CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Brent
Audit Advisory Committee, Wednesday 20 September 2017 at 6.30pm

Internal Audit and Counter Fraud Progress Report for the period 1 April - 31 August 2017

Noted Finance 1 paper

Audit Advisory Committee noted this item on Wednesday 20 September 2017. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED that the progress made in delivering the 2017/2018 Internal Audit Plan and the counter fraud work in the period 1 April – 31 August 2017, be noted.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Audit Advisory Committee

Summary

1.1This report provides an update on the progress against the internal audit plan for the period 1 April 2016 to 31 August 2017. The appendix to the report also summarises those audits from the 2016/17 plan which have been finalised since the last meeting of the Committee. The report also provides a summary of counter fraud work for the first quarter of 2017/18.

Recommendations

2.1That the Audit Advisory Committee notes the progress made in delivering the 2017/18 Internal Audit Plan and the counter fraud work in the period of the report.

3. Detail

3.1The Internal Audit Plan for 2017/18 initially comprised 62 audits.

• Much of the work of the first quarter of the year focused on the completion of the 2016/17 plan. A summary of reports finalised during the first quarter relating to last year’s plan is set out in Appendix 1. The 2016/17 plan is now complete with the exception of finalising one school report.

3.2The key points to note with regards to progress for the current year are: • Ten reports from the 2016/17 audit plan have been finalised since the last meeting of the Committee. Four had “reasonable” assurance opinions; three had “limited” assurance opinions and the remaining three were ‘non assurance’ reviews. Details are included in Appendix 1 of this report. • There were sixty two audit projects included within the agreed 2017/18 plan (excluding follow up and advisory work). Work has commenced on eleven of these. • The annual audit plan is necessarily a flexible document to meet the changing risks, issues and management requests that occur in year. Since the plan was approved we have, where appropriate, made amendments to the plan including: amalgamating certain reviews, ceasing work at scoping stage when the control environment became more fully understood, and removing reviews which were deemed low risk. Additionally, some audits have been removed or deferred at the request of management - either as a result of planned changes to services or because of other external consultancy work being undertaken during the current financial year. Table 2 below has the list of audits removed from the plan and the reasons for doing so. • Seven audits have been added to the plan. Three are audits which were deferred from 2016/17 and the remaining four have been added as replacements for audits removed from the original plan at the request of management. See table 3 below for the list of audits added to the plan. • Four audits have been delayed at the request of management. Details of the audits which have been delayed are set out in Table 4 below. • Three audits from the 2017/18 plan have been completed to draft or final stage. Only one of the audits has an assurance opinion associated with it (limited assurance in this case). The remaining two relate to consultancy work and a certification of accounts which do not have an assurance ratings attached.

Table 1 – Summary of Audits Completed Since last audit report

Total Substantial Reasonable Limited None Number of Non Assurance Audits Total l Completed

Finals - 4 3 - 5 12 Draft - - 1 - - 1 Total - 4 4 - 5 13

Table 2 – Audits Removed from the Agreed Plan

Audit Reason Grants To Voluntary Audit in this area was carried out in Organisations 2016/17. A ‘reasonable assurance’ rating was given.

Complaints/FOIs/Members Considered to be low risk and Enquiries managed corporately.

Employee Loans To be carried out as a pro-active piece of work by the Investigations team

Access Management To be combined with IT Security

IT Performance Management Removed on the basis of previous coverage in 2016/17 as part of IT Governance & Third Party Management audit.

IT Governance Covered as part of GDPR Consultancy

Technological Development of Removed at the request of systems and processes to management support delivery of services

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit and Counter Fraud Progress Report for the period 1 April: 31 August 2017Report 259 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
DE
David EwartChair, present
MA
Councillor M Aslam ChoudryVice-Chair, present
JD
Councillor Joel DavidsonCommittee Member, present
LD
Councillor Liz DixonCommittee Member, absent
KN
Councillor Kana NaheerathanCommittee Member, apologies
NN
Councillor Neil NervaCommittee Member, apologies, sent representative
ES
Eugene SullivanCommittee Member, present
LM
Councillor Lloyd McLeishAlternate, present as substitute

On this subject at Brent

Search all
  1. Internal Audit and Counter Fraud Progress Report for the period 1 April - 31 August 2017This decision
  2. Internal Audit Interim Report 2025-26 - AddendumNoted
  3. Review of Internal Audit External Quality Assessment OutcomesNoted
  4. Internal Audit Interim Report 2022-23Noted
  5. Internal Audit 2021-22 Annual Report - Addendum ReportNoted
  6. Draft Internal Audit Strategic Plan and Counter Fraud Plan for 2022/23Approved

More from Brent Audit Advisory Committee

All decisions
MeetingDecisionOutcome
10 Jan 2018 Minutes of the previous meetingIt was RESOLVED that the minutes of the previous meeting, held on 5 December 2017, be approved as an accurate record. Approved Open
10 Jan 2018 Objections to the Accounts Regarding the Payment to the Council's Former HR DirectorRESOLVED that: (i) The contents of the Objections to the Accounts Regarding the Payment to the Council’s Former HR Di... Noted Open
10 Jan 2018 Emergency Preparedness Task Group ReportIt was agreed that the topic would be revised in six months time. RESOLVED that: (i) The contents of the Emergency Pr... Agreed Open
10 Jan 2018 External Audit Progress Report and External Audit Plan 2017/18RESOLVED that: (i) The contents of the External Audit Progress Report, be noted; and (ii) The discussion on the Exter... Noted Open
10 Jan 2018 Order of BusinessRESOLVED that Agenda items 10 and 11 be discussed together. Decided Open