CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Brent
Cabinet, Monday 13 March 2017 at 7.00pm

Phase 1 Building Project at the Granville Centre - Approval to Tender Works Contract

Approved Executive 1 paper

Cabinet approved this item on Monday 13 March 2017. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

9.1 Cabinet approved inviting tenders for a works contract in respect of Phase 1 building project at Granville Centre on the basis of pre-tender considerations set out in paragraph 3.10 of the Phase 1 Building Project at the Granville Centre – Approval to Tender Works Contract Report. 9.2 Cabinet approved the evaluation of tenders on the basis of the evaluation criteria set out in paragraph 3.10 of the Report. 9.3 Cabinet delegated the authority to award the high value works contract referred to in Resolution 9.1 to the Strategic Director of Regeneration and Environment in consultation with the Lead Member for Regeneration, Employment and Skills. 9.4 Cabinet noted that the decision was subject to the Greater London Authority grant agreement and other legal documents being entered into by the parties. 9.1 Cabinet approved inviting tenders for a works contract in respect of Phase 1 building project at Granville Centre on the basis of pre-tender considerations set out in paragraph 3.10 of the Phase 1 Building Project at the Granville Centre – Approval to Tender Works Contract Report. 9.2 Cabinet approved the evaluation of tenders on the basis of the evaluation criteria set out in paragraph 3.10 of the Report. 9.3 Cabinet delegated the authority to award the high value works contract referred to in Resolution 9.1 to the Strategic Director of Regeneration and Environment in consultation with the Lead Member for Regeneration, Employment and Skills. 9.4 Cabinet noted that the decision was subject to the Greater London Authority grant agreement and other legal documents being entered into by the parties.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Summary

1.1The Granville Centre, will accommodate the Enterprise & Community Hub in the immediate term. This phase of works is referred to as phase 1 and includes refurbishing the Granville Centre by March 2018.

1.2This report seeks Cabinet approval to invite tender for a works contract as required by contract Standing Orders 88 and 89 to complete phase 1 of this project for refurbishment of the Granville Centre to accommodate the Enterprise & Community Hub. The project is being managed by Brent officers and will abide by the LA's financial regulations and standing orders in purchasing, tendering and contracting matters.

1.3This report also seeks a delegation of Cabinet’s authority to award high value works contracts to the Strategic Director of Regeneration and Environment in consultation with Lead Member Regeneration, Growth, Employment and Skills and also with the Chief Finance Officer and Chief Legal Officer in order for the delivery programme to be maintained and meet the GLA timescales necessary for receipt of funding.

Recommendations

The Cabinet is recommended to:

2.1Approve inviting tenders for a works contract in respect of Phase 1 building project at Granville Centre on the basis of the pre-tender considerations set out in paragraph 3.10.

2.2In respect of Recommendation 2.1 above, approve the evaluation of tenders on the basis of the evaluation criteria set out in paragraph 3.10 of this report. 2.3 Delegate authority to award the high value works contract referred to in Recommendation 2.1 to the Strategic Director of Regeneration and Environment in consultation with the Lead Member Regeneration, Growth, Employment and Skills.

2.4This decision is subject to the GLA grant agreement and other legal documents being entered into by the parties.

3.0Detail

3.1Since the 25 July 2016 there has been ongoing dialogue with the Greater London Authority (GLA) in respect of the funding for the Enterprise & Community Hub, who initially were to provide £1.8m towards an Enterprise & Community Hub, however, this came with a tight timescale of delivery of March 2018.

3.2Officers reviewed the timescale to determine what could be delivered within the GLA’s March 2018 timescale. It was evident that a new build could not be achieved, and as a result officers, working with the South Kilburn Trust (whom, it is proposed will manage and operate the Enterprise & Community Hub subject to terms being agreed by Brent’s Property Services), looked at delivering a Phase 1 option of refurbishing the Granville Centre in the immediate term to provide for a location for the Enterprise & Community Hub which would meet the GLA timetable. A Phase 2 option looks at the wider redevelopment of the Carlton and Granville Centres being developed in due course.

3.3The GLA is supportive of proposals detailed in paragraph 3.2 and has approved funding for the Council of £749,058 for the Enterprise & Community Hub project Phase 1. This figure is greater than the initial proposal which was for £350k for Phase 1.

3.4The delivery of Phase 1 will allow for the Nursery School and Barnardos Children Centre to stay on site in their current locations ( Brent Property Services are currently discussing the future use of one specific room with Barnardo’s and the SK Trust). The Granville Kitchen and Otherwise Club will enter into arrangements with the South Kilburn Trust for the space they use and will use within the proposed Enterprise & Community Hub, but to date this is expected to be achievable.

3.5The project team are due to have appointed Lead Architect and consultants to develop the design by the date of this Cabinet meeting.

3.6The project is being managed by Brent officers and as such will abide by the LA's financial regulations and standing orders in purchasing, tendering and contracting matters.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Phase 1 Building Project at the Granville Centre: Approval to Tender Works ContractReport 121 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
MB
Councillor Muhammed ButtChair, present
MM
Councillor Margaret McLennanVice-Chair, present
HF
Councillor Harbi FarahCommittee Member, present
KH
Councillor Krupesh HiraniCommittee Member, present
TM
Councillor Tom MillerCommittee Member, present
MP
Councillor Mili PatelCommittee Member, present
ES
Councillor Eleanor SouthwoodCommittee Member, present
ST
Councillor Shama TatlerCommittee Member, present
SC
Councillor Shafique ChoudharyCommittee Member, in attendance
AH
Councillor Aisha Hoda-BennCommittee Member, in attendance
KS
Councillor Ketan ShethCommittee Member, in attendance

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies