Resolved
RESOLVED that the progress made in delivering the 2016/17 Internal Audit Plan and the associated counter fraud work, be noted.
Audit Committee noted this item on Thursday 22 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the progress made in delivering the 2016/17 Internal Audit Plan and the associated counter fraud work, be noted.
1.1This report provides and update on the progress against the internal audit plan for the period 1 April 2016 to 31 August 2016. The appendix to the report also summarises those reports from the 2015/16 plan which have been finalised since the last meeting of the committee. The report also provides a summary of counter fraud work for the first quarter of 2016/17.
2.1That the Audit Committee notes the progress made in delivering the 2016/17 Internal Audit Plan and the associated counter fraud work.
3. Detail
3.1The Internal Audit Plan for 2016/17 comprises 1,110 days. 590 days will be delivered by PWC. The in-house resource will deliver a further 520 days.
3.2Much of the work of the first quarter of the year focused on the completion of the 2015/16 plan. A summary of reports finalised during the first quarter relating to last year’s plan are summarised in appendix 1.
3.3Following a competitive tender process, PricewaterhouseCoopers (PwC) were appointed as the new Strategic Audit Partner for the Shared Service, for 2016- 2020. The contract was not finally signed until the 16th of June 2016 but practical arrangements were made to mobilise work activity to avoid delays. These included the following mobilisation activities to ensure an effective transition from the previous internal audit service providers, Mazars:
• Established an agreed working protocol with the Head of Internal Audit and Investigation; • Agreed revised terms of references and interactive reporting templates with the Head of Internal Audit and Investigation;
1 • Held meetings with the Head of Internal Audit and Investigation and other key stakeholders to agree audit approaches, form a project plan to support the delivery of the audit plan and establish contract management arrangements; and • Arranged Audit Committee training for all three boroughs.
3.4The key points to note with regards to progress for the current year are: • Two reports from the 2015/16 audit plan have been finalised since the last meeting of the Committee. Both reports had substantial assurance opinions and details are included in the Appendix 1 of this report. • There are 56 internal audit projects included within the agreed 2016/17 plan (excluding follow up and advisory work). Work has commenced on fifteen of these. • Three audits projects have been delayed at the request of management. Details of the audits which have been delayed are set out in Table 2. • Seven audit projects have been completed to draft or final stage. Three of them have an audit opinion associated with them. One has a substantial opinion and two limited opinions. The remaining four relate to grant and account certifications as well as consultancy work which do not have an assurance rating attached.
Table 1– Projects Added to original plan
Audit Reason Planning Applications At the request of management IT Risk Diagnosis Shared Service Project undertaken by contractor Assurance Mapping Shared Service Project undertaken by contractor Kilburn Square TMO At the request of BHP Management (BHP) Essential User Permits At the request of management Rogue Landlords Grant Grant Certification work Certification Data Protection (BHP) At the Request of BHP Management
Table 2 – Projects to be Delayed
Audit Reason
Procurement – Non Postponed until Q4 at the request of major works (BHP) management due to ongoing structural changes within the team BHP Owned Properties Postponed until the early part of Q3 at the request of management due to staff being unavailable to assist with the audit IT Application Audits Postponed to Q4 at the request of management and work being carried out on IT Risks by the PWC
2 A summary of progress is set out in table 3 below:
Table 3 – Delivery Status as at 31 August 2016
Delivery Status Total number of reports to be delivered in current plan 56
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit and Counter Fraud Progress Report for the period 1 April: August 2016Report | 129 KB | DownloadRead as text |
PDF |
internal_audit_progress_reportReport | 409 KB | Download |
Follow Audit Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Mar 2017 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting, held on 11 January 2017, be approved as an accurate record of the ... | Approved | Open |
| 20 Mar 2017 | The Role of the Audit Committee in Local Government Ombudsman (LGO) ReportsRESOLVED that the contents of the report be noted. | Noted | Open |
| 20 Mar 2017 | External Audit Progress ReportRESOLVED that the contents of the External Audit Progress Report be noted. | Noted | Open |
| 20 Mar 2017 | Annual Report on Grant Claims and Returns 2015-16RESOLVED that (i) The contents of the Annual Report on Grant Claims and Returns 2015-16 be noted; and (ii) Officers f... | Noted | Open |
| 20 Mar 2017 | Internal Audit & Counter Fraud Progress ReportRESOLVED that the progress made in delivering the 2016/17 Internal Audit Plan, and the associated counter fraud work,... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.