SEN) provision. The school is currently located on two sites with the lower school on Ealing Road and the upper school on Stanley Avenue. There is also an additional off site playing field located at Mount Pleasant. This application seeks to relocate all of the school onto the Ealing Road site.
The lower school site on Ealing Road also contains John Boyle Centre, which is a separate facility that accommodates 40 MLDS/SEN pupils, and a Children's Centre. These are outside the remit of this planning application and will continue to operate during the construction works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.