It was RESOLVED :- ( i ) That the responses to the public consultations undertaken in the borough between 28 th November 2017 and 12 th December 2017 be noted; (ii) that it be agreed to proceed with the recommendations as set out in paragraphs 3.9 to 3.17 of the report from the Strategic Director of Regeneration and Environment, and to progress schemes that have majority support to statutory consultation stage for implementation of Traffic Management Orders; (iii) that the Head of Highways and Infrastructure be authorised, in consultation with the Lead Member for Environment, to consider any objections or representations arising from the statutory consultation process for making Traffic Management Orders in relation to the proposed schemes at Alpine House, Robson Avenue, Ealing Road and Controlled Parking Zones KG and GM, and implement proposed changes if there are no substantial objections, or otherwise refer objections or representations to the Highway Committee for further consideration; (iv) that the current status and further work necessary to deliver the approved Parking Management Review programme be noted; (v) that it be noted that a report on the current and anticipated future levels of demand for new CPZs, changes to existing CPZs and waiting and loading restrictions will be considered by Cabinet at the meeting on 12 th February 2018.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report provides Highways Committee with an update on the On-Street Parking Management Review programme of introducing new Controlled Parking Zones (CPZs) and reviewing existing CPZs, in response to petitions received from the community.
1.2It provides details of an analysis of the public consultation recently undertaken to gauge the community’s support for proposed changes as outlined in our Parking Management Review programme.
1.3The report also informs members of the programme status for the approved Parking Management Review programme. 2.0 Recommendation
2.1That Highways Committee notes the responses to the public consultations undertaken in the borough between 28th November 2017 and 12th December 2017.
2.2That Highways Committee agrees to proceed with the recommendations as set out in paragraphs 3.9 to 3.17 of this report, and to progress schemes that have majority support to statutory consultation stage for implementation of Traffic Management Orders.
2.3That Highways Committee authorises the Head of Highways and Infrastructure, in consultation with the Lead Member for Environment, to consider any objections or representations arising from the statutory consultation process for making Traffic Management Orders in relation to the proposed schemes at Alpine House, Robson Avenue, Ealing Road and Controlled Parking Zones KG and GM, and implement proposed changes if there are no substantial objections, or otherwise refer objections or representations to the Highway Committee for further consideration.
2.4That Highways Committee notes the current status and further work necessary to deliver the approved Parking Management Review programme.
2.5That Highways Committee notes that a report on the current and anticipated future levels of demand for new CPZs, changes to existing CPZs and waiting and loading restrictions will be considered by Cabinet at the meeting on 12th February 2018.
3.0Detail
3.1In recognition of an increase in public demand for parking management changes in the borough, Cabinet approved the report titled “On-Street Parking Management Review” at its meeting on 24th July 2017. This report provided details of an analysis of feedback from the public to identify levels of demand for changes and also a desktop analysis to identify areas, where there may be on- street parking pressures. It provided information on how areas where we receive numerous requests for changes, would be prioritised with the aim of introducing on-street parking controls that will benefit residents and businesses alike.
3.2Cabinet approved a programme for changes to on-street parking arrangements in prioritised areas, subject to public consultation and further approval by Highways Committee. Appendix A provides details of the approved 2017/18 On-Street Parking Management Review Programme.
3.3Parking stress surveys were carried out between 2nd October 2017 and 12th October 2017. These consisted of inspections of the existing parking measures and saturation of the on-street parking facilities in video a survey.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingIt was RESOLVED that the minutes of the previous meeting held on 27 June 2017 be approved as an accurate record of th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.