Granted planning permission as recommended with changes to the S106 in relation to highway works as set out in the Supplementary report in addition to further amendments to require the developer to undertake to resurface the footpath and the highway adjoining the development or affected by damage due to the development and, to record the condition and the highway prior to commencing construction work and to amendments to conditions 1 (to require a revised building layout adjoining Willow Court) and 7 (to delete the requirement for a complete resubmission on any amendment) , and amended or additional conditions to cover the control of noise and future maintenance of the vehicle lift and the retention where possible of existing boundary walls and to the addition of an informative relating to the Party Wall Act.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
Agenda Item 08 Supplementary Information Planning Committee on 13 January, Case No. 15/3616 2016
Location Former Manor School, 3-7 The Avenue, London, NW6 7YG Description Hybrid planning application for full permission for demolition of all buildings and the development of 74 residential units (Use Class C3) comprising of 33 x 1 beds, 23 x 2 beds and 18 x 3 beds in a part three / part four / part five storey building fronting The Avenue with related basement car park comprising 57 parking spaces; and a 3 storey plus basement building fronting Christchurch Avenue, new vehicular access; footways; landscaping and associated works ("Phase 1"); and Outline permission for a school (Use Class D1), with new vehicular and pedestrian access from Brondesbury Park, with details of "appearance", "scale", “layout” and “landscaping” being reserved ("Phase 2").
Agenda Page Number: 117
Members visited the site on Saturday 09 January and viewed the site from within. A local resident was in attendance.
A number of issues were raised:
1. Tree alongside No. 9 The Avenue The local resident requested further information as to whether this tree would be retained. The proposal, which has been reviewed by the borough tree officer, is to remove this tree as the works to construct No. 9 The Avenue (under planning permission 10/2789) have damaged it. The replacement of this and other trees to be removed from the site will be addressed in the proposed condition requiring the further details of hard and soft landscaping to be submitted, approved and implemented.
2. Cycle ways along the site boundaries The local resident noted that cycle ways are proposed along The Avenue and Christchurch Avenue and asked whether these could be incorporated into the site's highway works. The cycle ways are proposed as part of the wider cycle strategy for Brent however this is in the medium to long term in this location with other, higher priority cycle ways to be brought forward in the short term. As such there is no detail as to what form these cycle ways could take and it is unlikely that the highway works will be on-going by the time these cycle ways come forward. Should Members desire it, the Highway Works to be secured under a planning obligation via a S106 legal agreement could be amended to include a provision requiring the Developer to use best endeavours to accommodate the potential cycle ways works into the highway along the Christchurch Avenue and The Avenue frontages in the event that further details of the cycle ways are available prior to commencement of the works.
3. Impact of construction traffic on the road surface Members requested a provision to be included to ensure the road surface of Christchurch Avenue and The Avenue would be resurfaced in the event of damage being caused by the construction process. Transportation officers have confirmed that it is usual to require to the Developer to pay for repairs to the road and footway and in this case the Highway Works to be secured under a planning obligation via a S106 legal agreement could be amended to include explicit provision of a deposit for the repair of the road surface along the site frontages and nearby approaches, in addition to the deposit normally paid when Developer's contractors carry out works to the public highway.
4. Planning Committee Map The Planning Committee Map on page 118 is in error, with the red line omitting No. 3 The Avenue. This has not resulted in any procedural error in respect of consultation and the application has been assessed in terms of its impact on the correct neighbour 1-6 Avenue House, however this has been erroneously referred to as 3 The Avenue (or 3TA) in the report (paras 43 and 47), and reference to that should be read as 1-6 Avenue House. A revised map is shown below: Supplementary Report - printed 12 January, 2016 Page 2 of 7
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.