Financing Purchase of Residential Block by i4B or First Wave Housing

Approved Executive 1 paper

Cabinet approved this item on Monday 14 October 2019. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

i) Cabinet approved an equity investment in the existing i4B street purchases programme by purchasing i4B shares up to a maximum of £21.8m for the first 300 properties, as agreed in principle by Cabinet in February 2019. ii) Cabinet agreed for new loan facilities of up to £110.5m be made available to i4B and First Wave Housing for phase 2 of the PRS purchase programme, including the potential Quintain block purchase. iii) Cabinet agreed that drawdowns on the loan facility to finance the potential Quintain block E01 02 purchase would be conditional on the negotiation of points as described in paragraphs 3.15 and 3.16 below. iv) Cabinet delegated to the Director of Finance, in consultation with the Deputy Leader, authority to determine whether the conditions set out in paragraphs 3.15 and 3.16 below have been discharged. v) Cabinet agreed for equity investment of up to £22.1m for phase 2 of the PRS purchase programme, including by purchasing i4B shares up to a maximum of £22.1m. vi) Cabinet agreed to delegate the precise terms and mix of loan and equity funding for phase 2 of the PRS purchase programme to the Director of Finance, such that the total funding for phase 2 of the PRS purchase programme does not exceed £110.5m. vii) Cabinet noted the new details of the potential block purchase from Quintain , together with the financial and legal implications. i) Cabinet approved an equity investment in the existing i4B street purchases programme by purchasing i4B shares up to a maximum of £21.8m for the first 300 properties, as agreed in principle by Cabinet in February 2019. ii) Cabinet agreed for new loan facilities of up to £110.5m be made available to i4B and First Wave Housing for phase 2 of the PRS purchase programme, including the potential Quintain block purchase. iii) Cabinet agreed that drawdowns on the loan facility to finance the potential Quintain block E01 02 purchase would be conditional on the negotiation of points as described in paragraphs 3.15 and 3.16 below. iv) Cabinet delegated to the Director of Finance, in consultation with the Deputy Leader, the authority to determine whether the conditions set out in paragraphs 3.15 and 3.16 below have been discharged. v) Cabinet agreed for equity investment of up to £22.1m for phase 2 of the PRS purchase programme, including by purchasing i4B shares up to a maximum of £22.1m. vi) Cabinet agreed to delegate the precise terms and mix of loan and equity funding for phase 2 of the PRS purchase programme to the Director of Finance, such that the total funding for phase 2 of the PRS purchase programme does not exceed £110.5m. vii) Cabinet noted the new details of the potential block purchase from Quintain , together with the financial and legal implications.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report requests Cabinet approval of equity investment in i4B’s existing street purchases programme, as agreed in principle by Cabinet when approving i4B’s business plan in February 2019.

1.2i4B or First Wave Housing is intending to purchase a block of 153 key worker accommodation apartments in Wembley Park from Quintain. This paper is seeking approval of the Council to fund this transaction by a mix of loan and equity, subject to the negotiation of some outstanding points as detailed in paragraphs 3.15 and 3.16.

1.3There is also a request for the decision on the mix of the loan amount and equity to be delegated to the Director of Finance.

Recommendations

2.1Cabinet approves an equity investment in the existing i4B street purchases programme by purchasing i4B shares up to a maximum of £21.8m for the first 300 properties, as agreed in principle by Cabinet in February 2019.

2.2Cabinet agrees for new loan facilities of up to £110.5m to be made available to i4B and First Wave Housing for phase 2 of the PRS purchase programme, including the potential Quintain block purchase.

2.3Cabinet agrees that drawdowns on the loan facility to finance the potential Quintain block E01 02 purchase would be conditional on the negotiation of points as described in paragraphs 3.15 and 3.16 below.

2.4Cabinet delegates to the Director of Finance, in consultation with the Deputy Leader, authority to determine whether the conditions set out in paragraphs 3.15 and 3.16 below have been discharged.

2.5Cabinet agrees for equity investment of up to £22.1m for phase 2 of the PRS purchase programme, including by purchasing i4B shares up to a maximum of £22.1m.

2.6Cabinet agrees to delegate the precise terms and mix of loan and equity funding for phase 2 of the PRS purchase programme to the Director of Finance, such that the total funding for phase 2 of the PRS purchase programme does not exceed £110.5m.

2.7Cabinet notes the new details of the potential block purchase from Quintain, together with the financial and legal implications.

3.0Detail

i4B Business Plan

3.1In November 2016 Cabinet agreed to establish a wholly owned investment company, i4B Holdings Limited. This company was set up to own and manage private rented sector properties in order to support the Council’s homelessness agenda.

3.2Cabinet approved the i4B Business Plan 2019/20 in February 2019. This included:

(i) increasing the budget for PRS Phase 1 from £103.5m to £109m; (ii) changing the PRS Phase 2 budget from £116m to £110.5m; (iii) total agreed funding for i4B remaining the same at £254.5m.

3.3The i4B Board proposed that the proportion of properties in Brent and Greater London increased from the initial business plan. The realignment of funding reflected the higher average property cost within Brent compared to the Home Counties.

3.4This paper requests authority to make this funding available to i4B, with additional flexibility to make some of it available to First Wave Housing (FWH) instead. This is because, as a registered provider of social housing, FWH is able to attract grant funding from the Greater London Authority, for example for key worker housing. 3.5 Phase 2 includes the potential purchase of a block to be used as key worker housing.

Key Worker Housing

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financing Purchase of Residential Block by i4B or First Wave HousingReport 102 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 17 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MM
Councillor Margaret McLennan Deputy LeaderVice-Chair, present
AA
Councillor Amer Agha MB BS, MSc, PHCM Lead Member for Schools, Employment and SkillsCommittee Member, present
HF
Councillor Harbi Farah Lead Member for Adult Social CareCommittee Member, present
KH
Councillor Krupesh Hirani Lead Member for Public Health, Culture and LeisureCommittee Member, present
TM
Councillor Tom Miller Lead Member for Community Safety & EngagementCommittee Member, present
MP
Councillor Mili Patel Lead Member for Children's Safeguarding, Early Help and Social CareCommittee Member, present
KS
Councillor Krupa Sheth Lead Member for EnvironmentCommittee Member, present
ES
Councillor Eleanor Southwood Lead Member for Housing and Welfare ReformCommittee Member, present
ST
Councillor Shama Tatler Lead Member for Regeneration, Property and PlanningCommittee Member, present
HO
Hakeem OsinaikeCouncil Staff, expected
KS
Councillor Ketan ShethGuest, in attendance

All 17 on the meeting page

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open