West London Economic Prosperity Board noted this item on Tuesday 21 November 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED : (1) to note overall progress on the project achieved to date; (2) to note the outline programme of activity and project plan identified to move the project forward as detailed in sections 2 and 3 of the report, along with the key stakeholders at national regional and local level that would need to continue to be ... view the full minutes text for item 7.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
21 November 2017 Title Orbital Rail in West London Report of Amar Dave, LB Brent
Wards All
Status Public
Urgent No APPENDIX 1: Summary of “GRIP” approach to delivering rail Enclosures projects APPENDIX 2: West London Orbital rail kay facts Luke Ward, Head of Growth, Employment and Skills, West Officer Contact Details London Alliance, [email protected]
Summary This report provides the Board with an update on work relating to the West London Orbital rail line. It sets out next steps, an indicative project plan and governance arrangements for taking the scheme to construction and delivery promptly, should it proceed to the next stage.
Recommendations The Board is asked to: 1) NOTE overall progress on the project and IDENTIFY any additional actions or activities not already included within sections 2 and 3. 2) IDENTIFY any stakeholders at national, London or local level who will need to be engaged with any future engagement activity associated with the project. 3) COMMENT on the project plan set out in section four of the report
1. WHY THIS REPORT IS NEEDED
The West London Economic Prosperity Board (WLEPB) has previously identified the West London Orbital (WLO) rail line as a scheme of shared priority. It has agreed that progress and next steps relating to the project be a standing item on its agenda, as suggested by the Deputy Mayor for Transport during their meeting with her over summer 2017. There is, at present, a range of activity being undertaken in relation to the scheme and this report provides the Board with an opportunity to comment on and shape this work ahead of the expected publication of the final Mayor’s Transport Strategy (MTS) in early 2018.
The intention is that, subject to the MTS containing the required references to the WLO, the momentum this project has will allow the initiation of the delivery phase of the project relatively quickly. If the MTS does not explicitly support the WLO proposition then the current body of work completed to date would nonetheless allow West London boroughs to present a “shovel ready” infrastructure project to London and national decision makers if and when the time is right.
FIGURE 1: Route of the line
2. MAIN BODY This remainder of this report is divided into a number of sections, covering:
- Summary of work undertaken to date - Immediate next steps between now and late 2017 - Activity required from early 2018 onwards (should the project continue) - Notional project plan for the delivery of the line - Risks, Issues, Challenges - Next steps
2.1Summary of work undertaken to date:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting on Wednesday 20 September 2018 be approved as a correct record.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.