Resolved
It was RESOLVED : 11.1 That the execution of a variation agreement to Memorandum of Understanding be approved.
Cabinet agreed this item on Monday 12 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED : 11.1 That the execution of a variation agreement to Memorandum of Understanding be approved.
Cabinet 12 February 2018
Report from the Strategic Director of Resources
Northwick Park, One Public Estate - Update
Wards Affected: Northwick Park Key or Non-Key Decision: Non Key Open or Part/Fully Exempt: Open No. of Appendices: 2 Background Papers: None Gordon Cooper Project Manager Tel: 020 8937 1739 [email protected]
Sarah Chaudhry Contact Officers: Head of Property Tel: 020 8937 1705 [email protected]
Althea Loderick Strategic Director of Resources Tel: 020 89371564 [email protected]
1.0Vision
1.1This is an exciting, ambitious project where Brent leads a consortium of public sector landowning partners, dissolving ownership boundaries and working collaboratively to deliver a residential led regeneration of the area.
1.2There is a collective vison amongst partners to make Northwick Park a landmark destination of choice, delivering a modernised university hospital, central hubs serving local people, improved infrastructure and transport connections, a common energy strategy, shared services and facilities, and reduced running costs.
1.3Key objectives for Brent are; more good quality affordable homes, more school places, growth, increased revenue from homes and businesses and generation of growth and skills opportunities within the borough. 2.0 Purpose of the Report
2.1The purpose of the report is to update Cabinet on Northwick Park One Public Estate initiative, and approve execution of a variation agreement to the existing Memorandum of Understanding, in order for the partners to deliver the vision.
3.0Recommendation(s)
3.1Approve execution of variation agreement to Memorandum of Understanding.
4.0Detail
4.1Brent received grant funding from the One Public Estate Office (OPE), to lead a consortium of land owning public sector partners in examining the potential regeneration of adjacent landholdings at Northwick Park. The other partners are London North West University Hospital (LNWUH), The University of Westminster and Network Homes Ltd.
4.2The partners have dissolved boundaries of individual ownership and worked collaboratively to produce proposals with a far greater vision than could be achieved individually. Supported by development and planning consultants, GVA, the partners have prepared a feasibility/capacity study, which outlines the next steps required for the project. (Appendix A)
4.3The four partners executed a Memorandum of Understanding in August 2017. This outlines common and individual objectives for the project, principles of collaboration, Governance and partnership values. Taking into account likely next steps, a variation to the MOU is attached. (Appendix B), to give a legal framework for partners to progress the proposals.
4.4The feasibility study looked at site constraints and development opportunities. It considered option appraisals, and outlined planning strategies. The report considered high level financial viabilities and commercial considerations of partners, and an analysis of delivery strategies. Finally it considered phasing and outlined next steps.
4.5The next steps outlined in the report are broadly;
Prepare a planning brief for the site. (Feb 18- Dec 18) Commission further transport studies. (Feb 18- Dec 18) Maximise OPE funding. (ongoing) Commission energy feasibility studies. (Jan 18- July 18) Consider potential for inclusion of a secondary school. (Jan 18 – July 18) Network Homes Ltd and LNWUH to conclude negotiations on NHS owned land. (June 2018)
Timescales are indicative. 4.6 Two agreements will follow from the next steps;
An infrastructure agreement between all four partners, dealing with delivery of infrastructure of the entire site. A joint venture/development agreement between The London Borough of Brent and Network Homes Ltd.
4.7The next steps and associated agreements have been discussed with partners and a variation agreement developed. (Appendix B). This incorporates the next steps and associated agreements outlined above, with responsibilities and approximate costs.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
GVA Feasability StudyAppendix A | 7.7 MB | Download |
PDF |
Memorandum of Understanding Variation AgreementAppendix B | 81 KB | Download |
PDF |
Northwick Park One Public Estate UpdateReport | 95 KB | DownloadRead as text |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.