CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Brent
Cabinet, Monday 15 January 2018 at 6.00pm

Air Quality Improvement Measures: Electric Vehicle Charging Infrastructure

Approved Executive 4 papers

Cabinet approved this item on Monday 15 January 2018. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

RESOLVED that: 16.1 Brent Council’s continued involvement in the GULCS for the Rapid Charging Infrastructure Project and the project to provide on-street electric vehicle charge points in residential locations, be approved; 16.2 Brent Council’s participation in a collaborative procurement led by Transport for London (TfL) and London Councils using the Crown Commercial Services Traffic Management Technology 2 Framework Agreement in order to select a single supplier to install, manage and maintain electric vehicle charge points in lamp columns in Brent, be approved; 16.3 The collaborative procurement exercise detailed in 15.2 above be exempt from the normal requirements of Brent Council’s Contract Standing Orders and Financial Regulations for good operational and/or financial reasons in accordance with the Contract Standing Order 84(a) and 85(c) for the reasons detailed in paragraphs 6.8 and 11.2.3 of the report, be agreed; 16.4 The provision and installation of electric vehicle charge points in lamp columns to serve residents with no access to off-street parking now and in the future (subject to funding), be authorised in principle; 16.5 The Strategic Director Regeneration and Environment, in consultation with the Lead Member for Environment, be authorised to undertake any necessary statutory and non-statutory consultations and consider any objections or representations regarding the installation of rapid charge points at on and off-street locations in Brent now and in the future (subject to funding), with consultation results referred to Highways Committee to determine the outcome of the responses; 16.6 The intention to commence a procurement using a mini-competition under the TfL Rapid Charge Point Concession Framework for the installation of electric vehicle rapid charge points, be noted; and 16.7 Authority to award contracts following mini-competitions under the frameworks detailed in 15.2 and 15.6 above to the successful bidders of the Rapid Charging Infrastructure Project and the project to provide on-street electric vehicle charge points in residential locations for the reasons detailed in paragraphs 11.1.8 and 11.2.6, be delegated to the Strategic Director Regeneration and Environment, in consultation with the Lead Member for Environment.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report seeks to inform and obtain approval from Cabinet for Brent’s involvement in two projects that will provide new charging infrastructure for electric vehicles in Brent: The Rapid Charging Infrastructure Project and a project to deliver on-street residential charge points in lamp columns. Both projects require entry into supplier contracts. The report will also provide an update on progress with Source London infrastructure installation.

1.2The Brent Long Term Transport Strategy 2017 – 2035, Planning Policy Guidance, the London Plan and Brent Development Management Policies all seek improvements in air quality.

1.3Supporting greater use of electric vehicles to contribute to meeting these objectives requires access by owners to a reliable charging infrastructure. This includes charge points in residential streets to allow residents who don’t have access to off-street parking to charge an electric vehicle overnight. It also includes access to ‘rapid charge points’ which, due to their ability to charge an electric vehicle in 30 minutes, support the taxi and private hire trades to use electric vehicles. This charging infrastructure is required in addition to traditional freestanding charge points which the Council is currently installing as part of the Source London network in contract with BluePointLondon Ltd. 2.0 Recommendations

That Cabinet:

2.1Approves Brent Council’s continued involvement in the GULCS for the Rapid Charging Infrastructure Project and the project to provide on-street electric vehicle charge points in residential locations;

2.2Approves Brent Council’s participation in a collaborative procurement led by Transport for London (TfL) and London Councils using the Crown Commercial Services Traffic Management Technology 2 Framework Agreement in order to select a single supplier to install, manage and maintain electric vehicle charge points in lamp columns in Brent;

2.3Agrees that the collaborative procurement exercise detailed in 2.2 above be exempt from the normal requirements of Brent Council’s Contract Standing Orders and Financial Regulations for good operational and/or financial reasons in accordance with the Contract Standing Order 84(a) and 85(c) for the reasons detailed in paragraphs 6.8 and 11.2.3;

2.4Authorises in principle the provision and installation of electric vehicle charge points in lamp columns to serve residents with no access to off-street parking now and in the future (subject to funding);

2.5Authorises the Strategic Director Regeneration and Environment, in consultation with the Lead Member for Environment, to undertake any necessary statutory and non-statutory consultations and consider any objections or representations regarding the installation of rapid charge points at on and off-street locations in Brent now and in the future (subject to funding), with consultation results referred to Highways Committee to determine the outcome of the responses;

2.6Notes the intention to commence a procurement using a mini-competition under the TfL Rapid Charge Point Concession Framework for the installation of electric vehicle rapid charge points; and

2.7Delegates authority to the Strategic Director Regeneration and Environment, in consultation with the Lead Member for Environment, to award contracts following mini-competitions under the frameworks detailed in 2.2 and 2.6 above to the successful bidders of the Rapid Charging Infrastructure Project and the project to provide on-street electric vehicle charge points in residential locations for the reasons detailed in paragraph 11.1.8 and 11.2.6.

3.0Detail

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Air Quality Improvement Measures: Electric Vehicle Charging InfrastructureReport 284 KB DownloadRead as text
PDF
Rapid Charge Point DesignAppendix A 94 KB Download
PDF
Potential Rapid Charge Point Locations in BrentAppendix B 529 KB Download
PDF
Equality AnalysisAppendix C 281 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
HF
Councillor Harbi Farah Lead Member for Housing and Welfare ReformCommittee Member, present
KH
Councillor Krupesh Hirani Lead Member for Community WellbeingCommittee Member, present
TM
Councillor Tom Miller Lead Member for Stronger CommunitiesCommittee Member, present
MP
Councillor Mili Patel Lead Member for Children and Young PeopleCommittee Member, present
ES
Councillor Eleanor Southwood Lead Member for EnvironmentCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Growth, Employment and SkillsCommittee Member, present
RM
Councillor Roxanne MashariCommittee Member, in attendance

On this subject at Brent

Search all
  1. Air Quality Improvement Measures: Electric Vehicle Charging InfrastructureThis decision
  2. Air Quality Action Plan AdoptionNoted
  3. Air Quality Task Group Scrutiny Report and RecommendationsAgreed
  4. Executive Response to the recommendations from the Air Quality Scrutiny Task Group and recommendations of the Resources and Public Realm Scrutiny CommitteeNoted
  5. Resources and Public Realm Committee Task Group on Air QualityNoted
  6. Air Quality Task Group ReportNoted

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies