Quietway – Phase 2: Wembley Park to Harrow Weald

Agreed Executive 3 papers

Cabinet agreed this item on Monday 11 December 2017. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

RESOLVED that: 18.1 The route of the proposed Quietway through Brent be agreed, and it be noted that the scheme is to be continued to detailed design and consultation; and 18.2 The Head of Highways and Infrastructure in consultation with the Lead Member for Environment, be authorised to undertake any necessary statutory and non-statutory consultation and consider any objections or representations regarding the proposed Quietway route and interventions. If there are no objections or representations, or the Head of Highways and Infrastructure in consultation with the Lead Member for Environment considers the objections or representations are groundless or insignificant, the Head of Highways and Infrastructure in consultation with the Lead Member for Environment be authorised to deliver the scheme. Otherwise, the Head of Highways and Infrastructure in consultation with the Lead Member for Environment be authorised to refer objections or representations to the Cabinet for further consideration.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report introduces the proposed phase 2 Quietway cycle route from Wembley Park to Harrow Weald. This includes two spurs: one to Wembley Central station; and the second along Churchill Avenue to Kenton Road. The programme is at an early stage with only an indicative route, passing through the central and northern parts of the borough.

1.2Quietways are important as they provide a network of routes on safer, lower- traffic back streets, aimed at new and less confident cyclists and the proposed phase 2 route from Wembley Park to Harrow Weald forms part of the wider cycle network outlined in the Brent Cycle Strategy 2016 – 2021.

1.3Seven Quietway routes identified in the pilot phase are being implemented, including one from Regent’s Park to Gladstone Park, which will benefit Brent residents.

1.4The Quietway programme has evolved to include improvements for pedestrians as well as cyclists. Implementation will involve improvements to junctions and signage to make cycling and walking safer. 2.0 Recommendation(s)

2.1That Cabinet:

2.1.1 Agrees the route of the proposed Quietway through Brent and for the scheme to be continued to detailed design and consultation.

2.1.2 Authorises the Head of Highways and Infrastructure in consultation with the Lead Member for Environment to undertake any necessary statutory and non-statutory consultation and consider any objections or representations regarding the proposed Quietway route and interventions. If there are no objections or representations, or the Head of Highways and Infrastructure in consultation with the Lead Member for Environment considers the objections or representations are groundless or insignificant, the Head of Highways and Infrastructure in consultation with the Lead Member for Environment is authorised to deliver the scheme. Otherwise, the Head of Highways and Infrastructure in consultation with the Lead Member for Environment is authorised to refer objections or representations to the Cabinet for further consideration.

3.0Detail

3.1Phase 2 of the Quietway programme is now underway and a route is proposed to link Wembley Park and Harrow Weald. The section from Wembley Park to Northwick would run through Brent.

3.2Quietways are a ten year, £120m programme and part of the former Mayor’s Cycling Vision to provide a network of routes on safer, lower-traffic back streets, aimed at new and less confident cyclists. They are routes where people will want to cycle, by providing direct and comfortable journeys to key destinations across London, using parks and green spaces where suitable.

3.3Transport for London (TfL) asked boroughs to identify potential future routes for cycling. This long list was prioritised by TfL using their criteria and the Quietway network for the duration of the Quietway programme was established. The first seven routes selected by TfL formed part of the Quietway pilot programme, and subsequently further additional routes forming the London-wide Quietway network have been chosen for progression as part of phase 2.

3.4As part of the pilot programme, both Quietway 1: Waterloo to Greenwich and Quietway 3: Regent’s Park to Gladstone Park are complete with Quietway 2: Bloomsbury to Walthamstow due to open in autumn 2017. TfL are continuing work to implement the remaining four Quietway pilot routes, most of which are set to be complete by early 2018:  Quietway 4: Clapham Common to Wimbledon  Quietway 5: Waterloo to Norbury  Quietway 6: Mile End to Barkingside  Quietway 7:Elephant & Castle to Crystal Palace

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Route AlignmentAppendix A 637 KB Download
PDF
Equality AnalysisAppendix B 119 KB Download
PDF
Quietway: Phase 2: Wembley Park to Harrow WealdReport 249 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
HF
Councillor Harbi Farah Lead Member for Housing and Welfare ReformCommittee Member, present
KH
Councillor Krupesh Hirani Lead Member for Community WellbeingCommittee Member, present
TM
Councillor Tom Miller Lead Member for Stronger CommunitiesCommittee Member, present
MP
Councillor Mili Patel Lead Member for Children and Young PeopleCommittee Member, apologies
ES
Councillor Eleanor Southwood Lead Member for EnvironmentCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Growth, Employment and SkillsCommittee Member, present

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open