Resolved
that the progress made in achieving the 2015/16 Internal Audit Plan and the review of fraud work be noted.
Audit Committee noted this item on Tuesday 5 January 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
that the progress made in achieving the 2015/16 Internal Audit Plan and the review of fraud work be noted.
1.1This report provides an update on the progress against the internal audit plan for the period 1 August 2015 to 31 October 2015. The appendix to the report also summarises those assurance reports from the 2014/15 plan which have been finalised since the last meeting of the Audit Committee. The report also provides a summary of counter fraud work for the first two quarters of 2015/16 including October 2015.
2.1That the Audit Committee notes the progress made in achieving the 2015/16 Internal Audit Plan and the review of fraud work.
3. Detail
3.1The Internal Audit Plan for 2015/16 comprises 996 days. 590 days will be delivered by Mazars. The in-house resource will deliver a further 406 days.
3.2The key points to note with regards to progress for the current year are: • There are 79 internal audit assignments included within the agreed 2015/16 plan (excluding follow up and advisory work). Work has commenced on 39 of these. • Twenty two assignments have been completed to draft or final stage since the last report to the Audit Committee September 2015 (twenty seven for the year to date). Of the twenty two assignments, eighteen had an assurance opinion associated with them and four were in respect of non-assurance work including a grant and trust account certification.
1 Please see summary below: Table 1 – Summary of Audits Completed Since last audit report
Total Number of Substantial Limited None Non Assurance Audits Completed 22 13 5 0 4
3.3The Head of Audit & Investigations alerted members to the slow progress being made against the plan at the Audit Committee meeting in September 2015. This has largely been due to the significant work required to finalise the outstanding 14/15 audits, during the first quarter. A number of audits scheduled to be carried out in the first and second quarters were either also removed from the plan or as a result of request by management that they should be deferred. This was partly caused due to structural changes within some departments, or system changes because the proposed assignments were similar to audits recently undertaken. Where assignments were removed or deferred, the consequent available resources were re-allocated. The key changes to the plan are set out below:
Table 2 – Planned Assignments Withdrawn from original plan Audit
Home Care Contract – ASC 10 Area had been subject to a recent review as a result of changes in Department delivery mechanism. Public Realm Contract – COO 10 Area had been subject to a recent similar review. Department Total 20
Table 3 – Assignments Added to original plan Audit DFG Grant Determination 2 Grant required to be signed off by Certification Head of Audit & Investigations. Health and Safety – transferred 15 Review to be undertaken by Specialist from Mazars. from COO Contingency Budget Pre audit verification – Information 5 Audit work to prepare for visit from Governance Information Commissioner’s Office Total 22
Table 4 – Assignments Delayed Audit
START (Previously BACES) (R&G 15 Request from Operational Director for Department) audit to be delayed until December 2015 as a result of restructure of service and appointment of new Head of Service. Strategic Director notified. Transport Services 15 Request from Operational Director for
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit & Counter Fraud Progress Report for the period 1 August 2015: 31 October 2015Report | 165 KB | DownloadRead as text |
PDF |
Internal Audit Progress Report appendix 1: Audit Committee v2: January 2016Appendix | 226 KB | Download |
Follow Audit Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Mar 2017 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting, held on 11 January 2017, be approved as an accurate record of the ... | Approved | Open |
| 20 Mar 2017 | The Role of the Audit Committee in Local Government Ombudsman (LGO) ReportsRESOLVED that the contents of the report be noted. | Noted | Open |
| 20 Mar 2017 | External Audit Progress ReportRESOLVED that the contents of the External Audit Progress Report be noted. | Noted | Open |
| 20 Mar 2017 | Annual Report on Grant Claims and Returns 2015-16RESOLVED that (i) The contents of the Annual Report on Grant Claims and Returns 2015-16 be noted; and (ii) Officers f... | Noted | Open |
| 20 Mar 2017 | Internal Audit & Counter Fraud Progress ReportRESOLVED that the progress made in delivering the 2016/17 Internal Audit Plan, and the associated counter fraud work,... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.