Internal Audit and Counter Fraud Progress Report for the period 1 April – August 2016

Noted Finance 2 papers

Audit Committee noted this item on Thursday 22 September 2016. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED that the progress made in delivering the 2016/17 Internal Audit Plan and the associated counter fraud work, be noted.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Audit Committee

Summary

1.1This report provides and update on the progress against the internal audit plan for the period 1 April 2016 to 31 August 2016. The appendix to the report also summarises those reports from the 2015/16 plan which have been finalised since the last meeting of the committee. The report also provides a summary of counter fraud work for the first quarter of 2016/17.

Recommendations

2.1That the Audit Committee notes the progress made in delivering the 2016/17 Internal Audit Plan and the associated counter fraud work.

3. Detail

3.1The Internal Audit Plan for 2016/17 comprises 1,110 days. 590 days will be delivered by PWC. The in-house resource will deliver a further 520 days.

3.2Much of the work of the first quarter of the year focused on the completion of the 2015/16 plan. A summary of reports finalised during the first quarter relating to last year’s plan are summarised in appendix 1.

3.3Following a competitive tender process, PricewaterhouseCoopers (PwC) were appointed as the new Strategic Audit Partner for the Shared Service, for 2016- 2020. The contract was not finally signed until the 16th of June 2016 but practical arrangements were made to mobilise work activity to avoid delays. These included the following mobilisation activities to ensure an effective transition from the previous internal audit service providers, Mazars:

• Established an agreed working protocol with the Head of Internal Audit and Investigation; • Agreed revised terms of references and interactive reporting templates with the Head of Internal Audit and Investigation;

1 • Held meetings with the Head of Internal Audit and Investigation and other key stakeholders to agree audit approaches, form a project plan to support the delivery of the audit plan and establish contract management arrangements; and • Arranged Audit Committee training for all three boroughs.

3.4The key points to note with regards to progress for the current year are: • Two reports from the 2015/16 audit plan have been finalised since the last meeting of the Committee. Both reports had substantial assurance opinions and details are included in the Appendix 1 of this report. • There are 56 internal audit projects included within the agreed 2016/17 plan (excluding follow up and advisory work). Work has commenced on fifteen of these. • Three audits projects have been delayed at the request of management. Details of the audits which have been delayed are set out in Table 2. • Seven audit projects have been completed to draft or final stage. Three of them have an audit opinion associated with them. One has a substantial opinion and two limited opinions. The remaining four relate to grant and account certifications as well as consultancy work which do not have an assurance rating attached.

Table 1– Projects Added to original plan

Audit Reason Planning Applications At the request of management IT Risk Diagnosis Shared Service Project undertaken by contractor Assurance Mapping Shared Service Project undertaken by contractor Kilburn Square TMO At the request of BHP Management (BHP) Essential User Permits At the request of management Rogue Landlords Grant Grant Certification work Certification Data Protection (BHP) At the Request of BHP Management

Table 2 – Projects to be Delayed

Audit Reason

Procurement – Non Postponed until Q4 at the request of major works (BHP) management due to ongoing structural changes within the team BHP Owned Properties Postponed until the early part of Q3 at the request of management due to staff being unavailable to assist with the audit IT Application Audits Postponed to Q4 at the request of management and work being carried out on IT Risks by the PWC

2 A summary of progress is set out in table 3 below:

Table 3 – Delivery Status as at 31 August 2016

Delivery Status Total number of reports to be delivered in current plan 56

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit and Counter Fraud Progress Report for the period 1 April: August 2016Report 129 KB DownloadRead as text
PDF
internal_audit_progress_reportReport 409 KB Download

At this meeting

Whole meeting

Who was there

6 of 9 attended
DE
David EwartChair, present
MA
Councillor M Aslam ChoudryVice-Chair, apologies
JD
Councillor Joel DavidsonCommittee Member, present
SK
Councillor Sabina KhanCommittee Member, present
KN
Councillor Kana NaheerathanCommittee Member, apologies
NN
Councillor Neil NervaCommittee Member, present
JL
Councillor Janice LongAlternate, present as substitute
AH
Councillor Aisha Hoda-BennAlternate, present as substitute
SC
Councillor Shafique ChoudharyCouncillor, in attendance

On this subject at Brent

Search all
  1. Internal Audit and Counter Fraud Progress Report for the period 1 April – August 2016This decision
  2. Internal Audit Interim Report 2025-26 - AddendumNoted
  3. Review of Internal Audit External Quality Assessment OutcomesNoted
  4. Internal Audit Interim Report 2022-23Noted
  5. Internal Audit 2021-22 Annual Report - Addendum ReportNoted
  6. Draft Internal Audit Strategic Plan and Counter Fraud Plan for 2022/23Approved

More from Brent Audit Committee

All decisions
MeetingDecisionOutcome
20 Mar 2017 Minutes of the previous meetingRESOLVED that the minutes of the previous meeting, held on 11 January 2017, be approved as an accurate record of the ... Approved Open
20 Mar 2017 The Role of the Audit Committee in Local Government Ombudsman (LGO) ReportsRESOLVED that the contents of the report be noted. Noted Open
20 Mar 2017 External Audit Progress ReportRESOLVED that the contents of the External Audit Progress Report be noted. Noted Open
20 Mar 2017 Annual Report on Grant Claims and Returns 2015-16RESOLVED that (i) The contents of the Annual Report on Grant Claims and Returns 2015-16 be noted; and (ii) Officers f... Noted Open
20 Mar 2017 Internal Audit & Counter Fraud Progress ReportRESOLVED that the progress made in delivering the 2016/17 Internal Audit Plan, and the associated counter fraud work,... Noted Open